Central Virginia
  • Virginia Passenger Rail Authority
  • Board of Directors Meeting 5/21/2026
  • Auto-scroll

Board of Directors Meeting   5/21/2026

Attachments
  • May Board Meeting Minutes.pdf
  • May Board Meeting Agenda.pdf
  • January Board Meeting Minutes.pdf
  • Executive Director’s Report.pdf
  • Construction Updates Report.pdf
  • 2026 General Assembly Updates.pdf
  • Bylaws Update.pdf
  • DRPT and Virginia Statewide Rail Plan Update.pdf
  • Key Project Funding Updates.pdf
  • FY27 VPRA Budget.pdf
  • Service Performance Updates.pdf
  • Decision Brief – May 2026 Bylaws Update.pdf
  • Resolution – May 2026 Bylaws Update.pdf
  • Decision Brief – Ratify FRA CMAQ Grant Agreement.pdf
  • Resolution – Ratify FRA CMAQ Grant Agreement.pdf
  • Decision Brief – FY27 Budget and Management Reserve.pdf
  • Resolution – FY27 Budget.pdf
  • Decision Brief – VPRA Procurement Procedures.pdf
  • Resolution – Procurement Rules Update.pdf
    • Mariia ZimmermanChair, Board of Directors
    • 00:00:01
      Thank you.
    • 00:00:02
      Good morning, everyone.
    • 00:00:06
      I am going to call our meeting to order.
    • 00:00:09
      We're officially in order and now it's briefing from Mike McGlothline.
    • Michael McLaughlinChief Operating Officer
    • 00:00:19
      I'm going to try to be as lively as Lamar usually is.
    • 00:00:22
      He could make it up here this morning.
    • 00:00:25
      So we are 1800 diagonal route.
    • 00:00:30
      on the third floor in Chesapeake Potomac Road.
    • 00:00:35
      If we need to call 911, Mary Stealth, you're assigned to that.
    • 00:00:40
      Secondary, Lord Farmer, DJ, CPR.
    • 00:00:43
      When we have meetings, DJ is always the first one to raise his hand for CPR, that's why he's assigned here too.
    • 00:00:48
      I'm assigned to meet first responders, Michael West, Mr. Westerman, General Counsel's secondary, medium first aid kits.
    • 00:00:57
      Matt Jett, I'm gonna ask you to grab that.
    • 00:01:00
      over in the King Conference Room.
    • 00:01:04
      Stairwells and fire extinguishers, stairwells and bathrooms.
    • 00:01:08
      Stairwells on both sides of the elevator, the bathrooms are both on the far side of the elevator.
    • 00:01:12
      You need to use those.
    • 00:01:13
      If you do need to use the restroom, there is some key cards out here, the orange key cards, you need to take them with you to be able to get into the restroom and get back into our office suite.
    • 00:01:23
      If we need to evacuate, we will use the stairwells.
    • 00:01:26
      Luckily, we're only on the third floor, we're only a couple floors down.
    • 00:01:29
      We'll meet at Ryan Kurtz
    • 00:01:31
      Duke, across from Whole Foods.
    • 00:01:33
      So just follow us in front of the Fidelity over in Rinehurst and Duke.
    • 00:01:38
      Make sure the person sitting to your left is present.
    • 00:01:42
      If there is an active shooter, flee, hide, fight.
    • 00:01:47
      And for those pretending remotely, please be aware of your surroundings.
    • 00:01:51
      For those of us here, be careful of the chairs.
    • 00:01:53
      They might pinch you on the table.
    • 00:01:54
      So unless I'm missing anything, DJ gave me a look that might have missed something.
    • 00:02:00
      We're going to pass it on back to the chair.
    • 00:02:05
      Thank you.
    • Mariia ZimmermanChair, Board of Directors
    • 00:02:05
      Well, good morning.
    • 00:02:07
      Welcome everyone again.
    • 00:02:09
      It's great to be here.
    • 00:02:11
      The last meeting we had, I think it was three days into the job.
    • 00:02:14
      So now I'm a few months into the job, but it's great to be here.
    • 00:02:17
      I know we have a lot that is going on.
    • 00:02:20
      So just a reminder to please silence all electronic devices if you have any of those.
    • 00:02:25
      I also just want to thank VPRA and in particular Mike McLaughlin.
    • 00:02:29
      Earlier this week, the Commonwealth Transportation Board was up in Alexandria for our monthly meeting and Mike and some other VPRA staff did a great job of giving CTV board members a tour of the construction work that's underway.
    • 00:02:43
      So thank you for that.
    • 00:02:44
      So with that, why don't we move to do a roll call for attendance.
    • 00:02:49
      So Mariia, I'll turn to you.
    • 00:02:51
      Ms. Bushue?
    • SPEAKER_10
    • 00:02:52
      Here.
    • Beth RhinehartMember, Board of Directors
    • 00:02:54
      Ms. Choe?
    • 00:02:55
      I know Dallas is representing Ms. Charlie Day.
    • 00:02:59
      Mr. Crawford?
    • SPEAKER_01
    • 00:03:01
      Here.
    • Beth RhinehartMember, Board of Directors
    • 00:03:03
      Mr. Delandro?
    • SPEAKER_10
    • 00:03:08
      Ms. Doersch?
    • 00:03:09
      Here.
    • 00:03:10
      Mr.
    • 00:03:10
      Flowers?
    • Beth RhinehartMember, Board of Directors
    • 00:03:12
      Mr.
    • 00:03:12
      Flowers is here.
    • SPEAKER_10
    • 00:03:14
      Mr. Jordan?
    • Dallas Richards
    • 00:03:15
      Here.
    • SPEAKER_10
    • 00:03:17
      Ms. Lawrence?
    • 00:03:18
      Here.
    • Dallas Richards
    • 00:03:19
      Apologies, present.
    • Patricia DoerschMember, Board of Directors
    • 00:03:21
      Ms. Mitchell?
    • 00:03:23
      Here.
    • 00:03:23
      Thank you.
    • 00:03:25
      Mr. Payne?
    • Dallas Richards
    • 00:03:27
      Here.
    • SPEAKER_10
    • 00:03:27
      Thank you.
    • 00:03:29
      Ms. Rhinehart?
    • 00:03:30
      Here.
    • 00:03:31
      Mr. Watkins?
    • 00:03:37
      And Mr. Zang?
    • SPEAKER_13
    • 00:03:40
      Here.
    • Beth RhinehartMember, Board of Directors
    • 00:03:42
      Thank you.
    • Mariia ZimmermanChair, Board of Directors
    • 00:03:44
      Next up, we have for public comment, no one has signed up to us.
    • 00:03:53
      I want to see, I know we have a few visitors in the room.
    • 00:03:56
      There's anyone who wanted to provide public comment?
    • 00:04:03
      All right, hearing none, we will move forward.
    • 00:04:06
      I want to first mention before we kind of get too much further down the agenda, we know that there are some board members that have some schedule issues.
    • 00:04:14
      So we're going to do a slight adjustment to our agenda.
    • 00:04:18
      We are going to move item number 11 to happen in March and we will
    • 00:04:23
      Move our budget discussion to happen before we break for lunch so we can accommodate taking action needed and try to move judiciously through the various other items on the agenda.
    • 00:04:36
      But with that, I want to see if we have a if there's a motion to approve the January 22nd, 2026, VPRA meeting minutes.
    • 00:04:46
      And is there a second?
    • 00:04:47
      Second.
    • 00:04:48
      All right, all in favor say aye.
    • 00:04:50
      Aye.
    • 00:04:51
      Aye.
    • 00:04:52
      All opposed say no.
    • 00:04:55
      And any abstentions?
    • 00:04:58
      All right.
    • 00:04:59
      With that, we will move to item number seven, the director's report, executive director's report.
    • SPEAKER_04
    • 00:05:03
      Excellent.
    • 00:05:03
      Thank you very much.
    • 00:05:04
      Good morning, everybody.
    • 00:05:05
      I'm going to go through this quickly because really the important thing we need to get through today, we're going to also be a little bit repetitive.
    • 00:05:14
      You kept the executive director in the same format as we always do.
    • 00:05:18
      And it's really, I happened to just by accident, look at one of the first executive director reports we did about five years ago.
    • 00:05:25
      And the way this report is involved is really important because we try to be responsive every stream back.
    • 00:05:31
      And I said, I'd go through this quickly.
    • 00:05:32
      Now I'm being very rewarding.
    • 00:05:34
      But, um,
    • 00:05:35
      Look, we're going to go through this quickly.
    • 00:05:37
      We're going to talk more during the construction update report about some of the progress that we're making.
    • 00:05:42
      The budget's going to talk about a lot of the finance stuff.
    • 00:05:44
      So we kept this in the same format, but I'm going to go through it quickly because I don't want to be too much.
    • 00:05:51
      The recent updates, we
    • 00:05:55
      We want to either get all of the Alexander folks and all the Richmond folks together in one place to talk about strategic planning to do, I mean, team coaching and development, and we did that earlier in May.
    • 00:06:05
      A highly, briefly with my folks, we'd be doing a survey afterwards and did a whole sector of persuading skills.
    • 00:06:13
      So we continued to grow and evolve as a workforce.
    • 00:06:17
      That was, again, very well received.
    • 00:06:19
      Also, I was asked by
    • 00:06:21
      FRA to speak on a rail technology summit.
    • 00:06:24
      I was there with another member of state support service, Patricia Grinford, Maine, and then the FRA was there.
    • 00:06:32
      And then as you can see, folks from Amtrak.
    • 00:06:34
      So it really shows that Virginia is seen as a leader in state passenger rail and accentuates the pressure that we have on us to continue moving forward.
    • 00:06:46
      We continue to have successes.
    • 00:06:49
      All right, I want to spend a little bit of time on Shenandoah Valley Trail.
    • 00:06:52
      So you all likely remember back in the fall of 2025, we were asked to orchestrate an agreement with the Shenandoah Valley Rail.
    • 00:07:05
      It's just sort of a stick and nail rail corridor out west that has not been used for anything of note in years.
    • 00:07:13
      Norfolk Southern is looking to sell it, and there was an agreement
    • 00:07:19
      and Shenandoah Valley Trail in Shenandoah Valley.
    • 00:07:27
      And we had come very, very close to an agreement with them where we would facilitate money that's not ours being used to purchase the trail.
    • 00:07:36
      They would own the trail and they would have to maintain the trail.
    • 00:07:38
      We would oversee that transaction and then they would do a rail and a trail
    • 00:07:44
      This is a good thing for us, we thought, because it mitigated any risk that we had, but it also allowed us to gain access to that rail for the future.
    • 00:07:58
      Candidly, that future is not 2030.
    • 00:08:01
      That future is not 2040.
    • 00:08:02
      That future is probably 2050.
    • 00:08:04
      We will continue to expand, and once it gets out to Gainesville,
    • 00:08:09
      It's a nice connection front-royal where we could turn the corner and have passenger train service right down to JMU Harrison Burgos.
    • 00:08:16
      So it's a good deal for us at that point.
    • 00:08:20
      You all approved an amendment to our budget to accept that money from the CTV and then pass it on to this Battlefield Foundation.
    • 00:08:27
      Unfortunately, when it went to the CTV, they made a change and they said, look, if there are other foundations or other people that think they can do similar, make similar progress,
    • 00:08:37
      VPRA should do a competition and determine which of these proposals is best.
    • 00:08:43
      CTB asked us to do a competition.
    • 00:08:46
      That goes against our bylaws, our rules.
    • 00:08:48
      It wouldn't be a competition, especially since we're about 90% done in agreement with the Battlefield Foundation.
    • 00:08:54
      So at the next CTB meeting, CTB called it back and said, you know what?
    • 00:08:58
      We're going to continue with the public process.
    • 00:09:01
      We're going to have B. have public meetings.
    • 00:09:03
      have the community's input and then determine the path forward.
    • 00:09:07
      That path forward may continue to be giving the money to us and going to the foundation.
    • 00:09:11
      It may be another path forward, but the CTB and VDOT are currently deciding that.
    • 00:09:18
      The bottom line is we don't have this line item in our budget.
    • 00:09:20
      We never accepted the money and we'll see what the CTB does.
    • 00:09:24
      We still feel very strongly that that is a good future opportunity for passenger rail.
    • 00:09:30
      The legislation that the General Assembly passed on this quarter said you need to not preclude future rail use, so we feel like it's protected.
    • 00:09:39
      But we, VPRA, are in a waiting mode, and I wanted to update you for this because we have voted for the budget amendment.
    • 00:09:44
      You likely read the budget and said, hey, where's that amendment?
    • 00:09:46
      And so we're waiting for those public meetings to continue.
    • 00:09:50
      They've had three so far.
    • 00:09:52
      I believe the third one was the last week of April.
    • 00:09:54
      We're waiting to see next step fronts who need that.
    • 00:09:57
      So.
    • SPEAKER_10
    • 00:09:58
      That is the update.
    • 00:10:06
      Any questions?
    • SPEAKER_04
    • 00:10:14
      I think there were, and this is my personal opinion, I'm not speaking to the VPRA, there were a lot of folks that felt like there should be a competition.
    • 00:10:26
      And then there were a lot of folks that felt like, well, no, this company, this, this foundation has been around a long time.
    • 00:10:32
      They were created to do just this, and they're going to get the communities what they want.
    • 00:10:37
      But as I think everyone saw, there were a lot of public comments and the public was concerned that they wanted you to get a trail, a trail with a
    • 00:10:45
      Rail component would be very expensive and I think there were members of the public that didn't think it could be done and that's really what caused the tenants' opinion.
    • Mariia ZimmermanChair, Board of Directors
    • 00:10:53
      If I may, DJ, since I was at that CTV meeting, a big point that the Secretary was making in that meeting is that I think there had been an earlier commitment that VDOT was going to do public hearings and there would be a public process to get input.
    • 00:11:10
      That process didn't really happen because things moved more quickly.
    • 00:11:15
      And so the Secretary has consistently made it clear of he's not opposed to this project moving forward, but he is opposed to not doing public engagement.
    • 00:11:26
      And so it was really to say, let's take a break.
    • 00:11:29
      Let's ensure that the public participation process that we committed to as a state previously does play itself out.
    • 00:11:36
      And then we can come back after that process has happened to determine the pathway to move forward.
    • 00:11:42
      And so it really was, I think,
    • 00:11:44
      Some members of the CTV felt like we should just move forward.
    • 00:11:48
      Like time is of the essence.
    • 00:11:50
      Let's go quickly.
    • 00:11:51
      Others felt like, nope, that makes sense.
    • 00:11:53
      We should honor the commitment that we previously said as a Commonwealth we would do to have VDOT do those hearings.
    • 00:12:01
      And again, I think feeling like that was VDOT's commitment and responsibility earlier.
    • 00:12:05
      So it made more sense for VDOT than VPRA to be the lead for doing that since that was in place.
    • 00:12:10
      And so that was, I think, some of the tension I picked up in that meeting was like, should we keep moving forward or should we pause for public involvement?
    • 00:12:17
      The public involvement process, they have had several meetings and that is going to be moving forward.
    • 00:12:23
      So I think everyone shares a desire to make sure that process plays out, not delay things forever, to make a decision to come forward and move that.
    • 00:12:33
      So I know
    • 00:12:34
      VDOT and the Secretary are tracking this all pretty quickly.
    • SPEAKER_10
    • 00:12:37
      Well, that's good to hear because that's one of the reasons I couldn't vote for it.
    • 00:12:40
      It just came out so quickly.
    • 00:12:41
      And the local officials were completely blindsided by it.
    • 00:12:44
      And, you know, they wanted the process to continue.
    • 00:12:46
      So that's good to know.
    • 00:12:47
      So thank you.
    • SPEAKER_04
    • 00:12:49
      Any other questions?
    • 00:12:52
      Okay, update on our FY26 organizational goals.
    • 00:12:55
      We're going to talk more about this later, but we continue to be on track for ridership and revenue.
    • 00:13:01
      Even with the service reductions, we found that the trains are really, really crowded.
    • 00:13:05
      I'd love to say that that's all because of the great work that VPRA is doing, and look, VPRA, the team is doing great work, but a lot of that has to do with gas being over $4 a gallon, and people don't want to spend money on gas, so they're more likely to take the train.
    • 00:13:17
      Historically, you'll find that as gas prices go up, train ridership goes up as well.
    • 00:13:21
      But ridership and revenue, we're still in really good shape, even with good service.
    • 00:13:26
      Long Bridge continues to move forward on schedule, and you see we pretty significantly hit and exceeded a lot of those goals.
    • 00:13:33
      As you go across the river, either on the train or in your vehicle, you can see we are moving quickly, and as you can see, we've got a lot more videos and pictures coming up later.
    • 00:13:43
      Key milestones for other projects, we could talk previously about the bypass,
    • 00:13:50
      Challenge, and we have made the determination that we are not going to have the shoot fly sub-base completed by August.
    • 00:13:58
      We've had some delays because of utilities and we'll talk more about those later as well.
    • 00:14:02
      In particular, jet fuel pipeline that goes along that and we've
    • 00:14:08
      struggling the CSX and with the kind of Morgan to get that moved.
    • 00:14:12
      We feel like we have broken that log jam and we're moving it forward quickly.
    • 00:14:17
      But with the time we've lost, we are working with the contractor to try to communicate under that 10 month loss.
    • 00:14:24
      But there's not really for us to get that out of state.
    • 00:14:28
      So we are going to miss that, that goal.
    • 00:14:31
      Thankfully, we did get the fourth track construction started and we did get Franconia and Talorton, or we're on track to get Franconia and Talorton bid out by the end of August.
    • 00:14:42
      Those are in good shape.
    • 00:14:44
      And then the other update is the platform for New River Valley.
    • 00:14:48
      That concrete will not, the pouring has started, but it will not be completed by the end of June.
    • 00:14:54
      That was a pretty aggressive date.
    • 00:14:56
      Good news is we're still
    • 00:14:57
      on schedule to start service in 2027.
    • 00:14:59
      That schedule is not changing, but we're not going to get that done.
    • 00:15:03
      So there's one where we made an aggressive goal.
    • 00:15:05
      We tried to push ourselves.
    • 00:15:06
      We tried to push on each other.
    • 00:15:08
      We didn't hit it.
    • 00:15:08
      So that's another one we're going to miss.
    • Patricia DoerschMember, Board of Directors
    • 00:15:11
      The concrete pouring is delayed, but final project isn't delayed.
    • SPEAKER_04
    • 00:15:16
      We were hoping.
    • 00:15:17
      Yes.
    • 00:15:17
      Let me answer your question.
    • 00:15:19
      Yes.
    • 00:15:19
      We started the concrete pouring.
    • 00:15:20
      It will not be completed by June.
    • 00:15:23
      June was a very aggressive date.
    • 00:15:25
      Norfolk Southern didn't expect to get it done by then, but we were trying to have them get it done.
    • 00:15:31
      They said it was a possibility.
    • 00:15:32
      Now it's not a possibility.
