Central Virginia
Virginia Passenger Rail Authority
Community Advisory Group Meeting #3 - Arlington and Alexandria Projects 1/30/2026
Auto-scroll
Community Advisory Group Meeting #3 - Arlington and Alexandria Projects
1/30/2026
SPEAKER_00
00:01:33
I just realized I was on mute.
SPEAKER_06
00:01:35
Good afternoon.
00:01:36
Welcome everybody.
00:01:38
Let's get started.
00:01:40
Good afternoon and welcome to the third VPRA and VRE community advisory group meeting with a focus on Arlington and Alexandria.
00:01:49
As a reminder, our community advisory groups are designed to maintain ongoing coordination and communication with leaders in our project areas.
00:01:58
This includes residential groups, business groups,
00:02:01
regional organizations, advocacy groups, elected officials and staffers, and others.
00:02:07
And we meet virtually on a quarterly basis for project updates and to hear your thoughts.
00:02:12
Today's agenda, we can go ahead to the next slide.
00:02:18
Today's agenda will cover all of our VPRA and VRE projects in Arlington and Alexandria, including Long Bridge, Alexandria Fourth Track, Crystal City Station, Alexandria Station, and the King and Commonwealth Bridges.
00:02:33
We will also share updates on the latest Amtrak and VRE service changes associated with Long Bridge project construction.
00:02:40
So let's start by introducing our team that's presenting today.
00:02:44
Next slide, please.
00:02:46
Let's start in the upper left and go across the top and then across the bottom.
00:02:49
Naomi?
SPEAKER_14
00:02:52
Good afternoon.
00:02:52
My name is Naomi Klein.
00:02:54
I am the Permitting and Stakeholder Manager for the Long Bridge Project.
SPEAKER_06
00:03:03
Jeremy?
SPEAKER_10
00:03:05
Hi, Jeremy Lattimer, Director of Rail Services, Virginia Passenger Rail Authority.
SPEAKER_06
00:03:15
Brian?
SPEAKER_12
00:03:17
Good afternoon, I'm Brian Bries, Project Manager for Long Bridge Rail Partners here on the Long Bridge South Project.
SPEAKER_06
00:03:24
Thank you.
00:03:24
And I'm Meredith Judy.
00:03:26
I'm the Community Affairs Manager for Virginia Passenger Rail Authority.
SPEAKER_02
00:03:33
Sarah.
00:03:34
Good afternoon.
00:03:35
I am Sarah Hoover.
00:03:36
I am the VPRA Project Manager for Alexandria Fourth Track.
SPEAKER_13
00:03:44
Good afternoon.
00:03:45
I'm Jason Skofy.
00:03:46
I'm with the Construction Management Team for the Alexandria Station and King and Commonwealth Bridge Project.
SPEAKER_05
00:03:53
Hi, everyone.
00:03:54
My name is Lindsay Martin.
00:03:55
I am VRE's Public Affairs Administrator.
SPEAKER_11
00:04:00
Good afternoon, everyone.
00:04:01
I'm Adam Olcovic.
00:04:02
I'm the Deputy Program Manager of Construction for CSX on the PRB program.
SPEAKER_06
00:04:10
Fabulous.
00:04:11
Thank you to our presenters for being here.
00:04:14
Let's start with Naomi.
SPEAKER_14
00:04:17
Thanks, Meredith, for that introduction.
00:04:20
So I'm going to briefly talk about the Virginia Passenger Rail Authority, who we are, and then I am going to give you some background information about the Long Bridge project.
00:04:31
So the Virginia Passenger Rail Authority, we are an independent state authority.
00:04:35
We were created in 2020, so we're relatively new by the Virginia General Assembly.
00:04:41
Our responsibility is to expand and promote passenger and commuter rail.
00:04:45
So we're not a rail operator.
00:04:47
We don't run trains like VRE Amtrak or CSX does.
00:04:52
but rather you can think of us as the entity that owns the rail tracks and builds projects that expand the rail tracks so that we can have more passenger rail and separate passenger from freight rail.
SPEAKER_03
00:05:07
Next slide please.
SPEAKER_14
00:05:11
So our purpose is to increase capacity, which means more passenger rail trains running.
00:05:18
And so think of, for example, VRE being able to run trains on nights and weekends.
00:05:23
Our other goals are to improve efficiency and improve reliability.
00:05:28
So not just run more trains, but also run more trains that are running on time more often.
00:05:33
Next slide, please.
00:05:38
So TRV stands for Transforming Rail in Virginia and that is a program of many projects that you can see all the way between Union Station and Richmond, Virginia that will expand passenger rail.
00:05:53
We had a landmark deal with CSX, we being the state of Virginia, back in 2019 that allowed us to acquire right-of-way
00:06:03
Next to the privately owned freight rail tracks that would allow us to complete all of these projects that you see listed on the right hand side to be able to increase passenger rail by adding additional tracks.
00:06:18
What you can see is that we have 11 projects and an agreement with CSX that in completing these projects, it unlocks new service, two new Amtrak and three new VRE round trips, including VRE late night and weekend service and then additionally future capacity for even more Amtrak and VRE trips.
SPEAKER_01
00:06:40
Next slide, please.
SPEAKER_14
00:06:43
So the economic impact of transforming rail in Virginia, we are adding nearly 30,000 jobs during construction and hundreds of jobs in the operations of these new projects, these new tracks post-construction.
00:06:59
That means billions of dollars that are paid to workers through the construction and operation of these projects and millions of dollars that will be put back into the economy.
00:07:11
promoting future spending and building up the U.S. economy.
00:07:17
Next slide, please.
00:07:21
So this just shows the Virginia passenger rail network, where it all goes to, the existing tracks, and then future tracks as well.
00:07:31
So there are four state-supported Amtrak routes.
00:07:33
You can see on the right-hand side where those routes go to.
00:07:37
And then five Amtrak long-distance round trips.
00:07:39
So when you're on an Amtrak train often you think, oh this is Amtrak, but actually the state of Virginia pays for state-supported routes, meaning that that funding is coming from Virginia to ensure that we have an interconnected system and that residents of Virginia and visitors are able to get to all of our major destination locations.
00:08:03
And one North Carolina state-supported round trip
00:08:07
There's also 32 trains a day from VRE that are split between Manassas and Fredericksburg.
SPEAKER_03
00:08:17
Next slide please.
SPEAKER_14
00:08:19
So now we're going to talk about the Long Bridge Project, the project that I specifically work on.
00:08:25
And again, the goal of this project is to separate passenger from freight rail so we can introduce better rail service.
00:08:33
The Long Bridge is a huge bottleneck on the East Coast.
00:08:38
South of the Long Bridge, there are three tracks, which we are expanding to four tracks through the Alexandria Fourth Track Project, which you will hear about after we talk about Long Bridge.