    • 00:15:34
      Total project is still right on schedule.
    • 00:15:36
      The project end date is right on schedule and getting service to our friends.
    • 00:15:43
      Mike, you looked at me funny.
    • 00:15:44
      No?
    • 00:15:45
      Okay, good.
    • 00:15:46
      All right, so that's where we are at 26 organizational goals.
    • 00:15:49
      We've actually started with our staff.
    • 00:15:51
      pulling together what the 27 goals are going to look like.
    • 00:15:53
      And as we've done in the past, we'll bring those to you in the opposite time.
    • 00:15:59
      Any questions on goals?
    • 00:16:02
      Okay, here's where I'll start to go very quickly.
    • 00:16:03
      Passenger service updates continues to be good news.
    • 00:16:06
      The ridership, as we saw in January, when we came to buses, you see the kind of ship went down, but it continues to be on track with what we've seen in the past.
    • 00:16:16
      The buses have been really a big success.
    • 00:16:21
      They were so successful, in fact, that after January came, we had people in Richmond saying, hey, we want a bus too, so we added two buses to Richmond.
    • 00:16:29
      They are very well utilized, highly utilized, so that's a good news story.
    • 00:16:34
      Here, you see the ridership for the four different routes, and then in the bottom right, you see the express bus ridership pretty much as expected or higher than expected, so
    • 00:16:43
      It's broken down route by route.
    • 00:16:47
      You've got all this information.
    • 00:16:48
      No real surprises from what you've seen in the last couple of months in the off.
    • 00:16:54
      Additionally, in the interest of not being repetitive, that's we on our operation services team is willing to do a presentation that what we looked at in this course, I'll just call it the journey presentation.
    • 00:17:06
      It's not available.
    • 00:17:06
      So we need seven.
    • 00:17:09
      She's going to do.
    • 00:17:11
      And here you see a little more about the buses.
    • 00:17:12
      You see the ridership on the buses.
    • 00:17:14
      You've seen how we're doing.
    • 00:17:16
      The big story is that just like you've seen over the last few years, our ridership per train out there is higher than the states that we compare ourselves to.
    • 00:17:27
      So it continues to show that in Virginia, people, if you've got a train, people get on it.
    • 00:17:32
      Really is positive towards Long Bridge.
    • 00:17:35
      When we go from what's currently six trains to 13, you're going to see these ridership numbers continue
    • 00:17:41
      Customer Service Standards, this continues to be watched by all of the other states because we're the only state that has the customer service standards agreement with Amtrak.
    • 00:17:50
      As the chart on the bottom shows you from the beginning of time and then it goes down as time progresses, you see the first line across the number of reds versus the number of greens is very high.
    • 00:18:02
      Now we've got all the greens except for one, so it shows that Amtrak folks are paying attention to it and exploring high.
    • 00:18:08
      which means that our customers are getting the service that they're paying for.
    • 00:18:16
      On the cost recovery, we've talked about this the last couple of months, 94% is incredibly high, but it's artificially high because last year when we finished the year, our capital project allocation allocates way too much to capital and we're going to fix that and you'll see it fixed in the budget.
    • 00:18:38
      I'm happy to answer any questions if folks have them.
    • 00:18:54
      And then here's the operations by route through March because we're still the 21st, we don't have the final date of April date.
    • 00:19:06
      Okay, capital project update, I'm gonna turn over to Mike, but we've talked a lot about the rapid pace with which we are moving forward.
    • 00:19:14
      You see the picture here, this is of Long Bridge North.
    • 00:19:17
      That's the tressel that's being built over the Washington Channel.
    • 00:19:20
      Our internal team, this is just folks that are being their employees.
    • 00:19:24
      I said, you know, it'd be nice to show the board a video.
    • 00:19:27
      And I said this like a Friday afternoon at two o'clock in Monday.
    • 00:19:30
      They said, hey, take a look at this and see if you like, yeah, it's your performance time here, it's really been good.
    • 00:19:38
      Paul Internal has literally done over a weekend our ability to be hired on the floor.
    • 00:19:42
      But just a quick video showing some of the progress.
    • 00:20:12
      Thank you.
    • SPEAKER_04
    • 00:22:12
      I have no questions on the video, but I just want to note,
    • Mariia ZimmermanChair, Board of Directors
    • 00:22:41
      for DRPT and VDOT along the CTV members who are doing our district hearing.
    • 00:22:47
      And there have been a lot of compliments to VPRA that have come up, particularly those we had in the new river valleys.
    • 00:22:56
      Folks very excited about that progress and the pace of the construction that's underway.
    • 00:23:01
      Folks are excited about Roanoke and the station redevelopment opportunities around there.
    • 00:23:05
      And so it's just been exciting, whether it's been in Hampton Roads
    • 00:23:09
      out in Roanoke or other parts around the state where folks are really watching what's happening and are excited about that work that's underway.
    • 00:23:19
      So just wanted to relay that and kind of report from the field as we've been up and about.
    • 00:23:27
      Thank you.
    • Dallas Richards
    • 00:23:29
      Mike.
    • 00:23:32
      Thank you.
    • Michael McLaughlinChief Operating Officer
    • 00:23:33
      We, as DJ said, we are consistent with our EDR every month.
    • 00:23:37
      We put it on our website.
    • 00:23:39
      But when we have board meetings, we also have construction update reports.
    • 00:23:41
      So I'm going to skip through a lot of these because some of the good folks in the back of the room are going to come up in a little bit and discuss them.
    • 00:23:48
      I do want to point out, though, we have been having Long Bridge public meetings.
    • 00:23:51
      It's been well received.
    • 00:23:53
      And we are honest when we're out there.
    • 00:23:54
      We tell them what we can and can't do.
    • 00:23:56
      And that has been well received out there in the area.
    • 00:24:00
      One thing I do want to point out came up in the finance committee meeting.
    • 00:24:04
      Our chair did ask about our spend to date.
    • 00:24:08
      We didn't have the data right in front of us at the Finance Committee meeting.
    • 00:24:12
      As you can see, we've already spent on Long Bridge North, $275 million.
    • 00:24:16
      Now, a lot of that is the activities you see in the water.
    • 00:24:19
      Also, you have things like insurance and bonding and mobilization payments that are big upfront payments that are being made.
    • 00:24:25
      But these numbers are a lot bigger than they were in previous years.
    • 00:24:28
      So I just want to point that out because this did come up at the Finance Committee meeting.
    • 00:24:31
      So thank you.
    • 00:24:32
      Next slide.
    • 00:24:33
      And again, for all these, we're going to have construction update reports also with some videos, I'll show you in a few minutes.
    • 00:24:39
      Long Bridge South, the big part here is the test piles that we're going to show you a video on in a little bit.
    • 00:24:43
      And again, you see that actual 81 million spent on Long Bridge South, again, being the, sorry, I mentioned Long Bridge North, that's the work at Main Avenue, and this is the work over the Potomac.
    • 00:24:53
      I'll change the report track again, we'll come to the construction update report, but this is the area from
    • 00:24:58
      just about a half mile south of your seminary yard and Telegraph Road all the way out to where Long Bridge begins at the aquatic center.
    • 00:25:07
      And these numbers I should keep in mind are from March.
    • 00:25:11
      A lot of activity happening in April and May.
    • 00:25:15
      So these numbers will look a lot higher.
    • 00:25:16
      And I think the next one that can come off, I can guarantee you more than 2.6 million has been spent for anyone who's looked out the window and seen the construction cranes in Dallas, you can confirm that
    • 00:25:27
      This is numbers from a couple months ago before the big construction activities have happened.
    • 00:25:33
      Next slide.
    • 00:25:35
      The bypass, we're going to talk about this again later on today.
    • 00:25:38
      Again, also $199 spent this year to date.
    • 00:25:41
      And this year, this year meeting the fiscal year.
    • 00:25:43
      So these are July 1st through the end of June.
    • 00:25:47
      So we are coming up toward the end of the fiscal year.
    • 00:25:50
      Next slide.
    • 00:25:51
      Franklin & Lorton Third Track.
    • 00:25:52
      This is a project that will be going to procurement
    • 00:25:55
      Hopefully this summer CSX will be releasing the procurement.
    • 00:25:58
      So a lot of that money will be the $11.4 million spent so far is design money spent.
    • 00:26:05
      CSX, we're working with CSX closely.
    • 00:26:07
      This is intertwined with the Franconia Bypass Project.
    • 00:26:10
      Some construction activities have happened though.
    • 00:26:12
      Up here we call CP Beltway, which is north of the Franconia Station that CSX is basically in the groundwork for.
    • 00:26:20
      of some signal work that's happening, signal towers that will be going up.
    • 00:26:24
      And then if you ever take the train up, you'll see that work happening up in that area.
    • SPEAKER_10
    • 00:26:28
      Michael, so CSX leading camera, will they be also providing the oversight?
    • Michael McLaughlinChief Operating Officer
    • 00:26:33
      We don't really provide oversight.
    • 00:26:34
      We do it with them, yes.
    • 00:26:39
      New River Valley, again we talked about these already mentioned it and we'll probably be up here later to talk about that.
    • 00:26:45
      I was out there a couple weeks ago and I was before that I was out there a couple months ago.
    • 00:26:48
      It is amazing to see the amount of work that happens just when you go out every month or two.
    • 00:26:56
      A couple things I do want to point out here that are not in the construction updates report.
    • 00:27:01
      These are two projects that, oh sorry, the Rowan Yard project is a project that has to happen for
    • 00:27:07
      Service to happen in New Bern Valley.
    • 00:27:09
      We need to fix the work.
    • 00:27:10
      We need to get a mainline track through Roanoke Yards.
    • 00:27:13
      So that is a project that we need as a precursor to, and that we'll be finishing up, we believe later in 2026, time frame Rob's in the back room nodding affirmatively, yes.
    • 00:27:23
      The other project, Nolks and Wick Calvertine, is a seven mile double track south of Manassas.
    • 00:27:28
      They'll provide a lot of fluidity between Culpeper and Manassas.
    • 00:27:32
      That doesn't have to be done for the New Bern Valley work to happen, but still an important project.
    • 00:27:37
      Next slide.
    • 00:27:38
      Rob's going to talk about the siding projects, especially D, E, F, and C. Siding A, though, is a project that's coming first.
    • 00:27:48
      And for those Fredericksburg people, they just conveniently, for me, have to be sitting next to each other.
    • 00:27:53
      I do want to let you know that Leland Road is going to go onto the knife and be taken out of service starting in the February, March time frame.
    • SPEAKER_04
    • 00:28:00
      The actual road, not the train station.
    • 00:28:01
      The actual road, not the train station, yeah.
    • Michael McLaughlinChief Operating Officer
    • 00:28:03
      And our director of planning, Christine Pix, has been meeting with our PAMPO TAC
    • 00:28:07
      Technical Advisory Committees, and others, to let them know that, to the various folks in the fan folder, that that road get closed, there'll be detours and so on and so forth.
    • 00:28:18
      And we'll continue to communicate to you about that.
    • 00:28:20
      That, if people recall the Leon Road Bridge, in some ways it's its own project, it's the same project, but we had to go out for a different procurement for the road work, whereas we did the procurement for the road work and CSX is doing the procurement for the track work.
    • 00:28:35
      Next slide.
    • 00:28:36
      And again, these are the siting projects.
    • 00:28:40
      So this is all related to siting A. I mentioned the road work and kind of got ahead of myself already.
    • 00:28:46
      So you have the track work, you have the Leland Road, and you also have, so in areas like Stafford and Fairfax, when the utilities need to move further agreements with CSX, we are working with them and spreading and doing the work for them.
    • 00:29:01
      because we have the capability to do so so they can continue to do what they need to do.
    • 00:29:05
      And they're paying us back for this.
    • 00:29:06
      This is money they're paying us back for.
    • 00:29:08
      And that's also the case in Fairfax County as well.
    • 00:29:15
      And again, Ron could talk about all these sightings further down.
    • 00:29:20
      So not trying to skip over them, but we are going to cover these.
    • SPEAKER_10
    • 00:29:25
      I guess my question is for these preparements.
    • 00:29:28
      CFS is handling the procurement.
    • 00:29:31
      So do they use audited FRA rates?
    • 00:29:35
      I've never done a commercial procurement with a freight rail company.
    • Michael McLaughlinChief Operating Officer
    • 00:29:42
      How is that?
    • 00:29:43
      So we do all the environmental work and a lot of the public relations and all that work.
    • 00:29:47
      So we're very intertwined with CSX.
    • 00:29:50
      So CSX does go to their bench for design work.
    • 00:29:53
      And then they put out a...
    • SPEAKER_10
    • 00:29:55
      So that's like a commercial?
    • Michael McLaughlinChief Operating Officer
    • 00:29:56
      Yeah, they do a contract.
    • SPEAKER_10
    • 00:29:58
      So it's like a commercial contract that you get.
    • Michael McLaughlinChief Operating Officer
    • 00:30:01
      And we notify the board before CSX.
    • 00:30:03
      We're going to talk about that later on today with Franconia Lorton.
    • 00:30:07
      Jessica talked about that, how they're going out there.
    • 00:30:09
      We're going to be keeping you informed.
    • 00:30:11
      When these get to the point of going into construction, we're going to be updating you more and more.
    • 00:30:17
      Most of these, all these projects here are just entering 30% design.
    • 00:30:21
      These side of the project.
    • 00:30:22
      Now, if your question is, this says, yes, CSX will release the procurement for construction once we reach a certain level of design.
    • SPEAKER_10
    • 00:30:31
      But to answer the question more directly, so just curious, how does that work with the FRA audit rates?
    • SPEAKER_04
    • 00:30:41
      So on some projects, if there's federal money, there are flow downs from the grant that CSX has to comply with.
    • 00:30:47
      And if there's not federal money, then they don't.
    • 00:30:49
      So we've got to watch that very closely.
    • 00:30:51
      And that's when we talk about the budget, there's the fundability of the funds.
    • 00:30:54
      Now, CSX obviously has a bunch of unions that work for them.
    • 00:30:57
      So they've got agreements that they've got to
    • 00:30:59
      And there are some Amtrak money, now Amtrak contributed 944 million, that's considered federal money.
    • Michael McLaughlinChief Operating Officer
    • 00:31:13
      And that is on some of these projects, especially, I believe, like Siding Sea, I believe, which is, is not, it helps only Amtrak and freight trains, it doesn't have to be a re-turbatory.
    • 00:31:23
      Projects like that might tend to have more Amtrak money.
    • 00:31:28
      Next slide.
    • 00:31:30
      Richmond Area Projects, I want to point out how all here at Richmond are a labor facility.
    • 00:31:33
      We did receive 59 from CVTA.
    • 00:31:37
      Mariia, I believe you were the first ones to let us know we received that money.
    • 00:31:42
      Thanks to a gentleman from CTV as well, Mr. Davis, that helped us with that.
    • 00:31:47
      And we're also applying, there'll be a slide later, some of these projects we are applying for federal money as well.
    • 00:31:52
      And we're in the midst, we should find out in the next month or so, on money for Richmond Rail Facility, for Stanton Station,
    • 00:31:59
      and so on and so forth.
    • 00:32:00
      Also do want to point out, as I pointed out in Finance Committee, that the Richmond to Raleigh grant has finally been obligated by FRA.
    • 00:32:07
      North Carolina's lead on that, we are joint applicants, but for projects like Max River Bridge, that actually is kind of a big deal because it's our first chance of getting a look at what the scope would be for that Max River Bridge.
    • 00:32:19
      Right now, it's a single track.
    • 00:32:20
      That's the only single track in a two-track area.
    • 00:32:24
      It impacts Norfolk, it impacts trains down in North Carolina.
    • 00:32:27
      We have a staffer dedicated to working with North Carolina DOT and also the VDOT so well, because there's a lot of interface with I-85 especially in this area.
    • 00:32:38
      So that's another one I wanted to point out this page.
    • 00:32:40
      So it's good news that that conceptual engineering, if you are, has been kicked off and they have a deadline to finish by first quarter of 2027 with the conceptual engineering.
    • 00:32:50
      So we can get an initial cost estimate of not just projects like Atlantic River Bridge, but the whole
    • 00:32:56
      75 plus miles of Richmond to Raleigh S-Line project.
    • 00:33:00
      Again, for those who aren't familiar, this would be more along the I-85 route.
    • 00:33:04
      Currently, the route to Raleigh goes along 95, then it kind of cuts back northwest.
    • 00:33:09
      It's not the most convenient route.
    • 00:33:12
      This would make it more competitive with car travel.
    • 00:33:16
      Other capital projects, a lot of thoughts.
    • 00:33:18
      Another one I want to point out.
    • 00:33:19
      I know Dallas is here from VRE.
    • 00:33:22
      That is the last mile, if you will.
    • 00:33:24
      of our dedicated eight miles of passenger rail, two-track passenger rail corridor.
    • 00:33:30
      So that's a very important one, one that we need to finish, that uniformed bridge and alligator four-track are done and other projects are done.
    • 00:33:37
      If a lot of fine project isn't done, we don't get to add, go up to 13 Amtrak trains, we don't get to add weekend trains in VRE.
    • 00:33:45
      And as the project has a lot of FTA money on it, VRE and Dallas were working on this before VPRA existed,
    • 00:33:54
      and they have gotten to the point where they're in procurement.
    • 00:33:57
      So we can't say too much about it, I think, right?
    • 00:33:59
      Because we're in procurement, but they want to point out this important project moving far along.
    • 00:34:03
      And as you can see, they have some proposals due later this month.
    • 00:34:08
      Newington Railroad Bridge is a part of the, for a budget we keep it separate, but it's going to be part of the Franconia-Lorton procurement.
    • 00:34:15
      And one we're working closely with VDOT and CSX on.
    • 00:34:20
      I already mentioned the Fairfax County Utilities, so thank you.
    • 00:34:23
      And this is the summary.
    • 00:34:25
      A lot of these numbers are already in the individual slides.
    • 00:34:27
      So I was going to pass by this as a summary of your data actuals.
    • 00:34:32
      Same with the Western Rail projects.
    • 00:34:35
      Railway acquisitions, we talked to you about this a couple of years ago.
    • 00:34:37
      This was, we feel like we're at a good point here.
    • 00:34:41
      We had the survey work that we did, which was different from the original valve maps, valuation maps we had with CSX.
    • 00:34:48
      So we trued up the quarter, if you will.
    • 00:34:50
      So we feel a lot better about this now.
    • 00:34:54
      We are in the midst of completing a lot of acquisitions.
    • 00:34:57
      So when you get to that point, you see the light at the end of the tunnel.
    • 00:35:00
      Next slide.
    • 00:35:03
      So grant status update, you can see what is currently out there.
    • 00:35:07
      Now we did apply for 174 million for the Occoquan River third track.
    • 00:35:12
      That's not just the Occoquan River Bridge, it's four plus miles of track as well.
    • 00:35:16
      So from
    • 00:35:18
      Almost Lorton Road all the way down through Woodbridge Station.