00:08:49
North of the Long Bridge project is the L'Enfant project.
00:08:53
And that's going to include both station improvement and the addition of a fourth track all the way up to Union Station.
00:09:00
And then when you get to Union Station, it's four tracks all the way up the Northeast corridor.
00:09:04
But right here where the Long Bridge project spans the Potomac River, it's only two tracks.
00:09:10
So what that means is all of the freight, all of the Amtrak passenger rail and the VRE passenger rail
00:09:17
have to cross on this two-track bridge.
00:09:20
So you end up with a huge bottleneck here where, you know, if you're getting your orange juice from Florida and it's coming up the East Coast, it has to go across this two-track bridge and compete with all these other types of rail.
00:09:33
So the existing Long Bridge is owned by CSX, it will continue to be owned and maintained by CSX, and then VPRA, the Virginia Passenger Rail Authority, will be building a new two-track bridge
00:09:46
next to the existing two-track bridge.
00:09:49
So we will be doubling that rail capacity.
00:09:51
So you'll have a four-track corridor from Alexandria, Virginia, about six miles away, all the way up the northeast corridor, including at Union Station.
00:10:03
So additionally, we will be adding a bike pedestrian bridge across the river to mitigate for impacts to parkland.
00:10:11
and then a new pedestrian bridge over Main Avenue in Washington, DC.
00:10:16
Next slide, please.
00:10:20
So, due to the size of the Long Bridge project, it has actually been split into two what we call packages for the purposes of construction.
00:10:29
That just means that there are two different contractors that are going to be building the project.
00:10:35
There is a south package, which you can see here in purple.
00:10:38
That includes everything in Virginia.
00:10:41
starting at just south of the Long Bridge Aquatic Center, spanning over the George Washington Memorial Parkway and the Mount Vernon Trail.
00:10:51
And then the construction of the bridge over the Potomac River, ending at the abutment in East Potomac Park, right where it meets the riverside.
00:11:01
And then it also includes the construction of the bike pedestrian bridge over the Potomac River.
00:11:07
That bike pedestrian bridge connects Long Bridge Park and the Mount Vernon Trail on the Virginia side with the bike lanes in East Potomac Park on the DC side.
00:11:21
We're here today to talk about the purple portion.
00:11:25
But the north package constructs everything in DC, basically starting at that same abutment at East Potomac Park on the Riverside going over I-395, over Ohio Drive, the Washington Channel, over Main Avenue.
00:11:42
through the Maryland Avenue overbuild on which you can see all those buildings on the right hand side and then up just south of L'Enfant Plaza.
00:11:50
The south package in purple is a design build and the north was a progressive design build model.
00:11:59
Both are estimated to start full construction in the middle of this year.
00:12:04
The north package is already engaged in some construction and pre-construction activities in the Washington Channel.
00:12:11
and the south package.
00:12:13
You may have seen us out in the water.
00:12:14
We're doing some geotechnical exploration work and then we're also building bulkheads that will allow us to access the water and I believe Brian from Long Bridge Rail Partners will be talking more about those construction efforts.
SPEAKER_03
00:12:28
Next slide please.
SPEAKER_14
00:12:32
Okay and I think now I am handing it over to Brian to talk about the construction activities in the Potomac River.
SPEAKER_12
00:12:39
Thank you, Naomi.
00:12:40
Again, my name is Brian Breese.
00:12:41
I'm the project manager for Long Bridge Rail Partners here on the south project.
00:12:46
Over the past several months, the majority of our efforts have been what we call scope validation activities.
00:12:55
Going out there, confirming the assumptions we're making in our design, confirming geotechnical conditions, geological conditions to inform our foundation design, things along those lines.
00:13:06
You've seen us out on the river.
00:13:08
We got out on the river sometime, I think, in June of last year.
00:13:12
We've been out there with cranes and drill rigs and boats kind of moving around on the water, doing some of those investigatory type activities.
00:13:24
More recently, we've started cutting trees down.
00:13:28
on the GWMP side of the river, on the Arlington County side of the river, which will, you know, basically generating our access points to the water.
00:13:39
And most recently here over the past week, week and a half, we've been starting to build our bulkhead construction as part of that access plan.
00:13:49
So you've seen trees coming down, you've seen some access points and construction entrances off of GWMP, things along those lines.
00:13:58
Moving forward a little bit, we still have some vibration monitoring equipment to install out on the existing piers.
00:14:06
That'll be ongoing for a period of months.
00:14:09
Again, the bulkhead construction.
00:14:10
We have water access points to build on both the Virginia side and the DC side, so you'll see us on both sides of the river.
00:14:18
Building those basically fingers that kind of jet out into the river a little bit and that allows us to walk our cranes on and off barges and things along those lines.
00:14:29
So obviously with the weather you know had a little setback here but you'll see us out there and that activity will be fairly continuous moving forward.
00:14:38
Test Pile Operations.
00:14:39
So as part of the scope validation, we still do have to do some test pile operations out on the water to inform our foundation design and that'll allow us to optimize our driven piles and things like that.
00:14:53
We'll talk a little bit in more detail about the test piles.
00:14:56
and I just want to touch on Mount Vernon Trail and again we'll talk about this in a little bit more detail but there's obviously an interaction at this point with the with the Mount Vernon Trail and our access point that has to be managed and again we'll talk a little bit more detail about that on a future slide here so next slide.
00:15:20
Thank you.
00:15:21
So getting into a little bit more detail on the test piles.
00:15:25
We have four test piles to do to inform our foundation design.
00:15:28
One on the Arlington side of the river, two in the river, and one on DC.
00:15:33
And again, basically that goes out there.
00:15:36
We do some testing on it.
00:15:38
We determine the capacity of the piles and that helps us optimize our permanent design for our permanent pile.
00:15:47
Part of what we're doing now, building those bulkheads.
00:15:49
Once we get those bulkheads done, we'll walk our cranes onto the water and we'll start those test pile operations.
00:15:56
They'll take two to three months to get done and we do expect them to complete here late first quarter, early second quarter of 2026 here.
00:16:08
As part of this operation, you're going to hear the hammering activities driving the pile into the ground.
00:16:15
You're going to hear some elevated noise levels like explosive sounds from the testing operations, things along those lines.
00:16:23
So, you know, don't be alarmed if you hear some loud booms out there on the water.
00:16:31
We do intend to send some informational materials out in regards to this as we get a little closer to doing that work.
00:16:38
And just to point out, all of our work on the river throughout the course of the job, we do intend to keep the navigational channel open.
00:16:47
At times, we'll have to shift it to the auxiliary channel if we have to occupy the current navigational channel, but there will always be a path through the job.
00:16:57
We will have
00:17:00
8 to Navigation out there, buoys, no wake zones, things along those lines to inform the boating public as to our operations as we go through.
00:17:09
Next slide please.
00:17:14
All right, we talked a little bit about this, the geotechnical borings in the river as part of our scope validation are complete.
00:17:22
We've done some other investigatory work out there.
00:17:24
We've had divers out there in the navigational channel inspecting the existing fender system underneath the Wamata Bridge as we have to tie into that fender system and other surveys to confirm the design, the measurements, the depths, things along those lines so we know what we're
00:17:44
from a constructability standpoint.
00:17:53
Here over the next week or so, you're going to see us start to occupy the loops, the interior of the loop ramps at the boundary channel interchange with 395.
00:18:04
We're going to occupy those as major staging areas for the job.
00:18:07
So we're going to have our office complexes in there.
00:18:11
You're going to see some trees come down within those loops.
00:18:15
And of course, there's minimal landscaping in there right now.
00:18:19
But we're going to have temporary lane closures coming off of those loop ramps.
00:18:23
to be able to get that work done.
00:18:26
And we do expect to get our trailers in there and occupy those loop ramps as staging areas, parking areas, over the next couple months.
00:18:35
We'll also be beginning to build access from the 395 ramp
00:18:42
down along the Aquatic Center in between the ramp to GWMP southbound and the Aquatic Center.
00:18:49
We're going to build an access road to the job down along there, so we'll be clearing trees to facilitate that access in between the GWMP and the Aquatic Center.
00:19:00
So motorists should plan for some minor impacts as we have to take lanes and shoulder closures in those areas to facilitate that work being done safely.
SPEAKER_08
00:19:12
Next slide please.
SPEAKER_12
00:19:15
Alright, Mount Vernon Trail.
00:19:18
So again, our current activities are directly adjacent to the Mount Vernon Trail and we have a lot of construction equipment and personnel that have to go back and forth on that trail.
00:19:31
So here in January, if you go out there now, you'll see signage out there that kind of warns the bicyclists and the pedestrians of that activity.
00:19:42
We'll have flaggers out there.
00:19:44
We will
00:19:45
Bikers and walkers should expect to have brief stops just to avoid that interaction between the construction equipment and the public.
00:19:57
We ask that everybody follow the posted signs and wait for our flaggers direction.
00:20:03
We want to really try to minimize that interaction.
00:20:07
We're going to try to schedule work off of peak hours as much as possible to avoid that interaction, but it's certainly going to happen.
00:20:17
Obviously, this time of year with the weather, the traffic out there is much diminished from what it's going to be in the summertime.
00:20:25
And then in the fall of 2026, and we'll talk a little bit about this in future meetings and have some additional details, we will detour Mount Vernon Trail
00:20:35
further away from our activities to kind of minimize that interaction with the public.
00:20:43
So that way the trail users will not be adjacent to our access points to the river anymore.
00:20:52
So in the short term they're going to be adjacent to our access points on the river.
00:20:55
We'll have to be careful eventually.
00:20:58
We're going to detour them out of the way so it'll be a much safer operation.
00:21:04
And then, like I said, I just want to point out, stay informed, follow the signage.
00:21:11
We intend to make social media posts and we'll have routine interaction in regards to the Mount Vernon Trail as it's a major element in terms of managing the trail users in conjunction with our construction project here over the next couple of years.
SPEAKER_08
00:21:28
Next slide, please.
SPEAKER_12
00:21:33
And just to touch a little bit on safety, obviously we're working out there on the water.
00:21:37
We're going to occupy a lot of space out there on the water, have cranes, boats, barges, things along those lines.
00:21:44
And in an effort to try to get in front of this, we've had a lot of dialogue with local EMS, Harbor Patrol, emergency responders to start planning for
00:21:58
to work.
00:22:00
So running man overboard safety drills, we want to make sure that they know where we're going to be, whose phone to call, how they access the barges, and quickly in the case of an emergency, things along those lines.
00:22:16
So that dialogue will be continuing here over the course of the job, but we've made a lot of really good progress working with the local emergency response folks to make sure that
00:22:28
in the event of an emergency, they can do their job.
00:22:35
Next slide.
00:22:40
All right, now I'll turn it over to Long Bridge North folks to talk about DC construction activities.
SPEAKER_06
00:22:51
All right, Naomi.
SPEAKER_14
00:22:57
This one is for me.
00:22:59
Thank you, Brian.
00:23:01
So there is work ongoing on Main Avenue that includes utility relocation.
00:23:08
We are beginning construction on crash walls and support walls.
00:23:14
For the rail structures themselves, really just like early excavation work on the Washington Channel, they are beginning to build a trestle across the channel, and from that trestle they will be able to construct the rail bridge.
00:23:33
A lot of that construction will be occurring from the Washington Marina,
00:23:39
which Amtrak is working right now to get us the rights to access that marina.
00:23:46
The Washington Channel will be a no-wake zone.
00:23:49
Most people are going as far as boaters are going through the Potomac River rather than through the Washington Channel because it is very narrow and shallow.
00:24:00
There will be some periodic lane closures on Ohio Drive SW for deliveries and we are clearing trees and brush.
00:24:09
The other main access point for rail bridge construction on the Long Bridge North project is from East Potomac Park and the two parking lots there that are closest to the Potomac River are going to be used for construction, staging, and equipment.
SPEAKER_03
00:24:31
Thank you Naomi.
SPEAKER_06
00:24:33
Public outreach activities continue for the
00:24:37
Long Bridge project throughout this winter.
00:24:39
Some highlights include the digital display at the Long Bridge Aquatics and Fitness Center, which you can see here on the slide.
00:24:46
We introduced that to you at the last CAG meeting.
SPEAKER_05
00:24:49
We continue to update it with the latest information.
SPEAKER_06
00:24:51
Also, earlier this month, we mailed 21,000 postcards to residents of DC and Arlington that
00:25:01
may be experiencing impacts related to the Long Bridge Project, making sure everyone's informed, trying to reach out to the community in different ways.
00:25:09
We have a newsletter coming out in early February for the Long Bridge Project, and on February 13th, we're hosting a Winter Bike to Work Day event in Gravelly Point, so very close to the location that Brian was talking about where we're going to be having some trail impact.
00:25:27
We will have giveaways, hot chocolate,
00:25:30
will be there and granola bars and other activities for people.
00:25:36
We'll be partnering with National Landing, BID, Bike Arlington and WAVA.
00:25:41
So we hope that you will come our direction if you're out on the trail anyway, or maybe you'll just decide to come out.
00:25:47
It's a Friday afternoon from four to six and stop by to see us.
00:25:50
We'll have display boards and we just look forward to speaking with trail users and letting them know what they can expect.
00:25:57
We also will have our next CAG meeting in likely April or May.
00:26:01
We'll keep you informed.