    • 00:35:21
      This will give us money for design and for project development.
    • 00:35:26
      So that's a big one.
    • 00:35:27
      That'll be a big, Aquana River Bridge itself will be a big bridge, but so will Route 1, Furnace Road.
    • 00:35:31
      There's quite a few bridges in that.
    • 00:35:33
      So if you're wondering why that's only for design, there'll be a billion dollar plus project.
    • 00:35:39
      You'll be honest now to do that four plus miles plus quite a few bridges.
    • 00:35:46
      Also, I'm not going to read all these.
    • 00:35:47
      You see the build grants.
    • 00:35:48
      We are applying for some of them in the same, from different programs.
    • 00:35:53
      We've been told in the past that FRA likes that flexibility.
    • 00:35:56
      So they can mix and match what they need to do.
    • 00:35:59
      Obligating the grants is important as well.
    • 00:36:00
      As you can see, this luckily, not luckily, fortunately, our staff have been working hard and we are, more and more grants have been obligated.
    • 00:36:08
      So this should, this part should grow and this part should shrink as we move forward.
    • 00:36:13
      I think we've gotten a very good cadence with FRA and their staff.
    • 00:36:16
      Moving forward to obligating the grants.
    • Patricia DoerschMember, Board of Directors
    • 00:36:18
      Mike, can I just one thing that $729 million, that's a FED state partnership money, right?
    • 00:36:24
      And that's locked in, committed, obligatedly, right?
    • 00:36:29
      100% ours.
    • 00:36:29
      Yes.
    • 00:36:31
      The notion of it not going.
    • Michael McLaughlinChief Operating Officer
    • 00:36:32
      I talked to FRA last week.
    • 00:36:35
      The gentleman I talked to, the deputy administrator says he likes to work every time he goes over the bridges, whether it be in a train or a car.
    • 00:36:43
      So obligated, we're all set there.
    • 00:36:45
      That is, that was money for a Phase II project.
    • 00:36:47
      We determined, we elected to put it just on Long Bridge projects, both north and south.
    • 00:36:53
      But yes, that is money that's obligated and locked in.
    • Patricia DoerschMember, Board of Directors
    • 00:36:55
      It's off the federal books.
    • 00:36:57
      It's on ours.
    • SPEAKER_04
    • 00:36:58
      Well, we've not collected all of the money, but it's reimbursed to have it drawn down.
    • 00:37:03
      Okay.
    • 00:37:04
      But the level.
    • 00:37:06
      The level of risk there is what we're trying to do.
    • 00:37:09
      It's obligated and set aside.
    • 00:37:11
      The unobligated ones are always at risk because Congress can make decisions.
    • 00:37:15
      But once it's obligated, as long as you're continuing to comply with the grant agreement you're pitching.
    • Patricia DoerschMember, Board of Directors
    • 00:37:20
      Right.
    • 00:37:20
      I mean, we just know that some of these federal dollars are considering potentially being clawed back.
    • 00:37:26
      I know that Steve worked really hard end of December to make sure it's obligated.
    • 00:37:31
      I just want to confirm.
    • SPEAKER_04
    • 00:37:32
      If that's confirmed, anything under the federal grants obligated to fall into the, we've got a grant agreement.
    • 00:37:38
      And similar to, there have been other high profile projects where they have grant agreements and folks try to pull the money back and they went towards it and they can't pull it back because this is a side agreement.
    • 00:37:49
      So we feel comfortable.
    • 00:37:51
      And especially since we're continuing to make progress, we're continuing to make deadlines and fund grants.
    • 00:37:56
      So that stuff's low risk.
    • 00:37:58
      The other stuff, we have no indication that it's at risk, but until it's obligated, you don't
    • Laura FarmerChief Financial Officer
    • 00:38:02
      Right, right.
    • SPEAKER_04
    • 00:38:04
      And since you brought that up, I know there's a lot of press about a month ago where the president released the president's budget.
    • 00:38:10
      That happens every year.
    • 00:38:11
      Pretty low for transit, pretty low for public transportation.
    • 00:38:14
      That's the first shot across the bow.
    • 00:38:16
      That's nothing.
    • 00:38:18
      It's obviously something that we're watching closely, but we're not concerned.
    • 00:38:23
      Congress, House, and Senate have a lot to do, and we're comfortable that the good projects that are moving infrastructure and transportation forward, which is awesome.
    • 00:38:33
      Nothing to be alarmed about yet, but we'll watch it.
    • 00:38:38
      Thank you.
    • 00:38:40
      And then the only other thing I can butt in here, so continued butt in, I guess.
    • 00:38:45
      Under a waiting obligation, the second one there is a $56 million grant that we received, a CMAC grant for guest communication.
    • 00:38:52
      We came to the board last year.
    • 00:38:55
      and asked you all to give me the authority to enter into an agreement with DOT to have that grant agreement signed.
    • 00:39:02
      Unfortunately, when you all approve or give me the authority, I have that authority for 90 days and the final negotiations have taken longer than 90 days.
    • 00:39:11
      So what we're asking for today is to have you re-authorize that authority and give me that.
    • 00:39:18
      And spoiler alert, we'll talk later about the bylaws.
    • 00:39:20
      The bylaws very clearly say, when you give me the authority, I get it for 90 days.
    • 00:39:23
      We're going to ask you later to extend that time.
    • 00:39:26
      But for right now, what we're hoping to do is make a motion and give me the authority to once again enter into agreement.
    • 00:39:34
      We think it's going to come within the next few weeks.
    • 00:39:38
      It's going to come within the next few weeks, but we'd ask you to extend that authority for now.
    • Mariia ZimmermanChair, Board of Directors
    • 00:39:46
      My goodness, I made the announcement and then I didn't silence my own phone.
    • SPEAKER_03
    • 00:39:53
      Is this something that we have to go to FHWA directly about or is this part of the state's apportionment that they get from the Highway Trust Fund and then we are going to use a part of what the state gets?
    • Laura FarmerChief Financial Officer
    • 00:40:11
      Sure, it is part of Virginia's CMAQ apportionment.
    • 00:40:17
      and it was transferred from Federal Highway to Federal Rail and now we're in the throes of that agreement with Federal Rail.
    • SPEAKER_03
    • 00:40:25
      So just, and let me know if I'm jumping ahead too.
    • 00:40:28
      So did we have to go to Federal Rail and then do we have to go to the CTP to get this from the state's apportionment and then it comes to the VPRA?
    • Laura FarmerChief Financial Officer
    • 00:40:36
      We did it that first.
    • 00:40:37
      The CTP provided that allocation to the project and by that action started the pathway to move it from highways to rail
    • 00:40:46
      and now we're in the agreement stage.
    • Michael McLaughlinChief Operating Officer
    • 00:40:49
      That's a very good point.
    • 00:40:50
      On that grant statement and everything else, the discussion on grants, we apply for from the FRA or Youth Office of the Secretary.
    • 00:40:56
      The CMAC grant is, as you mentioned, through the state apportionment, so it is slightly different, but one we still have to go through processes for.
    • Mariia ZimmermanChair, Board of Directors
    • 00:41:07
      If I could also just notice if you go
    • 00:41:09
      That one, I just wanted to flag the Richmond layover facility that I think it's the city of Richmond, correct?
    • 00:41:15
      Let's put that in for SmartScale.
    • 00:41:20
      So just the process for that, that's for SmartScale 7, which are those applications are currently under review and analysis.
    • 00:41:29
      They're looking at the pre-application status now and then
    • 00:41:33
      VDOT would get back to applicants to let them know if they are invited to move forward to the next phase of the smart scale.
    • 00:41:40
      That would come before the CTB for final consideration of smart scale projects that would be funded.
    • 00:41:47
      I think that action happens in December for grants that would happen next year.
    • 00:41:51
      So just flagging that and that process that moves through.
    • 00:41:56
      So that may also be something as hopefully it continues to move forward.
    • 00:42:00
      That will be a discussion with CTB members to
    • 00:42:03
      I'll hopefully continue getting their support for the work.
    • Patricia DoerschMember, Board of Directors
    • 00:42:06
      How much are we seeking under SmartScale for that project?
    • Mariia ZimmermanChair, Board of Directors
    • 00:42:08
      17.8 million.
    • SPEAKER_04
    • 00:42:11
      And that's the- Okay, state grants, okay.
    • 00:42:14
      And we've asked, you can see on the chart, we've asked for that from a number of different places.
    • 00:42:18
      So we've got an Amtrak commitment.
    • 00:42:20
      We've got a CVTA commitment.
    • 00:42:22
      We're looking to get that last piece of that project.
    • Michael McLaughlinChief Operating Officer
    • 00:42:25
      Yeah, and original air facility is important because we need a place to put the trains when we're done Long Bridge and other projects in the Richmond area.
    • 00:42:32
      and three or four trains or so, depending on what the schedule is, whether they're layover or overnight, we need a place to put those trains.
    • 00:42:39
      There's not enough space to stable this mill, and frankly, we're doing a deadhead move right now in three-act yard, which is not optimal.
    • Mariia ZimmermanChair, Board of Directors
    • 00:42:46
      And then, I don't know, for CMAQ, do you want us to take action now, or should we leave each other?
    • 00:42:52
      Okay.
    • 00:42:52
      So, could we get a motion from someone on the board to approve ratification to execute CMAQ?
    • 00:43:02
      Agreement and provide the Executive Director additional time to be addressed by that.
    • Beth RhinehartMember, Board of Directors
    • 00:43:07
      So moved.
    • Mariia ZimmermanChair, Board of Directors
    • 00:43:08
      Second.
    • 00:43:09
      All in favor say aye.
    • 00:43:10
      Aye.
    • 00:43:14
      Those opposed say nay.
    • 00:43:17
      Anyone abstain?
    • 00:43:19
      The ayes have it.
    • 00:43:21
      Thank you.
    • Michael McLaughlinChief Operating Officer
    • 00:43:24
      And again, this is the summary of the year to date work so far.
    • 00:43:28
      A lot of this work
    • 00:43:29
      is one that I pointed out that takes that yard to move out.
    • 00:43:38
      We'll see that was a lot of these pick up in the next couple of years.
    • Dallas Richards
    • 00:43:41
      And I think that's it for me.
    • 00:43:42
      Hand it over to Laura.
    • Michael McLaughlinChief Operating Officer
    • 00:43:44
      Any questions for Mike on capital projects?
    • SPEAKER_03
    • 00:43:48
      Just that it's, you know, it is infrastructure week, right?
    • 00:43:51
      And so it's nice to, it's nice to, you know, see, I think, you know, there's a lot of products around the country that say people are still talking
    • 00:43:57
      The first view is our collections of the Commonwealth Rail Fund.
    • Laura FarmerChief Financial Officer
    • 00:44:23
      We still remain on target to meet the current year's
    • 00:44:27
      Revenue Estimate.
    • 00:44:29
      This is something I'm watching closely, just changes in driver behavior with gas prices that this may be of concern that we watch through the summer if these higher prices continue and affects their behavior.
    • 00:44:40
      So we're keeping an eye on this.
    • 00:44:42
      Next slide.
    • 00:44:44
      This just provides a view through March related to our investments and earnings.
    • 00:44:50
      We've earned $20.5 million to date based on those investments.
    • 00:44:55
      Next slide.
    • 00:44:57
      Through April 30th our gain of 1.9% which is slightly lower than our gain we reported in our January meeting but we still feel like that things are performing as they should.
    • 00:45:11
      And with regard to liquidity and the balance of the investments, this just provides a view of where we are today and the makeup of that.
    • 00:45:23
      Obviously with the maturities less than a year, this is something we'll be watching related to managing the resources available and the projects and their behavior and where we'll be drawing against our investments outside of the LGIP versus here and whether we need to rebalance this portfolio going forward.
    • 00:45:42
      That's likely a summer activity this summer for Selma and Charlie and I.
    • 00:45:45
      So we look forward to updates in this area.
    • 00:45:51
      and this just provides a different view of the return through April.
    • SPEAKER_04
    • 00:46:00
      Any questions on the financial stuff?
    • 00:46:02
      We can stay in the big budget presentation later.
    • SPEAKER_03
    • 00:46:07
      Laura, talking about the reallocation, are there like places that you think about, that you're thinking about, like is it commercial paper, right?
    • 00:46:15
      It's like getting, going to get smaller or getting larger or some other kind of asset classes?
    • Laura FarmerChief Financial Officer
    • 00:46:19
      There's some potential there.
    • 00:46:21
      We have some recommendations for METER to consider in the next couple of months and whether we would take advantage of some opportunities.
    • 00:46:28
      So I think, yes.
    • Patricia DoerschMember, Board of Directors
    • 00:46:31
      Is it still governed by the same investment principles, right?
    • 00:46:34
      There's no notion of changing those rules?
    • SPEAKER_04
    • 00:46:40
      Of course, ma'am.
    • 00:46:41
      All right, administrative updates.
    • 00:46:42
      Just current staff count.
    • 00:46:43
      We've got interns coming on board, which is always exciting.
    • 00:46:46
      They serviced a good pipeline for
    • 00:46:48
      and you see the interns listed there.
    • 00:46:51
      We have one non-intern hire starts next week, I believe, in financial planning analysis, and then you see the interns there going forward.
    • 00:47:01
      Here's a snapshot of our administrative budget.
    • 00:47:05
      Pretty much everything is in good shape.
    • Beth RhinehartMember, Board of Directors
    • 00:47:07
      DJ, I was curious, what schools do those students represent?
    • SPEAKER_04
    • 00:47:11
      I'm going to have to pull it up.
    • 00:47:16
      Later I'll be reporting to the board before school.
    • 00:47:20
      That's a good question though.
    • 00:47:22
      I'll get back to you.
    • 00:47:23
      Say I can draw Virginia, but I'll get back to you.
    • Michael McLaughlinChief Operating Officer
    • 00:47:26
      Some of the gentlemen and the ladies in the back of the room I think might have the information, so we might go to get that to you before the board meeting.
    • 00:47:33
      Thank you.
    • 00:47:34
      And West Virginia University.
    • SPEAKER_11
    • 00:47:37
      JMU, Jim Davidson, and West Virginia University, the Alexander intern.
    • SPEAKER_13
    • 00:47:42
      Mine's unfortunately Florida, but she lives in Toronto.
    • Beth RhinehartMember, Board of Directors
    • 00:47:45
      Are we able to take advantage of any of the intern funding that's available through BEDP?
    • SPEAKER_04
    • 00:47:56
      I don't believe we've explored that.
    • Beth RhinehartMember, Board of Directors
    • 00:47:59
      They changed the name of what used to be the BTOP grants, but it is set up specifically for offsetting employer costs for hosting interns.
    • 00:48:11
      Virginia has a target to increase the number of internships.
    • 00:48:15
      Thank you.
    • 00:48:19
      Here are the budget adjustments that were made in March.
    • SPEAKER_04
    • 00:48:31
      We just made a minor $3,000 change from IT services.
    • 00:48:37
      Contracting updates here.
    • 00:48:39
      Anytime there's a contact over $5 million, we notify you all five days in advance, and then anything over 50 we bring to the board.
    • 00:48:47
      Anything 250 or above, we just put in the EDR, and here is the list of those contracts.
    • 00:48:57
      Okay, supplier diversity.
    • 00:48:58
      We're going to be changing the way we update New York.
    • 00:49:03
      Reminder, these are the categories.
    • 00:49:06
      that we track against.
    • 00:49:14
      Here's our spending through the most recent quarter.
    • 00:49:18
      You see we've got 4.78% of spend.
    • 00:49:23
      Again, this is on the discretionary spend.
    • 00:49:26
      We have a lot of non-discretionary spending.
    • 00:49:28
      We've got to get money in CSX.
    • 00:49:29
      We've got to get money in the bulk of something.
    • 00:49:31
      We've got to get it to Amtrak.
    • 00:49:35
      This is below our goal.
    • 00:49:38
      And the reason I said that there's going to be a change is the recently lost paths that have made it different on how you can determine or make a determination to guess I'm a small business.
    • 00:49:49
      Yes, I'm a minority owned business, female owned business.
    • 00:49:52
      You no longer can just say this is me.
    • 00:49:54
      You've got to actually prove where you've been disadvantaged.
    • 00:49:57
      And so it changes the way we can look here, folks.
    • 00:50:00
      So we're going to I said that right, right, Michael.
    • Michael WestermannGeneral Counsel
    • 00:50:02
      You're close and we're going to talk about it more later.
    • 00:50:04
      It's the federal designation that has changed.
    • SPEAKER_04
    • 00:50:07
      So we're going to talk about it during Michael's legislative review, but we may see differences on how this is reported going forward because of this change.
    • 00:50:19
      And asking questions, I yield my time.
    • 00:50:24
      Thank you.
    • 00:50:24
      Any questions?
    • Mariia ZimmermanChair, Board of Directors
    • 00:50:27
      All right.
    • 00:50:28
      Well, we will move forward to item number eight then, construction updates.
    • Michael McLaughlinChief Operating Officer
    • 00:50:33
      Oh, really just an opportunity for me to tee up some of the folks in that room to come up.
    • 00:50:41
      And most of these folks should be familiar.
    • 00:50:45
      I know Charlene Claywood in New York today, she is taking another important meeting we have.
    • 00:50:50
      So Ian Langan, who was one of our Long Bridge ladies, can be here.
    • 00:50:54
      So with that, I'm going to let them have Cody.
    • 00:50:59
      Good morning.
    • SPEAKER_19
    • 00:51:00
      We'll jump right in.
    • 00:51:02
      Did you need to say anything about this mic?
    • Michael McLaughlinChief Operating Officer
    • 00:51:05
      It's just a good summary of the projects, though.
    • 00:51:07
      We reported a project that are under construction here.
    • 00:51:10
      So and as you can see, very happy to say we have a lot of stuff.
    • 00:51:15
      And again, some of these numbers are very similar to what I just showed you here.
    • SPEAKER_19
    • 00:51:20
      All right, we'll jump right into Long Bridge North.
    • 00:51:25
      All right, so we had a lot of exciting activity going on on the project.
    • 00:51:30
      We'll get into the listed activities here in a second.
    • 00:51:34
      But first, I want to remind you of the phasing that we're using to achieve the project here.
    • 00:51:41
      And in the project map, if I can make my pointer work, okay.
    • 00:51:48
      Railroad North is the top right of the screen.
    • 00:51:51
      Railroad South, obviously, to the bottom left.
    • 00:51:56
      So Phase 1 looks to build out a temporary alignment on the western side of the corridor in order for us to, at Main Avenue, start disassembling the bridge.
    • 00:52:11
      So you'll see a lot of photos of that here coming up, but that's what we're after for Phase 1.
    • 00:52:19
      Phase 2 then shifts to the east side of the alignment,
    • 00:52:22
      and there are several activities that SFJD, Skanska Flatiron is advancing in phase two as well.
    • 00:52:30
      Before we leave this slide, we'll call your attention to the upcoming activities.
    • 00:52:34
      We don't have any photos of these, but in a very short time, a matter of weeks, we are going to make a major maintenance of traffic shift on Main Avenue.