00:26:02
And we are planning public meetings in Arlington and DC in the spring.
00:26:08
So more details to come.
00:26:10
Next slide, please.
00:26:14
These are the ways to keep in touch with us.
00:26:16
We hope you're already following us, but if you're not, please join us on social media, on Facebook, Instagram, LinkedIn, and YouTube.
00:26:23
and a reminder of our project hotline and our email address.
00:26:27
We are committed to responding quickly and efficiently, so please never hesitate to reach out to us.
00:26:37
Next slide, please.
SPEAKER_02
00:26:38
All right, I'll hand it to Sarah.
00:26:41
Good afternoon, everyone.
00:26:42
So I'm going to be giving you all some information on the Alexandria Fourth Track project.
00:26:47
So just as a general overview, this is the construction of a fourth track between Long Bridge Park and Business Center Drive, approximately six miles.
00:26:55
There are several projects that are under that umbrella, specifically the Crystal City Station.
00:27:00
We have what we consider the King Street area projects, which include Alexandria Station,
00:27:06
The construction of the King Commonwealth Bridges and also some city streetcape improvements that are currently in the planning stage.
00:27:13
And then also telegraph tunnel where there's some pedestrian mitigation improvements going on.
00:27:18
Next slide.
00:27:20
So the specific Alexandria fourth track project itself, as I mentioned, it is six miles.
00:27:25
It will be adding that fourth track within the existing right of way between Arlington and Alexandria.
00:27:31
The intent here is to increase rail capacity and address the bottleneck that Naomi spoke to earlier that's currently at Long Bridge that's affecting both passenger and freight trains that are traveling north because we have a situation where five tracks converge into three.
00:27:45
We currently have limited construction activities beginning the quarter four of 2025 with some new updates to give you all for what's coming up this coming quarter.
00:27:56
Next slide.
00:28:01
So just to talk about some review on the project and next steps.
00:28:05
Recently, we had our invitation to bid go out.
00:28:08
We've selected a contractor.
00:28:10
There was a groundbreaking event some of you may have attended in November, and we've also executed a notice to proceed.
00:28:17
Currently, we have turnout panels that are being delivered on site and we're beginning to assemble them.
00:28:22
There's also some utility work and utility relocation that's ongoing as well.
00:28:27
Some things you all can expect to see this quarter for 2026.
00:28:30
These two items I'm going to mention are corridor-wide, so you'll see them along the six-mile corridor itself.
00:28:38
We have survey going on and also the installation of erosion and sediment controls.
00:28:43
We'll also, specifically at Slater's Lane, begin to have ground preparation or civil work that will begin where that works.
00:28:49
You might see some excavation and other items like that, some sub-ballast installation, etc.
00:28:55
Next slide.
00:28:59
So just looking at the project phasing overall for the fourth track construction, what we have here in the first two images are what you can expect for 2026 and then also the final configuration you can expect when the project's completed in 2030.
00:29:13
So during the spring of 2026, as I mentioned previously, there'll be a focus on the installation of crossovers in Slater's Lane.
00:29:20
So that's that southern end of the corridor here.
00:29:22
While that's going on,
00:29:26
We'll have the construction of turnouts adjacent to the right-of-way once those are complete, the actual installation of those crossovers at Slater's Lane, and also the construction of approximately a mile of the fourth track in that area as well.
00:29:39
Moving into the fall of 2026, we'll be building the fourth track between Slater's Lane and the Long Bridge Aquatic Center.
00:29:47
We'll also be building third track and fourth track at or interlocking the Long Bridge Aquatic Center.
00:29:54
with the installation of crossovers at that location as well.
00:29:57
And you will see a temporary track shift as part of the track realignment for the ongoing movement of trains throughout construction.
00:30:04
And then of course, in 2030, with the project being complete, you'll see that total construction of the fourth track up to Long Bridge.
00:30:14
Next slide, please.
00:30:19
So we'll touch on a couple of things you should be expecting to see as construction continues.
00:30:24
One of the things we have here, of course, is access points.
00:30:27
Throughout this project, we're looking at seven different locations where there may be access points.
00:30:33
While they may not all be happening simultaneously, these are all locations where you may be seeing some truck traffic, machinery moving in and out, et cetera.
00:30:40
The seven locations are at Business Center Drive and Roth Street, South Dove Street and Duke, King Street and Sunset Drive,
00:30:48
Potomac Greens Drive and Macy Lane, Potomac Greens Drive and Service Drive that's further up from that location, Crystal Drive and another service road and Crystal Drive and 12th Street South.
00:31:01
The reason the Potomac Greens Drive is bolded is those are the main locations we're looking at doing now within this quarter.
00:31:09
So what that means is you will be seeing truck traffic that will be visible as they go to those locations.
00:31:16
As I did mention earlier, that construction is on the railroad right-of-way, so while you may not be seeing construction itself, those trucks will be going to those locations to begin construction on the right-of-way.
00:31:28
Of course, to address those issues will be traffic control and safety measures in place as they're needed.
00:31:36
Next slide.
00:31:41
So,
00:31:42
Let's talk about crossovers a little bit.
00:31:43
I mentioned those earlier in the presentation and we just wanted to give you all an overview of what that construction actually entails on the track itself.
00:31:52
Excuse me.
00:31:52
So what crossovers are, for those of you that are not familiar, is they're made up of two turnouts or where the two tracks divide.
00:32:00
So if you have a single track, it splits into another one, that divide and that location is called the turnout.
00:32:05
This allows trains to move from one lane or one mainline to another.
00:32:10
So in this instance, of course, we're building the fourth track.
00:32:12
The installation of these crossovers allow trains to move from a third track to a fourth track.
00:32:19
The construction of these crossovers will allow us to shift trains around all the construction that's going on.
00:32:25
So if we have slow orders or work zones or any disabled equipment, even with all those in place, the crossover installations will allow the trains to continue moving.
00:32:35
That's something that's been key to our phasing on the fourth track is the intent to have
00:32:39
Two main lines open at all times, so we're trying to minimize any service interruptions that could occur.
00:32:45
And that's what these crossovers will allow for us.
00:32:49
They provide an alternate route for dispatchers to run these trains.
00:32:54
They also allow for, in the long term, asset longevity because we now don't have to run every single train over a single track.
00:33:03
That can now be distributed among the different main lines that are in place.
00:33:08
and it just allows the dispatchers overall to balance the traffic load to allow for more consistent running time for the trains themselves.
00:33:17
Next slide.
00:33:21
So now that we've talked about the crossovers, we're going to speak to the two locations where they are being installed.
00:33:27
The first one, as I mentioned earlier, in 2026, or the spring of 2026, is at Slater's Lane.
00:33:33
This particular location is just north of Alexandria Station.
00:33:36
and it's an issue where we have dwelled times at the station for passenger trains that create spacing challenges for trains that are running around it for the passenger trains themselves.
00:33:47
So the intent here is to create a safe way for dispatchers to reorganize the trains while crews also stage and shift the trains accordingly between Slaters and Aquatic Center overall.
00:33:59
What this means for the operation of the trains, it means the reordering of trains
00:34:04
between Alexandria and Long Bridge.
00:34:07
It'll allow for the improvement of the flow of traffic and for the through service from DC to Crystal City by giving more options for dispatchers to use for the trains to move throughout the locations.
00:34:20
What does this mean for the community?
00:34:22
Near term, as I mentioned before, all this construction will be within the existing railroad right-of-way, but you will of course be seeing that construction.
00:34:30
From a long-term perspective, which this does help here, is for some of you that are near the tracks, you may have seen this bunching that occurs where all these tracks or these trains stack up where they're waiting to move because there's not enough room.
00:34:43
This crossover installation and this overall fourth track will allow for that stop and go movement to hopefully be minimized because we're giving them more options to continue train movement consistently.
00:34:56
Next slide, please.
00:35:01
So the other location we're installing crossovers is the Aquatic Center just south of Long Bridge.
00:35:06
That, of course, is happening in the fall.
00:35:08
Why is this important?
00:35:10
This is where we have that choke point where the three tracks go across the bridge.
00:35:15
And this will hopefully with construction of a fourth track help to minimize service disruptions from the Crystal City Station improvements that are happening because the installation, the crossovers allow for the train movements to continue.
00:35:32
What does this mean for operations?
00:35:33
As I mentioned, it allows for that constant train movement through the construction period
00:35:38
It also reduces the need to merge trains back and forth and to hopefully alleviate some of the compression of train traffic that you see just south of Long Bridge.
00:35:49
What does this mean for the community overall?
00:35:51
In this particular area near term, you will see some heavy equipment.
00:35:55
Material deliveries and also staging onto the rail right-of-way, but of course you'll see that traffic movement.
00:36:01
And then for the long term, similar to what we have with Slater's Lane, there'll be more consistent, predictable train operations.
00:36:08
And you'll hopefully be seeing fewer backups south of the river, especially once Long Bridge is completed as well, we'll have that through-track opportunity.
00:36:15
Next slide, please.
00:36:19
And then
00:36:20
Just the last piece for Alexandria fourth track.
00:36:23
Here's just a general project timeline overall.
00:36:26
We've already completed our 100% design that was in 2023.
00:36:30
We've completed our permitting quarter one of 2025.
00:36:33
The property acquisition was completed in quarter three of 2025.
00:36:38
And now we're in that construction period with the limited civil work that had begun and the utility relocation that had begun during quarter four of 2025.
00:36:47
and with the completion scheduled for the project to be Q1 of 2028.
00:36:51
I think we'll be passing it over to Lindsay.
SPEAKER_05
00:36:57
Good afternoon, everyone.
00:36:59
I'm using a different headset today.
00:37:01
Can somebody just give me a thumbs up if you can hear me OK?
00:37:04
Awesome.
00:37:04
All right.
00:37:05
So without a out of the way, first want to start off with an aerial view.
00:37:11
If you've been to a few of these meetings before, you've likely seen this.
00:37:15
But just as a refresher, in the pink here is where we'll construct the new Crystal City platform.
00:37:22
It's about a quarter mile south of the existing VRE platform at Crystal City.
00:37:27
So the great thing about this is that it is a center central platform, which means that we can board on either side, utilizing two tracks to make operations go a little bit more smoother.
00:37:38
It will also accommodate eight car trains so that we can open up all doors and offload everybody, saving a good amount of time during that process as well.
00:37:50
In the green here, we have our pedestrian improvements.
00:37:54
To the north side, we've got a pedestrian underpass and ramp.
00:37:58
And then on the south side, towards the left of that photo, we've got the pedestrian bridge and stair and elevator platform, elevator tower, I should say.
00:38:06
Next slide, please.
00:38:11
All right, so I've touched a little bit on the last slide about this, but the station will have an island platform able to accommodate eight-car train sets.
00:38:20
As I've said, the longer platforms allow for all train car doors to open, improving operational efficiency.
00:38:25
And we've also got some enhanced intermodal transit connectivity planned for the station.
00:38:30
So the north entrance will reduce distance to the new metro entrance, and it also includes trail connections to the Mount Vernon Trail Connector.
00:38:38
The south entrance accommodates future pedestrian and bicycle connection and will include a connection between the station and the airport.
00:38:50
Next slide, please.
00:38:53
Just a quick little look at our timeline.
00:38:56
We completed 90% design in March of 2025.
00:39:00
We anticipate 100% design this quarter of 2026.
00:39:05
And then construction is anticipated to begin quarter one of 2027, just about a year from now, and last through quarter one of 2029.
00:39:16
Turn it over to our friend at GFT, Jason Skofie, but we have technical staff on.
00:39:25
Happy to answer questions about either the Alexandria Station, as you'll hear more from Jason about, or Crystal City when we open it up to questions.
00:39:32
Thanks, everyone.
SPEAKER_13
00:39:34
Thank you, Lindsay.
00:39:34
As mentioned, my name is Jason Skofie and I'm with GFT representing VRE and VPRA as part of the Construction Management Team.
00:39:42
I just want to start with a high level overview of the project here.
00:39:46
Historically, this was two separate projects that we combined them together for construction efficiencies and to minimize the impacts.
00:39:53
As you can see in green are the King Street and Commonwealth Rail Bridges.
00:39:57
They are over 100 years old and are ready to be replaced.
00:40:01
And then over at the station, you'll see where we're going to lengthen the platforms.
00:40:06
We're going to be removing the at-grade crossing and replacing it with elevators and also modernizing and completely redoing the pedestrian tunnel that connects the two platforms that are today.
00:40:19
And by lengthening the platforms and adding a boarding edge on track one, it'll help improve the riders boarding and onboarding the trains.
00:40:29
Next slide, please.
00:40:32
So kind of just zooming in here at the station, VRA designed the improvements to the existing station.
00:40:41
Like I mentioned, the intent was to remove the accurate crossing
00:40:45
We were able to improve the track and platform interface.
00:40:49
We're actually going to be raising the platform several inches and the idea that we can eliminate the need of the step boxes.
00:40:56
Obviously they're kind of cumbersome to align with the doors each time and that wastes time for people boarding and onboarding the train.
00:41:03
So by removing those, the people can board the train quicker and get off quicker as well.
00:41:09
And then by adding a boarding edge on track one,
00:41:13
We'll also be able to be more flexible with service in case there's an issue with the other tracks.
00:41:18
We can use that track one track for boarding.
00:41:23
Next slide, please.