    • 00:52:44
      Currently, we're in the northern maintenance of traffic area.
    • 00:52:49
      We're going to make a shift to the southern and that's all for the phase one work at Main Avenue.
    • 00:52:56
      And really that shift allows other upcoming activities, including retaining wall G and the abutment at Main Avenue to take place.
    • 00:53:09
      All right, so getting into the activities.
    • 00:53:13
      You see on the left hand side that is Craft Wall D on the very left.
    • 00:53:18
      Crash Wall C rather, that's Early Works package four.
    • 00:53:22
      And on the right hand side, that's Crash Wall D and F, that was an Early Works package that was completed last year.
    • 00:53:28
      And this bay underneath Maryland Avenue Overbuild is where the temporary alignment of track three will shift from the right side of Crash Walls D and F, and we'll end up in this bay here.
    • 00:53:40
      So we're ready to construct track here on the northern portion of phase one.
    • 00:53:46
      So that's a great new story here.
    • 00:53:48
      And then you also see Skanska Flatirons Field Offices located in East Potomac Park.
    • 00:53:53
      Those were completed and everybody's moved into that facility.
    • Michael McLaughlinChief Operating Officer
    • 00:53:57
      Even if I can't address, we'll see.
    • 00:53:58
      Isn't that where each track used to be?
    • SPEAKER_19
    • 00:54:01
      And it belonged that way?
    • 00:54:03
      Correct.
    • 00:54:03
      There was a stub track that was used for storage that ran in this area.
    • 00:54:10
      We demolished that track in order to make room to make these accommodations.
    • 00:54:17
      Again,
    • 00:54:17
      Maryland Avenue Overbuild.
    • 00:54:18
      We had to do this crash wall work, right?
    • 00:54:20
      We had to bring up the crash wall, strengthen them in order to protect the structure overhead, right?
    • 00:54:31
      So next, we recently completed CSX Duff Bank.
    • 00:54:34
      There is a Duff Bank that runs through the alignment that holds five fiber tenants.
    • 00:54:41
      This is located up in the right-of-way.
    • 00:54:43
      And what we're doing here is relocating it to a place where we can then further deconstruct the right-of-way and then build out new infrastructure.
    • 00:54:53
      So the right-hand picture here is the connection of the existing CSX Duck Bank to the new alignment.
    • 00:55:01
      And then on the far side, you see this in East Potomac Park, just adjacent to the old National
    • 00:55:10
      Park Service Headquarters.
    • 00:55:13
      This is where it'll actually jump into another duck bank and temporarily run underneath Washington Channel.
    • 00:55:19
      Again, this is very important for us to start taking down old infrastructure, right?
    • 00:55:26
      While we have completed a section of this, there's more to come north of here in order to completely get this out of the way.
    • 00:55:36
      All right, next, I'll call your attention to the left-hand
    • 00:55:40
      That is the Maryland Avenue overbuild and the crash walls that we saw about two slides ago.
    • 00:55:45
      Again, this is phase one construction.
    • 00:55:50
      We've completed the northern portion inside the overbuild and we're working our way south, right?
    • 00:55:55
      The construction you see in both of these photos is actually retaining wall L construction along the western side of the corridor, and that's going to support temporary track three, but it will end up being a permanent track alignment.
    • 00:56:10
      So we need to get this retaining wall in place in order to build track on top of it.
    • 00:56:16
      Then you see on the right-hand picture, but in the left corner, that's Main Avenue, what we call Maiden Lane, where they're working on the foundation elements, Maiden Lane.
    • 00:56:29
      So that is that northern phase of the maintenance and traffic scheme.
    • 00:56:36
      There's a cast-in-place section on the left-hand side, and this is a drilled shaft post and panel wall on the right-hand side.
    • 00:56:46
      All right.
    • 00:56:48
      Activities I talked about were phase one.
    • 00:56:50
      This is SFJV pulling activities in phase two forward where they're able to.
    • 00:56:55
      This is supportive excavation work at Ohio Drive.
    • 00:56:59
      They're doing this on the east side of the alignment again.
    • 00:57:02
      They'll build out this wall
    • 00:57:06
      as temporary law to support the embankment and then begin the bridging foundations behind it.
    • 00:57:15
      Next, we see the Washington Channel Trestle.
    • 00:57:19
      DJ touched on it a little bit earlier and gave you a different vantage point.
    • 00:57:23
      This is very important because once we move into that maintenance and traffic south area along Main Avenue, this trestle will actually feed the job, right?
    • 00:57:35
      So equipment and material that are sizable that we don't want to bring in by road on Main Avenue and further create congestion on the roadway.
    • 00:57:44
      We're going to bring in separately through National Park Service land, bring it across the Washington Channel and land in the marina, the former Washington Marina parking lot.
    • 00:57:55
      We recently were, Amtrak actually was recently able to acquire that property.
    • 00:58:00
      So we are now able to fully build out the trestle into that parking area, which is lining up perfectly with this traffic shift in Main Avenue.
    • Beth RhinehartMember, Board of Directors
    • 00:58:08
      I'll ask a quick question.
    • 00:58:09
      What happens to that after?
    • SPEAKER_19
    • 00:58:11
      It'll be removed.
    • Beth RhinehartMember, Board of Directors
    • 00:58:12
      What?
    • SPEAKER_19
    • 00:58:13
      It'll be removed.
    • 00:58:14
      This is temporary.
    • 00:58:16
      Temporary for five years.
    • Patricia DoerschMember, Board of Directors
    • 00:58:18
      And can you just give me coordinates on that?
    • 00:58:20
      That's coming from north side, built out south?
    • SPEAKER_19
    • 00:58:25
      We're starting in East Potomac Park, which would be the southern end, and working our way across the channel, working our way north.
    • Patricia DoerschMember, Board of Directors
    • 00:58:34
      Okay, thank you.
    • SPEAKER_19
    • 00:58:34
      Yes, that's correct.
    • Michael McLaughlinChief Operating Officer
    • 00:58:37
      The boat's in the area.
    • 00:58:39
      Ohio Drive is where a lot of people park for cherry blossoms on the right-hand side.
    • 00:58:44
      There's Ohio Drive, there's some tennis courts over there, golf courses over there just off on the right-hand side.
    • Patricia DoerschMember, Board of Directors
    • 00:58:48
      Okay, good.
    • 00:58:49
      That's helpful.
    • 00:58:50
      Thank you.
    • SPEAKER_19
    • 00:58:54
      And then we move into Main Avenue Foundation construction.
    • 00:58:58
      On the left-hand side, you see here two micro tiles are in place, and then the pile cap, right, which is the beginning to really come out of the ground for the foundation at Main Avenue.
    • 00:59:13
      So again, I told you we're working in the northern maintenance and traffic area.
    • 00:59:19
      This is that work that's taking place, building out the northern abutment and Pier 2.
    • 00:59:24
      We shift south.
    • 00:59:26
      That's our opportunity to start to do the same work, but for Pier 1 and the southern abutment.
    • 00:59:33
      All building out the area where we can then shift the track to the west and then start disassembling this existing bridge.
    • 00:59:40
      This is the critical path of Long Bridge Law.
    • 00:59:44
      Any other questions on north or south?
    • 00:59:50
      All right, so right now, the Long Bridge Rail Partners, which is the tri-venture of Trumbull Way, FAY, rather, and Wagman.
    • 01:00:04
      Right now, they're engaged in their test pile program.
    • 01:00:06
      They have completed the test piles out on the water.
    • 01:00:09
      We'll see some of that activity in some short videos here in a moment.
    • 01:00:16
      built out their marine access bulkheads, which is allowing them to walk equipment on and off the water.
    • 01:00:24
      And then upcoming work that we don't have photos of, they're going to start construction of the rail bridge, both on the Virginia side and the DC side and shore for her.
    • 01:00:39
      Once those are constructed, we do have a time of year restriction through July activity on that
    • 01:00:47
      All right, so those recently completed activities.
    • 01:00:55
      On the left-hand side, you see the Bradley Point lay down area.
    • 01:01:00
      In this area, the Mount Vernon Trail also runs, and we are realigning that trail.
    • 01:01:07
      It's heavily utilized by the Viking community.
    • 01:01:10
      We need to
    • Michael McLaughlinChief Operating Officer
    • 01:01:13
      And then on the right hand side, you see that
    • SPEAKER_19
    • 01:01:42
      Bulkhead has been constructed.
    • 01:01:43
      You see the Wamani Yellow Line in the background.
    • 01:01:46
      This is the Virginia Shore.
    • 01:01:47
      On the right-hand side is the existing Long Bridge.
    • 01:01:51
      Here they've got a crane that recently completed the test file and is actually walking off the water.
    • 01:01:59
      They are currently reassembling the same crane on land in order to perform the land side test file.
    • 01:02:09
      All right.
    • 01:02:12
      Actually, a short time ago they completed, so it's no longer ongoing, but completed this obstruction probing.
    • 01:02:21
      There is existing scour protection in the river bottom, which is just sizable rocks that exist around the existing piers.
    • 01:02:30
      That's put in place to ensure that during flood conditions, the foundation isn't undermined.
    • 01:02:39
      So some of that
    • 01:02:40
      Based on some of our survey work, look to be in the pathway of our aisle layouts for the rail bridge.
    • 01:02:50
      We have determined that those obstructions are not in our way, which is a very big win for the project.
    • 01:02:57
      And then on the right hand side, you see them finishing off the water test pile for the rail bridge.
    • Michael McLaughlinChief Operating Officer
    • 01:03:02
      And these are both taken from the DC side.
    • 01:03:04
      So this is near NPS Park headquarters.
    • Patricia DoerschMember, Board of Directors
    • 01:03:07
      And how close is that?
    • 01:03:09
      Where are the testing structures there?
    • 01:03:11
      How close is that to the alignment, the ultimate alignment of the bridge?
    • SPEAKER_19
    • 01:03:16
      These are, I'll say the search and probing actually took place where the final alignment would be.
    • 01:03:26
      The test pilot will perform the close vicinity within 30 feet or so, right?
    • 01:03:31
      We get enough data to really be able to project that across the river.
    • SPEAKER_12
    • 01:03:42
      I'm Jeremy Rogers with the Long Bridge Rail Partners.
    • 01:03:46
      We are here for our test pile program.
    • 01:03:48
      This is our 36-inch test pile.
    • 01:03:50
      What we're doing is driving this pile to make sure that all of our engineering assumptions are accurate for the depth of the pile and the capacity of the pile.
    • 01:04:02
      We are also checking, we'll be monitoring sound, so how much noise is traveling through the water when we're doing the activity, and we're also going to be checking
    • 01:04:12
      seismic activity on the river bottom while we do this to also make sure that that data corresponds with what the assumptions were made in our engineering.
    • 01:04:31
      After this pile is driven we get a lot of data gathered from that.
    • 01:04:35
      Then there is another test we do to this pile is a statinamic test and what that does is
    • 01:04:42
      It pushes a lot of force into the pile, and we get data from that force activity that says, hey, this pile has this amount of capacity, which, again, is very key to proving all of our engineering.
    • SPEAKER_19
    • 01:05:01
      This is the test that, that test rather that Jeremy referred to.
    • 01:05:11
      We've got one more.
    • SPEAKER_01
    • 01:05:14
      Oh, okay.
    • 01:05:47
      We had our first statinamic test go off here a short time ago.
    • SPEAKER_00
    • 01:06:03
      Everything went well, went off safe.
    • 01:06:06
      Next steps are to take the data back to the office and analyze it and determine our true pile capacity.
    • SPEAKER_19
    • 01:06:23
      That's a standard test.
    • 01:06:25
      We've performed two of those in the water so far.
    • 01:06:28
      So we've got two more to go, both on lakes.
    • 01:06:30
      A lot of things were on the seashore.
    • 01:06:33
      A lot of effort went into communicating with the greater community about what was going to take place.
    • 01:06:40
      This is a controlled explosion.
    • 01:06:43
      We do have the Pentagon in the close vicinity here.
    • SPEAKER_04
    • 01:06:48
      I'm sure that we're reaching out to them.
    • 01:06:50
      Yeah, we actually, Ian, sorry to interrupt, but we do a lot of public meetings, community meetings, and we had one a couple weeks ago, correctly, but Naomi, who's on our team, was speaking there, and said, look, this is what's going to happen, this is what it's going to be, and they just were standing ovation, basically, for her honesty and just her standard, and it was people that were like, I've never seen a public meeting like this.
    • 01:07:13
      It's really been a good experience for me.
    • Patricia DoerschMember, Board of Directors
    • 01:07:19
      Alright, I keep having questions on this.
    • 01:07:22
      That's clearly testing something for capacity or what are we testing by?
    • SPEAKER_19
    • 01:07:27
      We're ensuring that our assumptions for pile size and length, the foundation elements that will go into the river bottom are correct.
    • Patricia DoerschMember, Board of Directors
    • 01:07:39
      By a mini explosion?
    • SPEAKER_19
    • 01:07:42
      Yes, so they're sending
    • 01:07:44
      Force down into the pile, right?
    • 01:07:46
      And they've got gauges on the pile that are able to read what the capacity of the pile is based on that.
    • Patricia DoerschMember, Board of Directors
    • 01:07:54
      To take the force?
    • SPEAKER_04
    • 01:07:55
      So basically I've got a wall, and I think that wall can withstand a 30 mile an hour thing.
    • 01:08:00
      So if you punch it at 29 miles an hour, it doesn't break, you feel good.
    • Patricia DoerschMember, Board of Directors
    • 01:08:04
      So we're not testing to failure, we're testing to somehow within our calculated capacity.
    • SPEAKER_13
    • 01:08:09
      Correct.
    • Patricia DoerschMember, Board of Directors
    • 01:08:10
      Okay.
    • SPEAKER_13
    • 01:08:11
      I think you've done that now.
    • 01:08:13
      Yeah, you did great.
    • SPEAKER_19
    • 01:08:16
      All right, one more person out here.
    • 01:08:19
      Again, I touched on the Mount Vernon Trail realignment.
    • SPEAKER_04
    • 01:08:23
      This is a graphic that depicts what will happen.
    • SPEAKER_19
    • 01:08:29
      This hatched area is our work zone.
    • 01:08:31
      You see the red existing path running right through it.
    • 01:08:35
      In order to safely maneuver in this area, we needed to relocate the trail.
    • 01:08:41
      The relocated trail will actually hug Mount Block
    • 01:08:47
      The George Washington Memorial Parkway and the sneak underneath the bridge just adjacent, the existing bridge just adjacent to the parkway.
    • 01:08:57
      Obviously, pretty impactful work.
    • 01:09:00
      This was scheduled to happen in late May, but now with the weather actually this weekend, we're anticipating it will push into Virginia.
    • Michael WestermannGeneral Counsel
    • 01:09:13
      Any other questions?
    • SPEAKER_10
    • 01:09:15
      DJ, do we have all of our funding sources for North, North, South identified?
    • 01:09:21
      Does that include the PTA money?
    • SPEAKER_04
    • 01:09:23
      I don't believe it's the PTA money.
    • SPEAKER_10
    • 01:09:24
      Does it include the PTA money in either North or South?
    • 01:09:26
      I don't think so.
    • SPEAKER_04
    • 01:09:28
      It's exactly from this.
    • SPEAKER_10
    • 01:09:30
      Okay.
    • SPEAKER_11
    • 01:09:34
      Good morning, Madam Chair and Board.
    • 01:09:36
      My name's Jeff Peltier.
    • 01:09:37
      I'm Senior Director for Engineering and Construction, Northern Virginia.
    • 01:09:41
      We're going to continue our march south and get on Alexandria's fourth track.
    • 01:09:45
      Certainly not as glamorous as its neighbor to the north at Long Bridge, but no less important.
    • 01:09:51
      This is where we're picking up where Long Bridge leaves off, building out the four-track corridor another six miles down into Alexandria.
    • 01:09:59
      We're building this.
    • 01:10:00
      This is really the busiest, most congested rail segment in Virginia.
    • 01:10:05
      That's where the five tracks come together.
    • 01:10:06
      The tracks from south in Richmond and Fredericksburg meet up with the tracks from out west, Roanoke, Lynchburg, and Manassas.
    • 01:10:14
      So we've been under construction with CSX in the lead since January, and we're going to continue doing this really for the next 18 months to a year, two years to get it done.
    • 01:10:25
      The work that we've been doing in the last few months has really been involved in getting our site set up, access, staging, those sorts of things.
    • 01:10:32
      With CSX's contractor, they have a site contractor, Fay S&B, that is doing the work, and then CSX is also self-performing some of that work.
    • 01:10:40
      The work that we're focusing on right now is that we have three control points or areas where we have switches, crossovers, signals to move trains around in the corridor.
    • 01:10:50
      One is at the very north, Long Bridge is called the RO interlocking.
    • 01:10:54
      There's another one right about the midway point in Alexandria called Slayers Lane.
    • 01:10:57
      There's another one at the end called the AF interlocking.
    • 01:11:00
      So we've been working on the RO interlocking and Slayers Lane control points.
    • 01:11:05
      There's a lot of work that's going on.
    • 01:11:07
      Just set up the track, set up the track that's going to be coming in and get it ready for four track operation.
    • 01:11:13
      And once those control points are done later this year, we'll start marching the fourth track down from Arlington into Alexandria.
    • 01:11:22
      We are still working on utilities in the Alexandria corridor, as Ian alluded to earlier.
    • 01:11:27
      There are five different fiber optic utilities that are along this corridor that are in different places.
    • 01:11:33
      And what CSX has done over the last two years, they've built a common duct bank, as you saw in Ian's photo, and have been wrangling those five fiber optic tenants to actually get into that common duct bank so that we can build our track.
    • 01:11:47
      Right now, where those fiber optic lines are, are where we're planning to put in infrastructure.
    • 01:11:51
      And it has been a challenge.
    • 01:11:52
      We've got all that duct back in place.
    • 01:11:54
      The cable is pulled.
    • 01:11:56
      Just the last piece that we need to do is actually splice the new cable into the system and turn it on.
    • 01:12:01
      It's called cutover.
    • 01:12:02
      We were planning to do that by the beginning of this year but then the conflict in the Middle East happened and the Federal Government Department of War said no cutovers, we're not taking any fiber optic out of service, you need to wait until things have cleared up and we've actually just started the cutovers again this past month.
    • 01:12:19
      They started at the beginning of May and they're going to continue through the end of the summer.
    • 01:12:25
      Just a couple of photos of what's been going on.
    • 01:12:27
      I mentioned this is RO, so that's the Long Bridge Aquatic Center.
    • 01:12:30
      that you see on the left there.
    • 01:12:32
      There was some out of service track that we've demoed out.
    • 01:12:34
      We started getting that ready to go.
    • 01:12:36
      And on the right, you just see some of the work we have to do just to get the site ready to bring in all these prefabricated track panels that are assembled and plants off site.
    • 01:12:44
      They're brought in by rail, and then they're assembled on site.