00:41:27
As far as the bridges go, as many of you know, the top one there is the Commonwealth Avenue Bridge and the bottom one is the King Street Bridge.
00:41:38
VPRA and CSXT designed the two replacement rail bridges to span King Street and Commonwealth
00:41:44
They are going to be constructed by VRE as part of this project, as part of the Alexandria Fourth Track project that Sarah and my colleagues mentioned earlier.
00:41:52
This will reduce the maintenance and minimize the service interruptions and upgrades the bridge to meet current standards.
00:41:58
Like I mentioned, these bridges are over a hundred years old and kind of has a useful life.
00:42:03
And so, as you can see, it's illustrated there, we're going to be widening the bridges as well and also making the clearance greater.
00:42:11
and so that will enhance the safety for pedestrians and motorists that are traveling underneath the bridges.
00:42:16
There's a separate project that the City of Alexandria is undertaking, and that is the streetscape improvements for the pedestrians and motorists under there, like to incorporate additional lanes or bicycle lanes.
00:42:27
As many of you know that do travel there, especially on Commonwealth, it's very tight for pedestrians and bicyclists.
00:42:32
And so by being able to wind that, we'll provide more space for everyone that travels through the area.
00:42:39
Next slide, please.
00:42:41
Here's the overall schedule.
00:42:43
We've completed the design and completed the permitting.
00:42:46
We're just wrapping up property acquisition now, and we're getting into my favorite part of the project, which is the construction phase.
00:42:53
In the next slide, I'll show you the details on the construction phase.
00:42:59
Next slide, please.
00:43:01
So I mentioned for the completed activities, the design is complete.
00:43:04
We awarded the construction contract in the fall, and we also issued a limited notice to proceed to the contractor on November 17th.
00:43:13
and that allowed the contractor to begin some submittal review process with the city and with CSX and VRE and the engineer records.
00:43:22
So we've been busy since November.
00:43:25
We're anticipating the formal notice to proceed to be issued here any day now, and the contractor is eager to get started.
00:43:33
So you'll probably be seeing site work activities next week, which is February 2026.
00:43:40
Those site work activities include surveying, setting up the fence around the construction areas, erosion sediment control measures, and the temporary construction office trailers.
00:43:52
Some of the early items will be vegetation removal and the railroad right-of-way, so that's adjacent to the railroad.
00:43:58
We have to clear some of their vegetation to be able to bring in some of our equipment, like our cranes,
00:44:04
And then the big major milestones that we'll be hitting is planned for March and that's for the jump span installation.
00:44:11
That's going to be weekend work between three to five weekends of work that requires the contractor to obtain Alexandria noise permits and Alexandria MOT permits for lane closures.
00:44:22
And so we know that's going to be, you know, impactful to the surrounding community.
00:44:27
And so we're planning on launching a newsletter and a brand new website to keep everyone in the community up to date with news that's going on and construction updates.
00:44:38
Next slide, please.
00:44:41
Okay, and then as I just mentioned, VRA's website has all these details about the different projects for the Crystal City Station, the Alexandria Station, and the King and Commonwealth Replacement Bridges.
00:44:53
Apologies I just realized that a link is the incorrect link on there.
00:44:57
My colleague Lindsay just added the correct link to the chat if you'd like to navigate there and check out those projects.
00:45:04
And I'm going to hand that back to Meredith now.
00:45:06
Thanks.
SPEAKER_06
00:45:08
Thank you, Jason.
00:45:09
And we'll update the slide before we post the presentation on the website, too.
00:45:16
So keeping the community informed, we continue to be out in the Alexandria and Arlington community talking about our projects, including the Alexandria Fourth Track.
00:45:26
Most recently, we were at the Alexandria Station for numerous days, morning and evening, speaking with riders and commuters on Amtrak and VRE about
00:45:37
service changes that are upcoming for both.
00:45:40
And we have one of my colleagues here to talk in more detail about those outreach activities and the upcoming service changes for VRE and Amtrak.
00:45:50
Jeremy, next slide, please.
SPEAKER_10
00:45:53
Hi.
00:45:53
So yes, if you've paid attention to the first 38 slides, you've noticed that some construction has started.
00:45:59
And so in response, VRE and Amtrak had to make some temporary adjustments.
00:46:04
And we expect those adjustments to be evaluated and possibly shift a little bit as we go through essentially five years or until the construction is complete.
00:46:13
This is essentially driven by the Long Bridge North project, the portion in DC that Naomi went over earlier in the slides.
00:46:21
That's the reason for the work window that I'll discuss if we go to the next slide.
00:46:26
And so as we've done this, you know, one of the things I want to mention is that we're trying to stay ahead of the project schedules for construction and set the service schedules in advance so that you would, if necessary, get an email about any possible changes to your schedule.
00:46:42
But we really, our goal is to have you booking with confidence and showing up with confidence that the schedule you booked is what you're going to experience that day.
00:46:50
And so that's our endeavor.
00:46:51
And so it's January 12th when we started this.
00:46:53
We had already kind of put these in place and people received notices.
00:46:57
And what's driving this is that we wanted to maintain maximum service and performance for Amtrak and VRE and for CSX.
00:47:03
They still have to run their trains as well.
00:47:06
But we also wanted to maximize work window productivity and get this project done, you know, kind of minimize the pain in the sense that we have to take some pain to get this done.
00:47:15
But we want to maximize that work out there.
00:47:17
So this is being driven, as I said, by Long Bridge North portion of the project up there in DC.
00:47:22
And that's the picture that we're looking at here is up by this Elementor Hotel.
00:47:27
And DC noise and vibration laws restricting significant work to daytime hours is part of the reason there.
00:47:33
And so our goal was to look at the VRE morning peak hours and try and preserve as much ridership and service as possible.
00:47:41
Also minimize the schedule changes for VRE because commuters know it.
00:47:45
They largely know their trains by the time it arrives and by the time it gets in there, not necessarily by the train number.
00:47:49
So we want to accommodate the consistency that a VRE commuter expects.
00:47:54
We've also had to adjust Amtrak Northeast Corridor service and long distance services.
00:47:59
This is large because the trains that are going through this area of Northern Virginia and into DC is actually train service that goes as far north as Boston, goes all the way down to New Orleans, it goes to Florida, it goes to Chicago.
00:48:14
Mississippi, all the train services are experiencing some change because of this one project.
00:48:19
So we've adjusted Amtrak services.
00:48:21
We did have to truncate some services in Virginia temporarily and put in some bus services.
00:48:27
And so we'll continue to evaluate that.
00:48:29
And you can see at the bottom of the screen there, there's the times that we're having to work through the day to try and minimize any trains going through during that time to give Long Bridge the time they need to access the tracks.
00:48:42
You can go to the next slide.