    • 01:12:49
      And again, you see some of these hints that we've been doing to figure out where the existing fiber optic and utility lines are.
    • 01:12:57
      Those are all getting moved into a conduit that's on the other side of the tracks.
    • 01:13:01
      And that's all processing.
    • 01:13:02
      So that's been ongoing.
    • 01:13:04
      And then over here, you also see some additional signal work that's going on.
    • 01:13:10
      This is the work at Slater's Lane.
    • 01:13:12
      Again, not the most numerous stuff in the world.
    • 01:13:13
      It's correct, but it's also being done under the existing
    • 01:13:19
      freight and passenger traffic, right?
    • 01:13:21
      So again, most congested segment of track in Virginia, anywhere from 50 to 80 trains a day, we have to maintain that traffic while we're doing this work.
    • 01:13:30
      Some of it's happening at night, some of it's happening on the weekends and whatnot.
    • 01:13:33
      So it's very important that we get it done when we can.
    • 01:13:36
      And just off to the right, as I mentioned, these are some of the right-of-way acquisitions we did for the project to get staging.
    • 01:13:41
      This is off in Alexandria.
    • 01:13:43
      You can see just very far into that photo is the Potomac Yard Metro Station.
    • 01:13:47
      This is an area of land that the city jointly operates with Metro and we've been able to use it as well.
    • 01:13:54
      So some good partnership going on there between all the organizations.
    • 01:14:00
      Okay, Alexandria Station improvements came Commonwealth Bridges project.
    • 01:14:03
      This is probably our most advanced project in the Northern Virginia area.
    • 01:14:08
      I think we've explained it many times before we have multiple projects that are just across the street from us here.
    • 01:14:13
      In fact,
    • 01:14:14
      If you're listening carefully, there's that ringing noise that's in your ear.
    • 01:14:18
      That is the sweet sound of a vibratory impact pile hammer.
    • 01:14:22
      Only an engineer could love, but that's progress.
    • 01:14:25
      And welcome to it at some point today, you can go out and see the work that's been going on with the three cranes that are out there.
    • 01:14:33
      Great to see.
    • 01:14:33
      And we're really moving forward with VRE in the lead.
    • 01:14:37
      So as we've mentioned many times before, we combine the bridge project with the Alexandria Station improvements project,
    • 01:14:43
      VRE and Dallas' team is in the lead with Kakosin Construction Company doing that work.
    • 01:14:50
      This is a very challenging project, a lot of work that has to get done in a very tight corridor.
    • 01:14:54
      And not only that, it starts off hard.
    • 01:14:57
      It's not only these projects that kind of builds up to a crescendo of work, it starts off with some of the hardest work right up front.
    • 01:15:02
      And that's what we've been doing over the last few weeks here doing the jump span work, which I'll show a few photos of here in a minute.
    • 01:15:10
      In the last few months, the contractor for coasting, they've mobilized in at the old parking lot, the gravel parking lot right next to Alexandria Station.
    • 01:15:19
      It's called the Callahan Yard now.
    • 01:15:21
      We've taken it over for lay down and office space.
    • 01:15:25
      We did a great job with us, BRE, negotiating with the City of Alexandria.
    • 01:15:30
      They used to use this as a parking lot for their city vehicles.
    • 01:15:33
      They've actually been able to move off site and we're using it now for the project.
    • 01:15:37
      And then you see here all the work that we're doing in a very tight space.
    • 01:15:41
      three very large cranes, some of the biggest cranes you'll see in the region doing this work.
    • 01:15:46
      And it's, again, just wonderful to see in here.
    • 01:15:50
      I mentioned challenging work up front.
    • 01:15:52
      I actually briefed this at the board meeting back in January.
    • 01:15:55
      What we need to do, again, to keep building this work while maintaining all the rail traffic that we have in the corridor, we essentially have to build the bridge while it's still operating.
    • 01:16:05
      So what we do is this thing,
    • 01:16:08
      A practice under the banner of what we call accelerated bridge construction or ABC.
    • 01:16:13
      We're building these things called jump spans.
    • 01:16:16
      And what the jump span is essentially extending the bridge, building a bridge behind the bridge, and creating a space to build the new foundation for the new bridges.
    • 01:16:24
      So we essentially create this new span, excavate it out, and you start building that foundation behind the existing bridge while the existing bridge is still in service.
    • 01:16:34
      And we have to do this at three locations for all three tracks.
    • 01:16:38
      In the area, so there's nine different jump spans that have to get built, and we do them over the course of three different weekends.
    • 01:16:44
      We started the first one beginning of the month.
    • 01:16:47
      That took, I think the outage started on a Friday, we went into a Wednesday morning.
    • 01:16:51
      We have the next jump spans that are starting next weekend on track two, and then track one will be two weeks after that in the middle of June.
    • 01:17:01
      So many activities that have to happen in such a short space of time to make the jump span go into operation.
    • 01:17:07
      I'll just go through a couple of photos of the work that has to happen.
    • 01:17:10
      CSX comes in, shuts down the track, actually cuts the track out and removes it.
    • 01:17:17
      The contractor, Kakosin, comes in and starts putting in these sheet piles, which is what you're hearing getting driven right now, which is supports all of the earth that supports the track.
    • 01:17:26
      And then over here you see some cylindrical or circular piles that are actually supporting the beams for the jump span.
    • 01:17:32
      Those have to get driven in as well.
    • 01:17:34
      And we're under some pretty strict requirements from the city on noise.
    • 01:17:37
      They have to be done during daytime hours.
    • 01:17:39
      They have the really short window to get all these piles done in time at three different locations per weekend.
    • 01:17:47
      You see again here where the track was actually cut out in the areas getting prepared to see more of that.
    • 01:17:54
      The sheet piles right here getting vibrated in place, and then the cylindrical piles that the beams go on, those get cut off to get that span going.
    • 01:18:04
      These are the actual jump span beams that were getting installed.
    • 01:18:07
      Once they're installed, back filled, put into place, CSX then comes back in, puts that track section that they cut out back on top of the beams, and gets the track in service for the next morning.
    • 01:18:19
      This is what it looks like after it's done.
    • 01:18:20
      You see, you wouldn't even know the difference.
    • 01:18:22
      But that's the beam that we just showed with the new track on top of it.
    • 01:18:26
      And we're running VRE and Amtrak trains the next morning.
    • 01:18:34
      I also mentioned too, we are under a mandate from the FRA to keep two boarding edges at Alexandria in play or operable at all times.
    • 01:18:42
      So we've built out a new platform
    • 01:18:45
      at Track One, which was previously really never used at Alexandria Station.
    • 01:18:49
      So now we have an ADA accessible platform, and we're able to use Track One now when we take the various tracks out of service when we're putting these jumps back in place.
    • 01:18:59
      So it's been a great operation, a ton of work going on, still a lot left to do before June.
    • 01:19:05
      And then we can actually start building the new bridges and start building the track, the platform as well.
    • 01:19:11
      I think that's it for Alexander, but I did want to pass to Dallas if you wanted to add any comments to that.
    • Dallas Richards
    • 01:19:17
      I would love that, thank you.
    • 01:19:18
      And yes, you could hear the hammer a few minutes ago.
    • 01:19:22
      I'll point out to sort of repeat, but 83 trains a day roughly.
    • 01:19:28
      And so between the noise restriction at night and 83 trains a day, that doesn't leave a lot of time to build things, right?
    • 01:19:35
      So it's a very complicated dance that we do.
    • 01:19:41
      Back to the fourth track for just a moment, the two diamonds on that, the VRE stations within the footprint of the fourth track.
    • 01:19:48
      The nature of this, it's a very complicated choreography between projects and a delay in their project could have a benefit to ours and vice versa.
    • 01:19:59
      Like it's this weird sort of thing where there's things that we have to do first before they can come, or things that they have to do first before we can come.
    • 01:20:06
      And so when any one of those things gets off, it can complicate things even
    • 01:20:10
      even more.
    • 01:20:11
      So for instance, the fiber optics and things that we're dealing with there, we have lay down areas where those fiber optics have to go, handholds for those.
    • 01:20:19
      So it's very complicated.
    • 01:20:21
      I applaud the VPRA team.
    • 01:20:23
      We've been working very closely together with them and will continue to work very closely together with them.
    • 01:20:28
      Having these baseline schedules are very important and working together very important.
    • 01:20:32
      So yeah, let's keep it up and coming with this big outage coming in next week, it's
    • Michael McLaughlinChief Operating Officer
    • 01:20:39
      Now our next opportunity is... Shout out to Amtrak, working closely with them to make sure the operation is continued.
    • 01:20:46
      A lot of changes for passengers the past few months, and you will see the re-employees out there.
    • 01:20:52
      Some of us will often go out and train early and help people out.
    • 01:20:56
      Amtrak has had people out on the platform for every train that's out there, whether it's me or Amtrak.
    • 01:21:02
      So kudos to another good team effort.
    • 01:21:04
      I'm sorry I cut off.
    • SPEAKER_10
    • 01:21:06
      The Long Bridge is right up here, right?
    • Dallas Richards
    • 01:21:08
      They're both right there.
    • SPEAKER_10
    • 01:21:10
      Are those roads close then?
    • Dallas Richards
    • 01:21:12
      During the outage and only during the change.
    • 01:21:15
      So when we do these jump span installations two weeks ago, we took out King and Commonwealth Streets both.
    • 01:21:20
      And that is the complicated nature because the proximity of these two bridges and the track geometry, you can't do them.
    • 01:21:27
      They have to all be surfaced and lined all at the same time.
    • 01:21:32
      We built, we literally built three bridges in five days.
    • 01:21:35
      and then turn around two weeks later and do it again, and then turn around two weeks later and do it again.
    • 01:21:39
      And so it's like starting a marathon in the spring, right?
    • 01:21:43
      Literally, you know, 800 yard sprint.
    • 01:21:45
      So very, very difficult and very, very exciting.
    • 01:21:48
      I've also mentioned to Dallas through the outreach effort has been great too.
    • SPEAKER_11
    • 01:21:52
      I mean, it really has.
    • 01:21:52
      But that roadway closure, I thought it was going to be traffic apocalypse here.
    • Dallas Richards
    • 01:21:56
      I think it wasn't.
    • 01:21:59
      It's almost like it flows better.
    • 01:22:01
      It might be better actually with Dallas instead.
    • 01:22:06
      The outreach work between our two agencies especially has been one very, very good effort.
    • 01:22:16
      My project manager, Jason Boyd said it's been basically two nights a week.
    • 01:22:20
      He's been at every two evenings a week at the Rosemont or Crystal City outreach to these community groups working with Meredith and team.
    • 01:22:30
      So it's been very, very good.
    • 01:22:32
      One clarification, the requirement for two platforms at a time was not FRA.
    • 01:22:36
      That was the RE.
    • 01:22:37
      We said you got to do this because we need to maintain service for both us and Amtrak.
    • SPEAKER_11
    • 01:22:41
      Well, everybody liked it because they echo it.
    • Dallas Richards
    • 01:22:43
      Yeah, they liked it.
    • 01:22:44
      We mandated that in the contract.
    • 01:22:46
      Two tracks and two platform edges at all.
    • Mariia ZimmermanChair, Board of Directors
    • 01:22:49
      But I would also just add in addition to VRA and VPRA and Amtrak, Seth, I just want to
    • 01:22:55
      We need to also acknowledge and thank the cities.
    • 01:22:58
      I think their staff, their elected officials, everyone, it really has been a full team effort.
    • 01:23:05
      And I know they hear often first and foremost from citizens about things.
    • 01:23:09
      And I think it's generally been a very positive and productive partnership between everyone with that.
    • 01:23:15
      But I know having just been with the mayor of Alexandria and others, I heard again, generally positive things, but
    • 01:23:23
      I know a lot of coordinated outreach and communication happening with that.
    • 01:23:27
      So thank you to our, our local community partners.
    • 01:23:32
      And really, really, really would encourage folks if you haven't had a chance to just go across the street and look at this, cause you can visually see it.
    • 01:23:40
      Like you don't need, sometimes to do things you have to, you know, get in some weird convoluted space, but like literally let's go to the Amtrak station.
    • 01:23:49
      or even on the Metro, if they're taking the Metro and you can just look and see a lot of things that are on the way.
    • SPEAKER_10
    • 01:23:56
      And you guys cannot workflow?
    • Dallas Richards
    • 01:23:58
      So we can do certain activities tonight, but much like the Long Bridge project, those activities are limited by city restrictions, right?
    • 01:24:05
      So the noise, it is, I mean, you heard the staff man and driving those piles.
    • 01:24:09
      It's a very loud operation.
    • 01:24:11
      You don't want to be doing that at three in the morning, but.
    • 01:24:13
      But there are certain activities we have to do at night that can only be done at night between trains.
    • 01:24:18
      And so it's been very, very busy.
    • 01:24:19
      But no, again, the prohibition of some activities at night and trains during the day, it does not leave a lot of time.
    • SPEAKER_11
    • 01:24:30
      I should also note we're building out some new crossings in the area as well to be able to move passenger traffic throughout the existing platform configuration.
    • 01:24:38
      The ultimate goal of the project is to eliminate these crossings so you don't have passengers walking across tracks.
    • 01:24:45
      We will have elevators when the project is done, but just for moving people in this temporary configuration for the next two years, we have some new crossings, both for people and for equipment.
    • 01:24:56
      Okay, marching further south into the Franconia area, the Franconia Springfield Bypass continues.
    • 01:25:02
      And as DJ mentioned, we've had some challenges with utilities, we are working through that right now.
    • 01:25:07
      But there is still work that's ongoing.
    • 01:25:10
      By the end of last year, beginning of this year, we'd acquired all the property that we needed for the project.
    • 01:25:14
      We've built out all of our access to the site.
    • 01:25:17
      I think I've mentioned it in the board meetings in the past.
    • 01:25:19
      This is about as remote as you can get and still being in here.
    • 01:25:22
      And it's a hard site to get to.
    • 01:25:23
      You have to acquire property just to get to this site.
    • 01:25:27
      We have our access built out, our staging built out, our contractors on site doing work.
    • 01:25:32
      We have drainage that's underway.
    • 01:25:34
      We have two retaining walls that are underway.
    • 01:25:37
      We are fabricating.
    • 01:25:38
      We're just about to start the order for structural steel up in Williamsport, Pennsylvania to start doing the hundreds of pieces that have to get built for the bridges.
    • 01:25:47
      So there is still a lot going on.
    • 01:25:49
      The thing that is kind of a long pole in the tent right now are the utility relocations.
    • 01:25:54
      We have two fiber optic companies that need to move.
    • 01:25:57
      We have Verizon MCIs out there as we speak relocating lumens right behind them.
    • 01:26:02
      and then Kinder Morgan with the jet fuel pipeline is going to take place starting this summer.
    • 01:26:07
      So still a lot happening on the bypass, but we have run into some challenges on the utility side.
    • 01:26:13
      Not the most exciting photos in the world, but these are critical to the project.
    • 01:26:18
      This is a former Enterprise Rent-A-Car parking lot that we've acquired that is right on the tracks.
    • 01:26:24
      The tracks are just to the left of that photo.
    • 01:26:26
      This is just the best staging area and best access so you can get to the corridor in the area.
    • 01:26:31
      And actually, as DJ mentioned, looks totally different now than it does in that photo, because we are building it up and putting drainage in that area and doing lots of good things.
    • 01:26:41
      We also have crossings that we're building for equipment across the existing tracks, so we can keep the traffic of dump trucks, loaders, and things like that.
    • 01:26:51
      There's a lot going on in a really small area, and we've just been building that out over the last few months.
    • 01:26:57
      And you see a little bit more of that access that we're building out.
    • 01:27:01
      Again, this is a corridor that hasn't been touched in 150 plus years.
    • 01:27:06
      We're now making it accessible to build the bridge that we need to here.
    • 01:27:11
      And then I mentioned we have two big retaining walls.
    • 01:27:13
      The other thing we have to do is actually build out the space for the bypass bridge.
    • 01:27:17
      It is a pretty tight corridor.
    • 01:27:18
      It's got some very steep slopes in some areas.
    • 01:27:21
      So we're building some of these top down walls.
    • 01:27:23
      On the left there is a soil nail wall where we actually start at the top.
    • 01:27:26
      You inject these horizontal anchors, you put concrete face on them, and you actually start excavating down instead of building the wall.
    • 01:27:34
      So that's what we have going on right now.
    • 01:27:36
      As I mentioned, we have Verizon and MCI are out there right now doing utility relocations.
    • 01:27:43
      Franconia, Lauren, third track.
    • 01:27:45
      I know Mike mentioned it.
    • 01:27:46
      We are not yet into full construction.
    • 01:27:49
      CSX plans to procure their contractor later this year, but we have been doing some early work in this area.
    • 01:27:57
      For the bypass, we actually have to remove an entire and interlocking switching area called Ravensworth interlocking.
    • 01:28:04
      So we worked a package with CSX to actually do that work early on.
    • 01:28:09
      In a place that's just north of the project or just between the Beltway and Franconia Road, we're actually calling it Control Point Beltway for that reason.
    • 01:28:18
      We've been building that out since last fall.
    • 01:28:20
      So the site work happened last fall.
    • 01:28:22
      Back in March, CSX did all the track work.
    • 01:28:25
      And now they're working on the signals.
    • 01:28:27
      Where can we expect the signals to go into effect by the end of June?
    • 01:28:31
      CSX has to do that work themselves.
    • 01:28:34
      They have kind of roving crews that go around the country doing this signal work.
    • 01:28:37
      It's scheduled a year in advance.
    • 01:28:40
      And we get on the calendar for June.
    • 01:28:42
      So that's when they're going to be there.
    • 01:28:45
      And this is just some of the work from that track work that happened back in March that was going on.
    • 01:28:49
      As I mentioned up in Alexandria as well, these panels come and some of them get assembled on site, but a lot of them get fabricated offsite, brought in on rail cars, put off to the side, then put into place.
    • 01:29:00
      I think we have a video here just showing some of the work that CSX forces do.
    • 01:29:04
      This is where they're actually cutting out some of the existing track to make room for that special track work that's going in place.
    • 01:29:11
      You know, like everything else we're doing, very busy corridor, we have to do this work at night when there's as few trains as possible.
    • 01:29:19
      And this is actually the same group later on putting some of those track panels into place.
    • 01:29:25
      As I mentioned, they've been prefabricated offsite with some of the switching machines already attached, and they just lay them into place, get them set, put the ballast in place, and then weld the rails together.
    • Dallas Richards
    • 01:29:35
      Matt, if I may offer
    • 01:29:41
      And one of the things that's been very good about this close coordination is, for instance, when we were out for a jump span or when we will be out for a jump span construction at King Street, for instance, it affords CSX an opportunity to go do this sort of work at Slater's Lane, right?
    • 01:29:59
      So we're just sort of piling on one another and benefiting the projects who are benefiting each other.
    • 01:30:04
      A lot of close coordination required to do that.