00:48:45
So as Meredith mentioned, there's been a lot of outreach.
00:48:48
There's been multiple ways of doing outreach, but these are just some examples of kind of the push right before we went into the changes on January 12th where we were handing out these cards to passengers.
00:49:00
I think VRE also left them in seats and we were at stations with tables.
00:49:03
offering coffee so people come up and talk to us but also just going around and handing them out to folks and they have QR codes on them that take you to a website that we can keep up to date as any services change throughout the life of the project.
00:49:15
So our intent was to give people that notice and send them to a location where we keep information up to date.
00:49:21
And so now we've shifted from that initial push to putting some posters in stations.
00:49:27
We also make sure that people get notifications in pre-trip emails or through the VRE app.
00:49:32
And there's a coordination effort between agencies to ensure that we continue to keep customers informed.
00:49:39
Meredith?
00:49:42
Sorry, Linda.
SPEAKER_06
00:49:45
Thank you, Jeremy.
00:49:47
I'll go ahead and jump in.
00:49:48
I just wanted to go ahead and list the
00:49:51
ways that individuals can sign up for our email lists for all of our different projects that's listed here.
00:49:58
And also to highlight our construction hotline that we now have for all of Transforming Rail in Virginia.
00:50:05
And that's the contact, oh, excuse me.
00:50:06
Well, we have one that's a construction hotline and there's a phone number here and we will keep you posted on that information.
00:50:15
Next slide.
00:50:15
I'll hand it over to Linda to manage our Q&A session.
00:50:19
I'm eager to hear from you guys, we all are.
SPEAKER_03
00:50:22
Hello everybody.
00:50:23
Just wanted to open it up for questions.
00:50:25
You can either post a question in the chat or feel free to raise your hand or just shout it out if you'd like.
00:50:33
But we are available now to answer any questions.
00:50:39
Go ahead, John, Patrick.
SPEAKER_09
00:50:44
Thank you.
00:50:45
I had two questions.
00:50:48
First of all, I'm a little confused.
00:50:50
Unfortunately, as are so many people my age, I'm not terribly technically savvy, and I don't know exactly where to go to see the briefing slides.
00:51:06
How do I get information on that?
00:51:09
And then the other question is, I will of course report back, I represent the Rosemont neighborhood, which is, which borders the work in Alexandria, both at King Street and Commonwealth Avenue.
00:51:26
So that's my particular concern.
00:51:28
Once I report back to the neighborhood, I will probably have questions people ask me
00:51:35
that I would like to forward.
00:51:37
And if I can't answer them from the briefing materials, is there someone I can email?
00:51:43
I don't want to bother people.
00:51:44
I know you're very busy, but send an email that can be answered when that person has the time to answer my email.
SPEAKER_06
00:51:54
I think the construction hotline email is probably the best email to use.
00:52:00
Linda or someone on the Kinley horn team, can I ask you to drop that in the chat?
00:52:04
And we can also send that directly to you, John.
SPEAKER_09
00:52:12
If you would be kind enough, yes, you have my email, I'd very much like to receive that.
00:52:17
And also, as I say, exactly, if you could also drop in exactly where to go to look at this briefing online, because I've been trying to take notes, but it's a lot, a lot of information coming very fast.
SPEAKER_06
00:52:30
Yes, absolutely.
00:52:31
We will be posting the video and the slides on our website, and I can send an email out to all the community advisory group members after this call with a link to those materials as soon as we have them posted.
00:52:44
Excellent, thank you.
00:52:45
Probably by the end of the day, Friday.
00:52:46
Also, I see that Derek has posted the hotline information with the email and the phone number for all of Transforming Rail in Virginia in our chat.
00:52:56
So that's always a great place to reach us.
SPEAKER_09
00:52:59
Great, thank you.
SPEAKER_03
00:53:00
Hey, Meredith.
SPEAKER_06
00:53:01
You know, as I should have noted, for K&K Commonwealth, VRE is probably the best place to reach.
00:53:10
If you have questions about Alexandra Station or K&K Commonwealth, Lindsay, do you have the email?
SPEAKER_13
00:53:16
We have an email address.
SPEAKER_06
00:53:18
OK. We'll drop it in the chat for everyone.
00:53:21
Yes.
00:53:22
OK. And we can also send that to you, John.
SPEAKER_03
00:53:26
Great.
00:53:31
We have another question from Steve Mass, if I'm pronouncing that correctly, Mass.
SPEAKER_07
00:53:36
Yes, you're correct.
00:53:38
That's correct.
00:53:39
First of all, when are you going to be posting all of this stuff?
SPEAKER_06
00:53:45
We should be able to post it by the end of the day, Friday.
00:53:48
It just depends on how quickly we can process the video.
00:53:53
We'll do it as soon as possible.
SPEAKER_07
00:53:54
Now the other thing that particularly concerns Crystal City residents is the noise of the construction.
00:54:04
When do you have a sense of when different sections of the track will be worked on, how severe might the noise be, what it will be coming from, and vibrations as well.
SPEAKER_02
00:54:22
So regarding the construction, I'm assuming that area is probably close to the Aquatic Center in that general vicinity, that northern section, if you will.
00:54:34
With the construction isolated to the corridor, you will be hearing some construction noise, but it's not dissimilar from the noise you would see if those are for those of you that are familiar with the large workings that go through the corridor working with the same amount of
00:54:51
equipment and things going on.
00:54:52
It's of course great.
00:54:54
It's on a greater scale than basic maintenance, but it is somewhat similar to some of the large production work you've probably seen on that track.
00:55:02
I guess Adam, would you be able to speak towards any of the vibration concerns that Steve brought up?
SPEAKER_11
00:55:09
I don't think the vibration concerns will go much more than the kind of track corridor area.
00:55:16
I mean, we will have to
00:55:18
After we backfill, compact the soil to develop that subgrade and subbase.
00:55:23
But there shouldn't be much more beyond that.
00:55:25
I mean, there might be some vibrations with wall work, but it should all be isolated to pretty much the corridor location.
SPEAKER_07
00:55:33
What about the actual putting the track in?
00:55:36
I mean, is there going to be pounding or how do you do that?
SPEAKER_00
00:55:39
Yes.
SPEAKER_11
00:55:44
So as far as the installation of the track, I mean, we will lay ties, we will have rail brought in via train and laid down on the side, and then that will be lifted up onto the ties on top of plates and then spiked.
00:55:58
The spiking is typically done either via hand or rail-mounted spiker.
00:56:04
That should be, you know, from a vibration standpoint, should be minimal at most, and then from a sound standpoint, shouldn't be too loud.
SPEAKER_07
00:56:15
And when you say it shouldn't be too loud, would you be able to hear it from the street, from Crystal Drive?
SPEAKER_11
00:56:24
Based on the proximity of the track, you may be able to hear, like Sarah said, some of the tiegangs that have come through.
00:56:31
If you've seen those, it would be similar to the maintenance work that comes down through there.
00:56:36
I don't think it would be as loud as if you hear a train coming down through the area.
SPEAKER_07
00:56:40
Okay, and what about for the buildings that back onto the track?
SPEAKER_11
00:56:45
You mean as far as like echoing or inside the buildings themselves?
SPEAKER_07
00:56:49
Yeah, inside the buildings and just along that stretch, which includes where the new train station is going to be built.
SPEAKER_06
00:56:56
Yeah, I do want to note this.
00:56:57
There's a different answer for Crystal City station improvements.
00:57:01
Adam and Sarah are talking about the fourth track project.
00:57:06
Maybe we want to shift this question over to DRD.
SPEAKER_02
00:57:08
Yeah, I guess to close out the question, similar to what Adam said, for the track construction portion,
00:57:15
For the interior, I feel like the sound, and please correct me if I'm wrong, Adam, the sound should be minimal, comparatively speaking.
00:57:22
That is, while it is construction, as he said, it's isolated to the corridor.
00:57:28
If you're on the street, you may hear some of it, but it shouldn't be a large amount of noise happening inside.
SPEAKER_07
00:57:35
And do you have a schedule yet of like how long it'll be in different sections?
SPEAKER_02
00:57:42
So we have an initial phasing plan that we're coordinating with our outreach team to try and figure out the best way to disseminate that information.
00:57:51
So as I've noted here, that the spring you're going to see us focus on Slater's Lane and the fall will be closer to the Aquatic Center.
00:58:01
So we can provide it in that general kind of description as of right now.
00:58:06
Of course, as things become very clear or if there's specific work that's happening that we think from either a sound or vibration perspective that might be an issue for the public, that is something that we'd be coordinating with our outreach team, Meredith and her team, to try and get that out to you all if we have enough notice to give you all that heads up.
SPEAKER_07
00:58:25
And finally, is it going to be just during the day or at night too?
SPEAKER_02
00:58:30
There will probably be some night work for cutover purposes.
00:58:33
when we start doing track alignment itself.
00:58:39
And whenever we do have the night work, we will try and give you that notice as well.
SPEAKER_07
00:58:43
Great, thank you.
SPEAKER_06
00:58:44
And then the VRE station upgrades at Crystal City is a separate project that we should allow VRE to speak to, because Sarah and Adam are speaking to the Alexandria fourth track project.
00:58:58
I don't know if you have the right people to speak to right now.
SPEAKER_05
00:59:01
We have Chris Coker on.
00:59:03
He's the Deputy Project Manager for the Crystal City Project.
00:59:06
Chris, do you mind chiming in?
SPEAKER_08
00:59:12
Good afternoon.
00:59:13
So the station construction would be pretty similar to the activities you're going to get out there with the track construction, just vehicles in and out.
00:59:23
Platforms can be precast for the most part, so just lifting that
00:59:28
those members into place and then erecting a tower and doing the cut and cover operation for the tunnel.
00:59:34
So nothing really out of the ordinary.
SPEAKER_03
00:59:42
I think if we're done with that question, we have a comment or a question from Claudia.
00:59:47
Did you still want to ask your question, Claudia?
SPEAKER_04
00:59:50
Thanks so much.
00:59:51
I dropped it in the chat.
00:59:53
First, thank you for having a section dedicated to traffic impacts as that's something that I think a lot of people will be interested to know about and that AnchorLink makes it easy to share.
01:00:02
I guess my question for the Mount Vernon Trail activity is should we then confidently say for trail users that there will always be activity in that area beyond just January and February?
SPEAKER_12
01:00:20
Yes, there will be a constant interaction on a daily basis for the next four to five years.
SPEAKER_04
01:00:28
Four to five years.
01:00:28
Okay, thank you.
01:00:29
That's helpful to confirm.
SPEAKER_03
01:00:33
Thank you, Claudia.
01:00:34
I have a question here from Carol Fuller.
SPEAKER_01
01:00:38
Right, you may not have seen what I put in the chat, but I commented that the Crystal Drive and 12th Street access is located in the middle of many residential buildings in Crystal City.
01:00:49
We have a recurring problem with construction materials and vehicles being parked at that access overnight, which then requires the trains to honk their horns all night long.
01:01:00
So we're requesting that you ask the contractors who start in the fall on the Long Bridge Park that they park their equipment more into Long Bridge Park.
01:01:12
CSX has done that occasionally, but we have to constantly remind them of this because it's extremely annoying to the residents to have the honking horns all night because of the materials and the porta-potties being right next to the access.
SPEAKER_06
01:01:31
Thank you for your comments.
01:01:33
We will pass that along.
SPEAKER_03
01:01:40
Anyone else would like a chance to ask a question or make a comment?
01:01:56
I don't think I see anyone raising their hand.
01:01:58
If you want to just shout it out, feel free in case you don't know how to use the hand raised little option at the bottom of your screen.
01:02:06
Feel free if you just have a problem answering your question.
01:02:10
Go ahead, John.
SPEAKER_09
01:02:12
Uh, whoops.
01:02:14
Yes, can you hear me?
SPEAKER_00
01:02:15
Yes.
SPEAKER_09
01:02:16
Good.
01:02:18
There was a mention of Sunset Drive and King Street being one of the staging, well, near one of the staging areas that will see traffic.
01:02:30
Am I right in assuming that also includes Commonwealth Avenue?
01:02:33
Because it seems Commonwealth Avenue actually has the best access there to the roadbed.
SPEAKER_13
01:02:40
It's the area, this is Jason Scofi here, the area the contractor will be using is between King and Commonwealth.
01:02:47
It's just west of the railroad tracks now.
01:02:49
It's the area that they've used in the past for construction access as well.
01:02:56
Got it.
01:02:57
Thank you.
01:02:58
Yep.
01:02:58
And then just the other parts that the contract will be using are on the south side of King Street, like adjacent to the station in order to put in the elevators as well.
SPEAKER_09
01:03:08
Of course.
01:03:08
Yes.
01:03:09
Thank you.
01:03:10
No problem.
SPEAKER_03
01:03:15
Meredith, I don't know if we're doing on time.
SPEAKER_06
01:03:18
Yeah, we're past we're just we're 133 but if there's any other pressing questions we can answer.
01:03:25
Okay, well, please know that you can reach out to us at the email and phone number that we dropped in the chat and that we had on an earlier slide and we will be following up by sending out a link to the slides and the video for anyone who couldn't attend today.
01:03:43
Thank you for being here.
01:03:45
Thank you to our speakers and please keep in touch.
01:03:48
We'll be back for another community advisory group meeting in three months.
SPEAKER_00
01:03:54
Thank you.