    • SPEAKER_11
    • 01:30:10
      We've also been prepping for the utility relocations that are to come.
    • 01:30:17
      There's a lot of trees that had to come down.
    • 01:30:19
      We have time of year restrictions on trees.
    • 01:30:21
      The moratorium for tree clearing started on April 1st.
    • 01:30:25
      We got a lot of our tree clearing done in February and March.
    • 01:30:27
      And this, again, not a very glamorous photo, but it's a big milestone for us to be able to get the trees down.
    • 01:30:34
      and some of the Fairfax Water utility relocations that we have to do right around the Franck County Springfield VRA station.
    • 01:30:44
      With that, we're going to march much further south and west to the New River Valley.
    • SPEAKER_13
    • 01:30:52
      Exactly.
    • 01:30:53
      You still might want to know.
    • 01:30:54
      Much further south and west.
    • SPEAKER_10
    • 01:30:58
      Question.
    • 01:30:58
      Did I understand you correctly?
    • 01:30:59
      Did we have a buy plan for access?
    • SPEAKER_11
    • 01:31:01
      We did it, yeah.
    • SPEAKER_10
    • 01:31:03
      So who owns that?
    • 01:31:04
      I'm assuming we'll keep that access, right?
    • SPEAKER_11
    • 01:31:07
      Some of it's temporary just for construction and we'll return it back to the owner.
    • 01:31:11
      Some of it is permanent.
    • 01:31:13
      And in those cases, it actually depends on what side of the corridor it's on.
    • 01:31:16
      So if it's on the part of the corridor that the VPRA owns, we will keep it.
    • 01:31:21
      If it's on the CSX side, it'll at some point revert to CSX ownership.
    • SPEAKER_13
    • 01:31:31
      Chair,
    • 01:31:32
      Robert Ingby, Senior Director of Projects, overseeing projects that are not in Northern Virginia, as we affectionately call ROVA, or the rest of Virginia.
    • 01:31:41
      Let's start off with a little bit back to some more glamorous stuff, some teasers of what's coming.
    • 01:31:47
      So we've worked with the team for New River Valley, NS, the engineering folks, and creating these renderings.
    • 01:31:54
      These are exactly the 90 some odd percent, in fact, what you can
    • 01:32:00
      Envision to be done once we get out there and finished in 27.
    • 01:32:03
      So including colors, so brick color, socket color, roof color, all those things are now selected and coordinated.
    • 01:32:11
      And the next one we'll show will be the building as well.
    • 01:32:13
      And we'll take a look at that.
    • 01:32:15
      But you'll see you'll see the high level platform with the stairs, ramps, there's 150 odd parking spaces, the one way bus because there's a one way facility one way in one way out.
    • 01:32:26
      Long, long platform canopy 900 and
    • 01:32:30
      60 feet with two thirds of that covered by the canopy with a gap in the middle for the building.
    • 01:32:35
      We do have some ADA spots as well as some EV charging spots as well.
    • 01:32:39
      So this is the utility building that is, if you were to do this project to start with, you renovate the building, the original building.
    • 01:32:48
      We don't have that option.
    • 01:32:49
      We can do this a little bit backwards, right?
    • 01:32:50
      So
    • 01:32:51
      In here is all the electrical, networking, comms, everything that basically makes the platform work when trains come and go.
    • 01:32:58
      So to fire up the pins, all those things.
    • 01:33:01
      So this is a separate building that we own.
    • 01:33:04
      The building down in the middle or to the left there is the old station 1906 building that's going to be renovated after this project.
    • 01:33:14
      So
    • 01:33:14
      It's very close, but not quite.
    • 01:33:16
      But we'll be servicing this with trains before that building is in place.
    • Michael McLaughlinChief Operating Officer
    • 01:33:21
      Real quick, let me go back real quick.
    • 01:33:23
      So everyone gets their bearings.
    • 01:33:24
      That's heading toward Bristol.
    • 01:33:25
      Where's Beth?
    • 01:33:26
      Yeah, thank you.
    • 01:33:26
      That's heading.
    • 01:33:27
      That direction is Bristol.
    • 01:33:31
      This direction is Roanoke.
    • SPEAKER_13
    • 01:33:35
      That's Radford, right?
    • Michael McLaughlinChief Operating Officer
    • 01:33:37
      Yeah, Radford's next and then on the way to Bristol.
    • SPEAKER_13
    • 01:33:40
      Just kidding.
    • 01:33:41
      All right, so here's the building from the track side.
    • 01:33:44
      So keep in mind, this is the dedicated passenger track for the platform and the station.
    • 01:33:49
      This is one of the two main lines that NS has out on that project.
    • 01:33:53
      It's one of their busiest lines, heads off to the Midwest.
    • 01:33:56
      So that's the 1906 building.
    • 01:33:58
      So that rendering is actually from the architects that are working with the station authority to provide that.
    • 01:34:03
      So that is actually true on color and all the different selections as well.
    • 01:34:07
      So again, you can see we've done a lot of work trying to make those
    • 01:34:11
      Those two different projects coordinate and a lot of kudos to the team for keeping those all straight.
    • 01:34:17
      You see a little bit of the high level fence right here.
    • 01:34:20
      That's due to the close proximity.
    • 01:34:22
      You can almost reach out and touch the building when you're standing on the platform.
    • 01:34:26
      And we didn't want people accessing the roof or doing silly things.
    • 01:34:29
      So we ended up raising that fence in the back as part of this design iteration with the rendering center.
    • 01:34:35
      These have been a great tool and also a great PR thing also.
    • 01:34:38
      Now we're going to start shooting these out publicly.
    • 01:34:42
      All right, so some of the wet climber stuff.
    • 01:34:43
      All right, so we're out there.
    • 01:34:45
      This is a project we are delivering next year.
    • 01:34:47
      We're excited to stay on track.
    • 01:34:49
      DJ did allude to, we had a threshold to get that concrete done, but we are making good solid project progress out there.
    • 01:34:56
      Excuse me.
    • 01:34:57
      So you can see it's recently completed, drill pillar foundation.
    • 01:35:00
      So that was really to set up the platform canopy.
    • 01:35:03
      There's 114 of those.
    • 01:35:05
      Those are all done.
    • 01:35:06
      There's a lot of signal work being done.
    • 01:35:08
      If you remember, I think we showed one of the previous presentations.
    • 01:35:12
      We were doing cellular concrete, which is a lightweight fill that looked like layers of Cool Whip that we built up to make the platform, or make the parking lot to grade.
    • 01:35:21
      And we'll show you what that parking lot's starting to look like and shape up.
    • 01:35:24
      That parking lot retaining wall is done now, which is a fill wall.
    • 01:35:27
      You heard Jenna talk about top-down.
    • 01:35:29
      We did a bottom-up wall for the parking lot.
    • 01:35:31
      We're also doing a top-down for the peephole street, and we'll show you the picture as well.
    • 01:35:36
      The layerwork site's been a little bit quieter.
    • 01:35:37
      It's been sitting
    • 01:35:38
      Doing a little bit of electrical work.
    • 01:35:40
      Big, big thing for the, was actually a win this past week.
    • 01:35:44
      We ordered the modular building for Bradford, which has been a long time coming.
    • 01:35:48
      So that's where the crew will get change orders, get orders for track and crew orders.
    • 01:35:56
      The station site has been very busy.
    • 01:35:58
      Platform walls and pilatures are going on.
    • 01:36:00
      You'll see some progress in some of the photos upcoming.
    • 01:36:02
      Over at the layover, we do actually, we haven't shown it this week.
    • 01:36:07
      Just happened.
    • 01:36:08
      Ballast came to town.
    • 01:36:09
      So now the tracks were unballasted for a couple of months.
    • 01:36:12
      Now Ballast is in.
    • 01:36:13
      Light falls went up this week and you'll see that as well.
    • 01:36:16
      So on to some pictures.
    • 01:36:19
      So on the left, it's a big thing to get the signal crew out there.
    • 01:36:24
      They've been out, they've installed some canaries.
    • 01:36:26
      We've had a couple of different ones.
    • 01:36:27
      This is actually the western one at Cambria.
    • 01:36:31
      This picture on the right is actually
    • 01:36:33
      Standing above the parking lot, looking east, so this is actually the MOW building for Norfolk Southern that we built as part of this project.
    • 01:36:40
      This wall is actually the wall I was just talking about.
    • 01:36:42
      You can see some of the old, this is the cellular concrete getting filled in with some subcase that is now completely for that next picture.
    • 01:36:51
      But here's the wall again.
    • 01:36:52
      And now we fill it up.
    • 01:36:55
      So if you all remember, this grade here is about 15, 20 feet down from the depot.
    • 01:37:00
      And Frank, it's this whole parking lot, so when you pull in, it's not this big, steep slope, right?
    • 01:37:05
      So now this is starting to shape up and look like the parking lot, so this is actually the islands between, if you remember the rhetoric.
    • 01:37:11
      Here's the bus lane, and this is starting to be the parking for cars, and then off to the right will be the station building.
    • Mariia ZimmermanChair, Board of Directors
    • 01:37:18
      Do you have bike parking there too?
    • SPEAKER_13
    • 01:37:20
      There are bike racks, so not specific parking per se, it's like a dedicated space, but there are racks around.
    • 01:37:26
      All right, onto concrete.
    • 01:37:31
      So these are actually pictures of the wall and pilasters for the platform.
    • 01:37:36
      On the left is all the formwork.
    • 01:37:38
      And you can see that's actually the gantry, the signal gantry in the previous picture.
    • 01:37:41
      So this is the western side of the platform approach.
    • 01:37:46
      Again, 960 feet worth of platform.
    • 01:37:48
      We are about over a third of that now.
    • 01:37:51
      We have another pour coming up this week.
    • 01:37:54
      Fingers crossed the weather is not ideal the rest of this week.
    • 01:37:56
      So we're going to see some rain out in Christianburg area, but we are working forward on that.
    • 01:38:01
      Keep in mind, high level platform.
    • 01:38:02
      Underneath there are hundreds of feet of conduit that we have to install for forms of electrical and pounds.
    • 01:38:09
      So that's up next as well.
    • 01:38:10
      And then comes the columns for the canopy, as well as there will be precast planks and a topping slab for the ADA compliance.
    • 01:38:18
      And right here is a pump truck, right?
    • 01:38:20
      So again, a tight site for us, one way in, one way out.
    • 01:38:23
      Best way to service that with a pump truck for the pores.
    • 01:38:26
      And I think just a candid picture with a straight in the back.
    • 01:38:29
      So we've got an active corridor that we're working right next to all the time.
    • 01:38:34
      So this is a less glamorous wall, but so on the left is the, this is again, a different type of wall.
    • 01:38:39
      We've heard a couple of different ones.
    • 01:38:40
      This is a soldier pile lagging wall.
    • 01:38:42
      So those piles, they're galvanized.
    • 01:38:43
      They actually get drilled and then set in concrete.
    • 01:38:47
      There's 110 of those.
    • 01:38:50
      We are over halfway on them now.
    • 01:38:51
      You can start, this is actually the wall looking overhead.
    • 01:38:54
      This is west.
    • 01:38:57
      I'm sorry, East to West.
    • 01:38:59
      So this crane is actually one starting to set the lagging.
    • 01:39:02
      So what we do is we drill the piles in and then we start to excavate.
    • 01:39:05
      Then we slide those panels in.
    • 01:39:07
      Or anybody asked that it's not the finished product.
    • 01:39:10
      So on that goes a nice precast panel that basically slides in on the H files.
    • 01:39:16
      And there's almost like a, almost a fear of playing Connect Four, right?
    • 01:39:19
      And slide those in.
    • 01:39:20
      And they have a nice form lying around them.
    • 01:39:22
      They look like an astral stone or a block.
    • 01:39:25
      They're coming, they've been ordered, but they're all very custom as well.
    • 01:39:30
      This wall is at the tallest point, about 20 feet, and right behind it is Depot, right?
    • 01:39:35
      So this is the busy little street down in downtown Christiansburg.
    • 01:39:38
      So we do see a lot of traffic there.
    • 01:39:40
      And again, we had to put this wall in to make enough space to get the buses and traffic.
    • 01:39:44
      All right, moving over to Radford.
    • 01:39:50
      So these are the two new layover tracks.
    • 01:39:53
      Like I just said, in this picture we're unballasted.
    • 01:39:56
      They are now almost ballasted.
    • 01:39:57
      They're in process.
    • 01:39:59
      G-pile wall to separate us from the Norfolk Southern yard.
    • 01:40:03
      There'll be a fence around the entire perimeter of this for Amtrak folks.
    • 01:40:08
      On here will come the modular building.
    • 01:40:10
      On the left is electrical pads and pressure pads.
    • 01:40:15
      So a lot of power that we need for the new aero trains when they come.
    • 01:40:18
      It's changed some of the new things for Amtrak, but making good steady progress here as well.
    • Michael McLaughlinChief Operating Officer
    • 01:40:23
      Real quick, that direction is the Christiansburg Station.
    • 01:40:27
      There you go.
    • 01:40:28
      So the train will be coming from that direction here for the layover facility at Radford.
    • 01:40:32
      And that is Radford University track and field.
    • 01:40:36
      There's softball and baseball in there.
    • 01:40:38
      A lot of the sports are on the left-hand side of the picture, most of the academics on the right hand.
    • 01:40:44
      be on the right-hand side of the picture.
    • SPEAKER_13
    • 01:40:45
      Downtown Rapids on the right-hand side of the picture.
    • 01:40:48
      Yes, correct.
    • 01:40:49
      And there's a bridge right here, the University Boulevard.
    • 01:40:51
      This is actually a drone shot, but it's a great spot to stop and look over if you're ever in that area.
    • 01:40:58
      Back up.
    • 01:40:58
      Any questions about where we're about?
    • Beth RhinehartMember, Board of Directors
    • 01:41:11
      Thank you.
    • SPEAKER_04
    • 01:41:13
      We're not using 2027 as, oh my gosh, we've got 365 days in 2027 to get it done.
    • 01:41:39
      We're pushing for early, but we are under promising and overjoyed.
    • 01:41:43
      Any other questions on the construction update?
    • Beth RhinehartMember, Board of Directors
    • 01:41:54
      The next logical question is when can Radford University get on the train at Radford?
    • SPEAKER_10
    • 01:42:00
      We get to Radford until we get to Christchurch.
    • Beth RhinehartMember, Board of Directors
    • 01:42:06
      I told Cynthia as we were watching the amazing work
    • 01:42:12
      Longbridge and others said, that makes getting it to Bristol seem like just easy peasy.
    • 01:42:19
      I mean, looking at the complexity of that work and the Potomac River and all those complications, it seems so simple.
    • SPEAKER_04
    • 01:42:27
      Well, those three responses doesn't have one for that.
    • 01:42:29
      I will say this, though, that we would have to negotiate with Norfolk Southern to have a stop in
    • 01:42:41
      Our agreement with them does contemplate that.
    • 01:42:44
      So it's definitely on the table.
    • 01:42:45
      And as we're building the labor facility there, we're building a high level platform.
    • 01:42:48
      So we could use the platform we're building that the maintenance folks will be used to clean the train and service the train.
    • 01:42:55
      That platform could be a station platform in the far future.
    • Patricia DoerschMember, Board of Directors
    • 01:42:59
      Aren't college kids like a big part of the demographic?
    • 01:43:03
      So Jeremy question, right?
    • 01:43:04
      Whenever I ride the train, it's people like me and college kids.
    • SPEAKER_04
    • 01:43:09
      Yes, so let me ask the question directly.
    • 01:43:11
      Yes, that's what I know.
    • 01:43:13
      But to expand, really that generation, whether they're in college or not, they want to stare at screens and they don't want to be bothered with driving and getting gas and being all that.
    • 01:43:23
      So that generation is huge for our question.
    • 01:43:27
      And Amtrak will tell you that if you've got a station in a college town, it is a heavily utilized station.
    • 01:43:34
      Elementary?
    • Beth RhinehartMember, Board of Directors
    • 01:43:35
      Yeah.
    • 01:43:35
      Pat, to that point also,
    • 01:43:37
      Our conversations, University of Tennessee is all over about conversations for that exact reason.
    • 01:43:46
      Very, very interesting.
    • Patricia DoerschMember, Board of Directors
    • 01:43:47
      We'll meet up in Bristol, right?
    • SPEAKER_10
    • 01:43:52
      At Amtrak, sort of that second line in Virginia, down to Wors Liberty University, which I was in at Amtrak working, they were shocked that that had the highest line of shape than any
    • SPEAKER_04
    • 01:44:06
      Well, we started Lynchburg in 2009, there was an estimate that there'd be 30,000 riders and it turned out to be 100,000 riders.
    • 01:44:16
      And I remember before there was a big fight because the CFO was really kind of a jerk and
    • 01:44:24
      Hey, if this isn't funding itself, you're going to have to come up with the money in Virginia.
    • 01:44:29
      And then Virginia said, okay, we'll take that risk.
    • 01:44:32
      And then 100,000 riders came and there was profit.
    • 01:44:34
      And that CFO said, well, we want that profit.
    • SPEAKER_10
    • 01:44:39
      That's right, DJ.
    • 01:44:39
      That's amazing.
    • SPEAKER_04
    • 01:44:43
      Any other questions on the construction update?
    • Mariia ZimmermanChair, Board of Directors
    • 01:44:46
      Alrighty.
    • 01:44:46
      Let's move forward again.
    • 01:44:48
      I just want to note, we do have some folks leaving around noon.
    • 01:44:53
      So if we can
    • 01:44:54
      Move quickly for the next few items.
    • 01:44:55
      Thank you, Greg.
    • SPEAKER_10
    • 01:45:12
      Good morning, everyone.
    • SPEAKER_06
    • 01:45:13
      My name is Jessica Eglen.
    • 01:45:14
      I'm the Government Affairs Manager with VPRA.
    • 01:45:16
      This is the first time I've been speaking to you, so I thought I'd introduce myself.
    • 01:45:19
      We're just going to do a quick run through of this General Assembly cycle, give you guys some updates on what we were focusing on.
    • 01:45:26
      So these are just some of the key dates.
    • 01:45:28
      As you can see, this was an even year, so it's a long session.
    • 01:45:32
      So it's 60 days long.
    • 01:45:33
      It began on January 14th and ended here a little while ago on Saturday, March 14th.
    • 01:45:39
      Next year will be a short year, 45 days.
    • 01:45:42
      So when it says long, it's really not that long.
    • 01:45:44
      It moves just as quick as those short years.
    • 01:45:47
      Some dates that are important that are coming up is, of course, the governor has until this Saturday at 1159 to take actions on any of the bills that have not been finished since reconvene session.
    • 01:45:58
      She's taken action on a lot of bills this week.
    • 01:46:01
      I'm not sure how many she has left.
    • 01:46:03
      I'm sure there might be a couple, but most of the bills that we've been tracking have already had action taken by the governor on it.
    • 01:46:09
      And then, of course, any of those bills that don't have delayed enactment clauses on them, they'll be effective starting July 1.
    • 01:46:16
      Our priorities this session was, of course, really focusing on the two bills that we had, HB141 and HB446.
    • 01:46:25
      Westermann is gonna talk more about those later, but they were just mostly general cleanup bills, some legislative fixes that we've noticed over the last five years that we thought would be beneficial for us in the future.
    • 01:46:35
      There were over 2,000 bills introduced this year, so of course, one of our big priorities was making sure that we went through
    • 01:46:43
      vetted all of those bills for any impacts that they might have on VPRA's ability to operate in the future.
    • 01:46:48
      And then, of course, monitor any of those bills as they move through.
    • 01:46:51
      In some cases, when applicable, we would meet with the patron of the bill and work with them to address whatever our concerns were, putting in an amendment that solved whatever our issue was with it.
    • 01:47:01
      We had a couple of those bills this year.
    • 01:47:03
      Most of the time, they deal with things like easements or eminent domain, usually in that space of kind of increasing our cost of doing business.
    • 01:47:12
      Of course, we spent our General Assembly educating and informing new members about BPRA.
    • 01:47:17
      It's Virginia, there was an election last year, all hundred House of Delegates seats were up for reelection.
    • 01:47:23
      So there were a number of new members that we wanted to just make sure that we met with, let them know who we were and what projects we were doing, especially new members with projects in their district.
    • 01:47:33
      And then of course, always trying to work to build relationships with those legislators, making sure that they feel comfortable and bought into what we're doing that
    • 01:47:42
      We're accountable for the work we're doing.
    • 01:47:44
      We use a lot of taxpayer money on these projects.
    • 01:47:46
      So we just want to make sure that our General Assembly is aware of what's going on.
    • 01:47:50
      And of course session is a great time where they're all in one place to talk to them about those projects.
    • 01:47:55
      As I said, there were 2000 bills.
    • 01:47:57
      So it's not just me who's looking over them.
    • 01:47:59
      We have a really great legislative review team, which consists of a couple staff members from each different area of VPRA that helped me go through the bills to make sure that
    • 01:48:09
      They indeed either don't or do have an impact on VPRA.
    • 01:48:13
      We have a daily process I go through.
    • 01:48:15
      I look through the bills, anything that I think might need additional sort of monitoring, embedding.
    • 01:48:20
      I put it in Excel sheet and I let my wonderful colleagues who are sometimes smarter than I am in that space take a deeper dive into that to make sure that we aren't missing anything in the process.
    • 01:48:31
      And then of course, we wanna be able to do our jobs without some of the great partnerships that we have.
    • 01:48:35
      So of course, connecting with DRPT, VDOT,
    • 01:48:38
      and all of our other stakeholders like Norfolk Southern and CSX to make sure that we're on the same page about legislation as it's moving through and that they knew what we were doing and what our two pieces of legislations were about.
    • 01:48:51
      All right, so I'm going to pass it over to Michael Westman here who's going to get into more details about those bills.
    • Michael WestermannGeneral Counsel
    • 01:48:58
      Thanks, Jessica.
    • 01:48:59
      And by the way, before I say anything about the bills that got passed this year, I have to say Jessica did a tremendous job for the team this year.
    • 01:49:06
      We probably talked five times a day during session.
    • 01:49:09
      When the snow and ice was coming, Jessica looked at me and said, I don't know what to do.
    • 01:49:12
      We have all these meetings with senators the next day.
    • 01:49:14
      I think I'm going to sleep in the office.
    • 01:49:17
      I laughed.
    • 01:49:18
      She wasn't joking.
    • 01:49:19
      So she really dedicated herself to our bills and did a tremendous job.
    • 01:49:25
      And I just kind of went where she said and did what she said and went on successful.
    • 01:49:29
      All right.
    • 01:49:29
      So we had two bills this year.
    • 01:49:30
      One is HB 141, the other one is HB 446.
    • 01:49:34
      We split them into, the first one is what we call general cleanup.
    • 01:49:39
      The second one had to do with land use.
    • 01:49:41
      So we kind of separated them out.
    • 01:49:44
      I'm not going to go way into detail, but I'm going to tell you generally the substance of each bill, what we're accomplishing.
    • 01:49:52
      HB 141, the changes in the law because of that require us to change our procurement rules.
    • 01:49:58
      So the next slide, I'm going to talk about some updates we have to our procurement rules.
    • 01:50:02
      After that, we'll ask for a motion to adopt the changes that were in the procurement rules that went out in the board package.
    • 01:50:09
      So that's where we're headed with all this.
    • 01:50:11
      So starting on the left, HB 141, after five years of operating, realized that there were some gray areas in the law.
    • 01:50:18
      We realized that some of our sister agencies like VDOT, DRPT had the benefit of certain exemptions that we thought we should have as well as a transportation entity.
    • 01:50:28
      So the majority of the changes in the law that we introduced through HB 141 is simply clarifying some exemptions or gaining for ourselves some exemptions that we didn't have.
    • 01:50:39
      I won't go into each and every one of them, but the top one's a very good example, state grievance procedures.
    • 01:50:44
      There's an act in the law that gives state employees access to state codified grievance procedures.
    • 01:50:51
      We're different.
    • 01:50:51
      Our enabling access, our board has to adopt previous procedures for our employees.
    • 01:50:56
      That was done back when we started in 2021, 2022 timeframe.
    • 01:51:00
      We have this conflict because when you're looking to go to Virginia, we're not explicitly exempt from state previous procedures.
    • 01:51:06
      We don't want to have a situation where
    • 01:51:08
      Some employee wants to pursue grievance procedures and we don't know which one applies.
    • 01:51:13
      You know, there's one argument that the state wants to do.
    • 01:51:15
      There's one argument that our board adopted wants to do.
    • 01:51:17
      So just as a cleanup measure, we had an explicit provision added to the code that says VPRA is exempt from state grievance procedures.
    • 01:51:25
      It follows the exact model that authorities like ATC and Virginia Port Authority have where they're explicitly exempted from state grievance procedures because their boards also adopt specific grievance procedures for those two entities.
    • 01:51:38
      And the same is true down the line.
    • 01:51:40
      You can look at every single one of those.
    • 01:51:41
      One of our sister agencies has those exemptions.
    • 01:51:44
      So we said, hey, treat us like you treat VDOT, treat us like we treat the port.
    • 01:51:48
      So we have more flexibility under law generally, or exempt from certain fees when we talk about our projects.
    • 01:51:55
      The very last bullet point down here, that is the one unique feature of our bill.
    • 01:52:00
      Nobody else has this.
    • 01:52:02
      This is a procurement related change.
    • 01:52:05
      We go out and we hire, we use what's called bench contracts for engineering firms.
    • 01:52:08
      We will solicit offers.
    • 01:52:11
      We will hire four, five or six firms all at the same time.
    • 01:52:15
      We'll say you're on the bench when we need you, we'll tell you, we'll issue task orders.
    • 01:52:20
      The problem with that is under the existing law, there were very low thresholds.
    • 01:52:25
      You can see for a project, you can only spend $2.5 million.
    • 01:52:29
      And for the entire term of the project, the entire term of the contract, you can only spend up to $10 million for any given firm.
    • 01:52:35
      We found that very limiting.
    • 01:52:37
      So we would have new projects pop up.
    • 01:52:39
      We would need to issue a task order and hire an engineer to start design work.
    • 01:52:43
      We would be capped at $2.5 million for this new project.
    • 01:52:47
      Well, we often need to spend more than that.
    • 01:52:49
      And what you really don't want to do, you don't want to start with one engineer firm
    • 01:52:52
      and then midstream switch to another one.
    • 01:52:55
      Because the work product, they can't handle those off very efficiently.
    • 01:53:00
      Besides that, if we went through a traditional procurement and said, okay, this is going to cost, we think $10 million to design.
    • 01:53:09
      Let's go, let's start at the very beginning and do a competitive procurement for this project specific design work.
    • 01:53:15
      That would add like a year to what we're trying to do.
    • Michael McLaughlinChief Operating Officer
    • 01:53:18
      Since I can,
    • 01:53:19
      While no other entity in the state might have the $10 million caps, the freight railroads don't have the caps for design.
    • 01:53:25
      North Carolina doesn't have caps for their North Carolina DOT.
    • 01:53:28
      Rail Division doesn't have caps.
    • 01:53:29
      We talked to them.
    • 01:53:30
      So what we're asking for is to act more like a railroad, like some other states might do with regard to railroad activities.
    • 01:53:35
      So I mentioned Occom River Third Track.
    • 01:53:37
      If we, some elements of that, rather than taking nine to 12 months to do a procurement, we can go to our bench, which we're renewing this summer, and give someone a task for one entity up to nine, $10 million.
    • 01:53:48
      instead of the much slower process.
    • 01:53:50
      So, thanks a lot, John.
    • 01:53:51
      But this is something we worked with ACC Virginia on for over a year.
    • 01:53:54
      We started meeting with them in March of last year to work through these changes to get their support.
    • 01:54:00
      So, thank you to Christina and the private resident team at ACC Virginia and the answering farms for working through this with us to get to a point where we want to move these projects forward in a quick manner.
    • Michael WestermannGeneral Counsel
    • 01:54:11
      Thanks, Mike.
    • 01:54:12
      So, that's the summary of HB 141.
    • 01:54:15
      HB 446 is our land use bill.
    • 01:54:18
      This is the key here.
    • 01:54:19
      It aligns our quick take process with what all other condemnation orders in Virginia have to follow.
    • 01:54:26
      Quick take makes it sound like we're rushing in without notice and taking private property.
    • 01:54:30
      Notice how we're doing.
    • 01:54:31
      There's a very prescriptive process where we notify landowners, we go through a platting process, an appraisal process, we make offers and try to negotiate.
    • 01:54:39
      So it's the same process at the point where we cannot come to a voluntary transaction and grow in price with the landowner.
    • 01:54:46
      We will go file
    • 01:54:48
      Papers in court, we'll pay money into court, the landowner will actually have access to the money that we pay into court.
    • 01:54:55
      And while the trial happens, there will be a jury trial that happens that determines the valuation of the landowner, says the value is high, we say it's lower, and then there will be a jury trial to determine the actual valuation with the landowner, ultimately gets paid.
    • 01:55:07
      During the years that that process might take, we actually get access to the land and get to undertake construction activities so the project is not slowed down.
    • 01:55:13
      So we talk about quick take, that's what we mean.
    • 01:55:15
      Instead of having to wait for the whole core process to play out, we get earlier access to the property and get to undertake construction activities during the time where the core process is playing out.
    • 01:55:26
      We have very broad, very robust quick take powers.
    • 01:55:30
      The problem is we don't have to follow the process at all.
    • 01:55:33
      The other people, the condominiums,
    • 01:55:35
      The state have to follow.
    • 01:55:36
      We also don't get to follow the process.
    • 01:55:39
      So we're, we're filing documents in court that don't look like what court clerks are used to.
    • 01:55:44
      We're paying deposits in court in a way that they're not used to perceiving money.
    • 01:55:48
      So we said, we need to clean this up.
    • 01:55:50
      We need to be like everybody else.
    • 01:55:51
      So the, we got the law passed that said, Hey, you VPRA must follow.
    • 01:55:56
      It's titled chapter three, title 5.1.
    • 01:56:00
      Just like VDOT, just like other condominiums, you have to follow this process where we file certificates and quick take process.
    • 01:56:08
      And that's something that clerks are used to.
    • 01:56:10
      And it puts us in the exact same procedural posture as all other condominiums.
    • 01:56:15
      I heard that we need to hurry up.
    • 01:56:17
      So I won't, we have a few other sort of minor features of the bill.
    • 01:56:21
      One is that, hey, if we condemn land and acquire it, and later we want to sell it, we have a duty to offer that back to the prior owner.
    • 01:56:28
      uh exactly like VDOT does and then there were some categories well we didn't really technically we did not expand the categories of land that we've condemned there are some very specific statutes that give VDOT the ability to condemn specific types of property we're looking at saying okay we have this broad authority but then there's this very specific statute and we're not in it we don't want to have to argue about whether we have this authority or not so we went ahead and claimed that out okay so because of
    • 01:56:58
      This change here with how we do our engineering bench contracts, those prior thresholds were reflected in our procurement rules.
    • 01:57:07
      We had to update those thresholds.
    • 01:57:09
      So we pulled our procurement rules out.
    • 01:57:10
      We haven't updated them since 2022.
    • 01:57:12
      And we said, OK, what needs to change?
    • 01:57:15
      The red line was the board package that went out.
    • 01:57:20
      Just as a quick summary, here are all the substantive changes.
    • 01:57:24
      First, we said, look, where there's a federal requirement, we have lots of federal money in our program.
    • 01:57:28
      There's a federal requirement that applies that takes priority over our procurement rules.
    • 01:57:33
      We had to update the definition of professional services to include financial advisors, insurance brokers, because the law behind that changed, so we updated to mirror the law.
    • 01:57:45
      There are certain federal thresholds for micro and small purchases, which are non-competitive procurements.
    • 01:57:51
      Under $15,000, you can do a micro purchase, which means you can just buy what you need to buy.
    • 01:57:57
      Under $350,000, you can do a small, which is rather than doing a long, formal, drawn-out procurement, you just get three quotes and you can purchase from the best quote you get.
    • 01:58:08
      The prior thresholds were $10,000 and $250,000 respectively.
    • 01:58:14
      Since the federal limits went up, we have proposed to change our rules as well.
    • 01:58:20
      Section 3.25, we already talked about our bench contracts and those thresholds, so we reflected that in the procurement rules.
    • 01:58:26
      Section 4.3, this is very minor, but what we found ourselves doing on a very large mega project is we not only have a performance bond that guarantees performance of the contract, we also get a guarantee from the parent corporations because often what we have is a sole purpose entity that's created to undertake the project.
    • 01:58:45
      So what it is is a second layer of security.
    • 01:58:48
      So the entity with actual financial needs to perform is the one who's also promising to perform the contract.
    • 01:58:55
      And then section nine, we removed the requirement for DBE, Disadvantaged Business Enterprise usage plans from our solicitations.
    • 01:59:06
      Well, why did we do that?
    • 01:59:07
      The legal landscape on DBE has changed drastically in the past 18 months or so.
    • 01:59:11
      This past October, there was federal guidance that came down that basically said, not basically, it said, look, this historic practice of saying, okay, if you're in this racial category or if you're in this gender category,
    • 01:59:24
      Your business is automatically deemed disadvantaged and you count toward contract goals.
    • 01:59:31
      That's gone.
    • 01:59:32
      And what they said is all DBEs need to be reevaluated.
    • 01:59:37
      And then you need to look at the actual statements of the owners of the business and then have an affirmative duty to prove historical advantage.
    • 01:59:45
      And if they can't, then they're not going to be listed as DBE.
    • 01:59:49
      So what that's done is that's thrown us into a posture of, okay, everybody who is
    • 01:59:53
      and has been a DBE, is now being reevaluated.
    • 01:59:57
      And nobody is being, who's applying to become a DBE now is being granted application.
    • 02:00:03
      At the moment, everybody's kind of in this hopper being reevaluated and has to get re-certified under new rules.
    • 02:00:09
      So we don't want to look at our contractors and say, tell me which DBEs you're going to use, or tell me what percentage you're going to use, because they can't really, because we don't know what's going to happen on the back end of this process.
    • 02:00:20
      So we said, okay, we kept all of the small business, the state level designations, swam plans inside of the procurement rules, but we've removed the DBE plans.
    • 02:00:31
      And what the procurement rules say now, if adopted, they'll say, you know, when a DBE requirement applies, we will follow the program requirements and kind of leave it at that because right now it's kind of unknown how it's all going to shake out.
    • 02:00:46
      So I'm happy to answer any questions about the
    • 02:00:49
      The changes to the procurement rules that we're advancing, or the legislation that we got passed this past session.
    • Mariia ZimmermanChair, Board of Directors
    • 02:00:59
      Any questions?
    • 02:01:03
      Thank you, Mr. Osmond.
    • 02:01:04
      So we need to take Board action to approve this change to the procurement rules.
    • 02:01:10
      So I'm looking to see if there's any motion to approve proposed changes to procurement rules.
    • 02:01:16
      So moved.
    • 02:01:17
      Is there a second?
    • 02:01:18
      Second.
    • 02:01:20
      Any further questions or discussion?
    • 02:01:22
      All righty, all in favor say aye.
    • 02:01:25
      Aye.
    • Mariia ZimmermanChair, Board of Directors
    • 02:01:26
      Say nay.
    • 02:01:27
      Aye.
    • 02:01:27
      Sorry, forgot about ourselves.
    • 02:01:30
      Anyone else online?
    • 02:01:30
      Sorry.
    • 02:01:34
      All right, anyone opposed?
    • 02:01:36
      Any nay?
    • 02:01:37
      Anyone abstaining?
    • 02:01:41
      All righty, the ayes have it.
    • 02:01:42
      Thank you, Mr. Bicerman.
    • Laura FarmerChief Financial Officer
    • 02:01:45
      Thank you, Ms. Eichler.
    • Mariia ZimmermanChair, Board of Directors
    • 02:01:47
      All right, so what we're gonna do, just to make sure we have enough time, we're actually gonna jump to item 15 to discuss the budget, and work through that, and then we will kind of see where we're at at the end of that, how it might devise our agenda.
    • 02:02:05
      It's over to Ms. Farmer.
    • SPEAKER_04
    • 02:02:13
      And while they're getting ready, I just want to point out
    • 02:02:16
      Later in the day, we're going to talk about the project planning updates, what we want to do, and similar to what we did last year.
    • 02:02:23
      Last year, we asked you all to approve a budget with the knowledge that three months from now, we're going to have more information on the infrastructure that's going to be associated.
    • 02:02:32
      This afternoon, we're going to hear about the sightings that are going to be procuring government.
    • 02:02:37
      So what we have now for the sighting projects is our best estimate, but we know we're going to come back in August, September, October, and give you our
    • 02:02:45
      So the ownership kind of changes that conversation a little bit.
    • 02:02:49
      Just be advised that what you see in the budget for the signage, we all know is going to change and we'll hear more about that.
    • 02:02:55
      Any questions on that?
    • Laura FarmerChief Financial Officer
    • 02:02:57
      Lauren, I do that.
    • 02:02:59
      Yes, there's contingency on those projects.
    • 02:03:01
      I'm really excited that we didn't have to speak today.
    • 02:03:06
      So good morning, everybody.
    • 02:03:08
      Sam and I are going to provide an overview of the recommended budget for fiscal year 2027.
    • SPEAKER_07
    • 02:03:15
      Hi, everyone.
    • 02:03:16
      My name is Selma Nanovich.
    • 02:03:17
      I'm the Director of Financial Planning and Analysis.
    • 02:03:21
      To start off, I'll try taking a look at a summary of our budget process.
    • 02:03:26
      So the VPRA budget consists of three core components, starting with capital projects, capital and operating grants, and operations.
    • 02:03:37
      And please note that our operations include Amtrak operations and our administrative
    • 02:03:44
      The two capital components have to go to the CTB for approval and the capital budget was provided to the CTB by the February 1st deadline and it was approved on April 22nd.
    • 02:04:00
      So next we're going to take a look at our larger VPRA financial plan which compares our sources and uses from inception of
    • 02:04:14
      Our program to fiscal year 31, which is the completion of our four capital program.
    • 02:04:22
      So the top section we looked at during the January board meeting, so we're not going to take a look at that again.
    • 02:04:28
      We're going to focus on the bottom section of the slide, which includes changes since our January board meeting.
    • 02:04:39
      So our sources, which is
    • 02:04:41
      Our revenues increased by $0.8 million.
    • 02:04:44
      Our uses, which are our expenses, also increased by $24 million, causing a decrease of $23 million in our management reserve.
    • 02:05:00
      And taking a deeper dive into the primary drivers that are causing the increase in our sources, we're going to focus on the right
    • 02:05:09
      table of the slide, the left side we talked about during the January board meeting.
    • 02:05:16
      So there was a $0.3 million increase in our sources related to a Chrissy Ehrmakul award that VPRA received for the Alexandria fourth track project.
    • 02:05:29
      There was an increase in the DC Pedbridge contribution of $4.0 million.
    • 02:05:34
      and that was offset by two decreases in the Stafford utility reimbursement of $3.3 million and a decrease of $0.2 million related to the access fee payments that we make to VRE.
    • 02:05:49
      And then on the next slide, we're going to talk about the changes in our uses.
    • 02:05:55
      So this slide just shows an overview by budget component.
    • 02:06:01
      So we're going to focus on the April update column.
    • 02:06:04
      So in the I-95 corridor, there was a $3 million increase in our net base budget changes.
    • 02:06:13
      Other capital projects saw a decrease of $9 million, and our operations section increased by $30 million, excuse me, for a total change in uses of $24 million.
    • 02:06:31
      So we're going to...
    • 02:06:33
      Dive deeper into each of the budget components.
    • 02:06:36
      We're going to focus on the peach colored lines, the rest of the items we talked about during the January meeting.
    • 02:06:43
      So these are changes that happened between January and May.
    • 02:06:48
      So we are comparing the amended fiscal year 26 budget to our proposed fiscal year 27 budget.
    • 02:06:55
      So starting with Long Bridge north and south, the north component
    • 02:06:59
      Project budget increased by $1.5 million.
    • 02:07:03
      The south component increased by $3 million.
    • 02:07:06
      And both of those are related to the district DOT project oversight costs that were not previously included in those project budgets.
    • 02:07:16
      Next, we're going to talk about the Potomac Creek Third Track.
    • 02:07:20
      So this is project Siting A.
    • 02:07:22
      There was an additional $2.5 million increase in that project budget.
    • 02:07:28
      in addition to the increase that we saw in January related to utility expenses that are not covered by Stafford County.
    • 02:07:36
      So these are expenses that VPRA is responsible for and will not be reimbursed by Stafford County.
    • 02:07:42
      And lastly, the Potomac Creek Third Track.
    • 02:07:45
      So this is the Stafford Utilities portion of that project.
    • 02:07:49
      There was an increase of $1 million related to or fined their first sign up.
    • 02:07:57
      There were no additional changes to the Western Rail Corridor, the $2 million we talked about in January.
    • 02:08:11
      So in the other capital projects component of the budget, the Manassas Line Capital Maintenance increased by $9 million, and this is as a result of refined estimates that were provided to us from Norfolk Southern.
    • 02:08:27
      related to the capital maintenance of the M-Line.
    • 02:08:30
      There is no additional change in the capital and operating grant section of the capital budget.
    • 02:08:39
      And the next couple of slides just show our expenditure plans for our capital projects.
    • 02:08:45
      And there's more details by project that were included in the board materials that were provided to you all.
    • 02:08:55
      I'm going to pause to see if there's any
    • 02:08:57
      Questions to the capital side of our budget.
    • 02:09:02
      And I'm going to hand it over to Laura to talk about our Amtrak operations budget and our admin budget.
    • Laura FarmerChief Financial Officer
    • 02:09:11
      Okay, so since January, when we talked to you then, within a couple of weeks of the service changes that occurred on January 12th, and we made note that
    • 02:09:22
      Based on lessons learned, we come back to you with any changes that we recommend related to operating costs.
    • 02:09:28
      What we found is that the most extensive change that we have related to operations has to do with a change that we're recommending working with Amtrak on and have proceeded to implement, which is opening up what is considered deadhead cars, where there's additional capacity available in these trains that start in Virginia where we remove service, particularly in Richmond, and we're opening up an additional car
    • 02:09:51
      to passengers.
    • 02:09:53
      And that affects not only availability, but ticket pricing as well.
    • 02:09:58
      And so we've worked with Amtrak to estimate what it would take to bring on an additional conductor, the staffing, the Wi-Fi, the cleaning responsibilities, all the things that goes along with opening that capacity.
    • 02:10:11
      And that value is about four and a half million dollars.
    • 02:10:13
      We felt that was best related to the operations going forward.
    • 02:10:17
      And so this change of 32 million
    • 02:10:20
      represents a five-year impact of that change throughout the remaining construction and the reduced service.
    • 02:10:26
      And so that is the most significant change in the operating budget that we're recommending since January.
    • 02:10:34
      Related to asset maintenance, we have refined budgets provided by Norfolk Southern for a slight adjustment there.
    • 02:10:41
      Related to operations administrative costs, we have an overall change of $2 million.
    • 02:10:47
      We've had additional refinements of costs, but mainly our safety and security improvements have been added as a new line item.
    • 02:10:57
      We have property that you need to take care of that's beyond the rail asset that we have a responsibility to maintain safety.
    • 02:11:05
      And then in other operations, this decrease is primarily related to refined bus service costs.
    • 02:11:11
      So as we brought the buses online and also entered into that procurement,
    • 02:11:16
      Our estimates were a little bit too high related to what we saw in the procurement results.
    • 02:11:21
      A good news story in that area.
    • 02:11:27
      This slide just provides a view of the amended current year budget against the recommendations for fiscal year 2027.
    • 02:11:35
      Most of these adjustments are related to the change in service year over year, but also bringing New Bernal Valley online.
    • Beth RhinehartMember, Board of Directors
    • 02:11:42
      and some additional calls that we'll experience in the western side of the state.
    • Laura FarmerChief Financial Officer
    • 02:11:50
      This slide provides the details of the administrative budget changes for VPRA.
    • 02:11:55
      With regards to payroll benefits, our staffing remains pretty much the same in terms of assumptions year over year.
    • 02:12:02
      The biggest adjustment here is us making adjustments for our retirement costs for the agencies and what we get passed on to us through VRS.
    • 02:12:12
      Pension adjustment has been provided based on what we've learned over the last two years.
    • 02:12:18
      With regard to professional services, we have a planned depreciation study related to the property that we have.
    • 02:12:26
      We'll be updating the financial plan going forward in the upcoming months.
    • 02:12:31
      We also have recommended adjustments in our IT area related to cybersecurity and penetration testing.
    • 02:12:40
      They get grouped in that category.
    • 02:12:42
      And the biggest change here also is related to a station study.
    • 02:12:47
      As we're making improvements to the rail and adding capacity, it's very important that we look at stations and take a look at any recommended improvements going forward that we can not only recommend for funding, but seek alternative funding to make those improvements and working with Amtrak going forward.
    • 02:13:06
      In the area of IT, as we've brought systems online and having the systems amortization across, that is really just the driver of these costs.
    • 02:13:17
      We also have additional reporting responsibilities related to using our internal financial systems, make sure that we're getting the best data out of it to make recommendations.
    • 02:13:30
      And we're also looking for a grant system implementation.
    • 02:13:33
      We have tremendous alternative sources
    • 02:13:35
      Managing those is quite cumbersome and we're looking for solutions to help us work a little bit smarter related to seeking reimbursements.
    • 02:13:45
      And then for building and office related costs, we've had a decrease year over year.
    • 02:13:51
      We had some one-time expenses for building improvements that are no longer in the budget.
    • 02:13:58
      In terms of the other employment costs, we have other employee costs just based on historical spending,
    • 02:14:05
      as well as future needs.
    • 02:14:08
      We're looking at a new human resources and payroll system.
    • 02:14:12
      What we have works for us, but we're not 100% happy with it and we're looking at opportunities, but we don't envision a tremendous cost increase there.
    • 02:14:19
      One of the biggest items here is also planned groundbreaking and what it's going to take to do that event and the expectations around it.
    • 02:14:31
      We have a small,
    • 02:14:33
      An 11% increase related to insurance costs just based on what we have incurred to date and future needs.
    • 02:14:41
      We've also adjusted our third party projects administration budget.
    • 02:14:45
      Again, this is included in our administrative budget, but it represents money provided by others.
    • 02:14:51
      And then as I mentioned earlier, property management.
    • 02:14:55
      This is a new line item in our budget related to improvements that we need to make related to signage,
    • 02:15:02
      Ben Sane, or other improvements that are needed at these sites beyond the actual rail.
    • 02:15:09
      Any questions on those details?
    • 02:15:18
      This provides an analysis of a comparison of our administrative costs to total expenditures.
    • 02:15:25
      Obviously, as the capital program is really kicking into high gear, this graph is trending in the same way we would expect.
    • 02:15:34
      And then in terms of the management reserve, with those adjustments that we described related mainly to the Amtrak operations, our management reserve is decreased since our last quarter to $89 million.
    • 02:15:51
      And we still have about 23% of our remaining program to get to final construction pricing.
    • 02:15:58
      And so this is something that we're watching very carefully, but we felt like that operational adjustment was really required to ensure that the remaining routes are operating the way they should.
    • Mariia ZimmermanChair, Board of Directors
    • 02:16:11
      Any questions?
    • 02:16:15
      I just want to note, particularly for those who might be listening in case you're wondering why we didn't have a lot of questions on that, I just wanted to
    • 02:16:23
      Notes meeting that happened last month.
    • 02:16:25
      I think it's on April 26th.
    • 02:16:27
      We do have a separate finance and audit committee that Member Doersch is our chairperson for that.
    • 02:16:34
      We had a very robust discussion in that meeting about a lot of these budget issues and about particular projects where funding was added and budgets for those.
    • 02:16:44
      So I just want to assure anyone listening, we do have robust discussions.
    • 02:16:48
      I don't know.
    • 02:16:49
      If there's anything you want to add in from that meeting, but I think we've kind of got the update where we're at here too, but anything else you might want to add?
    • Patricia DoerschMember, Board of Directors
    • 02:16:57
      Well, just that the committee recommended approval of the budget to the full board.
    • Mariia ZimmermanChair, Board of Directors
    • 02:17:06
      Alrighty, so with that, if there are no questions, additional questions on the budget, could we get a motion to approve the VPRA FY 27 budget and management reserve?
    • Laura FarmerChief Financial Officer
    • 02:17:18
      I move approval.
    • Mariia ZimmermanChair, Board of Directors
    • 02:17:20
      All in favor, say aye.
    • 02:17:23
      Aye.
    • 02:17:24
      Any opposed, say nay.
    • 02:17:29
      Anyone abstaining?
    • 02:17:32
      All right, the ayes carry it.
    • 02:17:33
      Thank you very much, both of you.
    • 02:17:35
      All right, let's do our time check.
    • 02:17:37
      I think that was so fast and furious.
    • 02:17:39
      We can go back to, should we go to the bylaw insects?
    • 02:17:44
      All right, let's have that conversation.
    • 02:17:46
      on some proposed changes to the bylaws and a bylaw.
    • SPEAKER_04
    • 02:17:58
      Thank you, Madam Chair, and thank you all.
    • 02:18:00
      Every year, we take a look at the bylaws, bylaws were created back in 2020.
    • 02:18:05
      We look to make any acquired change, recommend change here in this cycle.
    • 02:18:11
      We look at what we did last year.
    • 02:18:13
      Last year, we made the change actually on the bottom.
    • 02:18:18
      We had discovered an issue where the executive director's authority to move money back and forth didn't allow for new projects.
    • 02:18:26
      The example was we had a siding.
    • 02:18:29
      We worked with the CSF and decided that that siding was in a place that was good, but would require us to place a high barrier, which was very, very expensive.
    • 02:18:39
      We talked to the exec.
    • 02:18:40
      We moved the siding north a little bit.
    • 02:18:42
      Take that coffee, move it out, save us a significant amount of money.
    • 02:18:46
      They said, yeah, let's look at that.
    • 02:18:47
      Let's study that.
    • 02:18:48
      Well, when we wanted to study that, we had to create a new line item to study what would be a new siding.
    • 02:18:53
      And I didn't have the authority to do that.
    • 02:18:55
      So last year we did a bylaw amendment that would allow me to not only move money back and forth without increasing the budget, but also to create a new line up.
    • 02:19:05
      That, I think that authority is in there now.
    • 02:19:08
      We are now coming back this year to ask for that same modification for both the passenger service budget and for the administration budget.
    • 02:19:16
      It comes in play.
    • 02:19:18
      For example, Amtrak comes and says, hey, we've got a new line item.
    • 02:19:20
      We've got new train sets.
    • 02:19:21
      We're going to create a maintaining arrow.
    • 02:19:23
      Why not?
    • 02:19:24
      Or some other required line item.
    • 02:19:26
      We would have to come back to the board and get approval.
    • 02:19:28
      What these changes allow us to do, it allows its media authority to create a new line item up to a certain percentage of the budget, 1.5% of the budget.
    • 02:19:37
      and of course it would be transparent.
    • 02:19:40
      We showed you the executive director report, we talked about it, but it prevents us from having to get the whole board together to vote on a new lineup or to make small movements like that.
    • 02:19:50
      So we're looking for that same authority that we have now under capital and capital projects to be extended to the afternoon service and the administration.
    • 02:19:58
      The other thing that we need to do is what we talked about earlier.
    • 02:20:01
      The bylaws currently say, when you give me an authority to do something, I've got 90 days to do it, as we've seen with
    • 02:20:08
      and partners across the board, freight railroads, Amtrak, DOT, sometimes it takes longer than that 90 days, so we're asking to extend that authority from 90 days to 12 months.
    • 02:20:20
      Those are the changes that we're recommending and requesting to answer any questions on.
    • Mariia ZimmermanChair, Board of Directors
    • 02:20:29
      I've got one.
    • 02:20:30
      On extending that to 12 months,
    • 02:20:33
      Do we think we should extend it any longer and so we're not having to come back again if it looks like maybe even another 30 days or 60 days beyond that?
    • SPEAKER_04
    • 02:20:43
      I don't, I wouldn't want that.
    • 02:20:45
      Number one, if we're bringing it to the board and we've got 12 months left in negotiation, I think we're bringing it too early.
    • 02:20:50
      The other thing is that we've got three members every 12 months that rotate off.
    • 02:20:55
      And I don't want to be in a situation where I'm now signing something that less than 75% of the board has voted on.
    • 02:21:01
      Okay, look, we
    • 02:21:03
      speaking for the current leadership.
    • 02:21:05
      When the changes, we bring them to you.
    • 02:21:07
      No surprise, you can say that all the time.
    • 02:21:09
      So we're not going to get bored for something and then do not hear about it for 12 months.
    • 02:21:15
      But I think 12 months is way on the farm.
    • Mariia ZimmermanChair, Board of Directors
    • 02:21:17
      All right.
    • 02:21:19
      Thank you.
    • 02:21:22
      That's probably a yes.
    • Beth RhinehartMember, Board of Directors
    • 02:21:24
      I would just note that I think that in the transparency, which is very noted here,
    • 02:21:31
      Anything about that, but I think that's the important piece of this, is that transparency of whenever any of those kind of changes are made, that the Board is advised, I think that's the easy part of it.
    • SPEAKER_04
    • 02:21:44
      Yeah.
    • 02:21:44
      Absolutely.
    • Beth RhinehartMember, Board of Directors
    • 02:21:45
      No surprise.
    • Mariia ZimmermanChair, Board of Directors
    • 02:21:49
      Any other questions or concerns that members may have?
    • 02:21:56
      All right.
    • 02:21:57
      Well, hearing none.
    • 02:21:58
      We have a motion to approve the adoption of the revised GPRA bylaws.
    • 02:22:05
      So moved.
    • Michael WestermannGeneral Counsel
    • 02:22:06
      Second?
    • 02:22:07
      Second.
    • Mariia ZimmermanChair, Board of Directors
    • 02:22:07
      All right, a motion and a second.
    • 02:22:12
      Let's see if we have all those in favor say aye.
    • 02:22:15
      Aye.
    • 02:22:18
      Those opposed say nay.
    • 02:22:21
      Any abstentions?
    • 02:22:23
      All right, the ayes have it.
    • 02:22:24
      Thank you.
    • 02:22:25
      Alrighty, we have been fast and furious.
    • 02:22:28
      I know that we have a couple still on our agenda.
    • 02:22:32
      Do you think that where we could talk about one of the projects, funding updates, and still be able to have the discussion we need to have there before we break for lunch?
    • 02:22:44
      Is that fine with folks if we have a few more minutes while we have everyone?
    • 02:22:48
      I also just do want to note, if folks do know that you have scheduling issues, please do let us know ahead of time.
    • 02:22:55
      The staff is always great at working with me to adjust our agendas as needed.
    • 02:23:00
      So as always, just let us know if things come up.
    • 02:23:04
      We know that does happen at times.
    • 02:23:10
      Mr. McLaughlin, I'll have you on the team.
    • Michael McLaughlinChief Operating Officer
    • 02:23:13
      Just like Lachlan, we passed the budget and then we came back to you and talked to you about
    • 02:23:18
      I'll give you a fourth track in King and Commonwealth.
    • 02:23:21
      Similarly, I already mentioned some projects such as Franklin and Lorton are going to procurement soon, some signing projects moving to them.
    • 02:23:29
      So we wanted to, in the same context of the budget meeting, also talk about these so you're not surprised in the future.
    • 02:23:37
      And with that, this gives you an idea, just a quick picture of when we're building a third track, where it's going to go.
    • 02:23:45
      So we can move on.
    • 02:23:47
      And I'm gonna hand over to Rob.
    • 02:23:50
      Try to be quick.
    • SPEAKER_13
    • 02:23:53
      Right in the spirit of being quick.
    • 02:23:55
      So these are the five siding projects that are currently active.
    • 02:23:58
      Mike alluded to this a little bit earlier.
    • 02:23:59
      We're gonna talk about DE, F and C. Keep in mind they were ABC for phase one, DE and F for phase two previously.
    • 02:24:06
      So the nomenclature was a little bit more, now it's a little bit mixed up.
    • 02:24:10
      From north to Neabsco to Bridge 3 track is D, Aquia Creek 3 track is E, Selma Creek 3 track is A,
    • 02:24:17
      Crossroads for your track to F, and then Taylor for your track to C. So we've been spattering across the board.
    • 02:24:23
      So we started to progress these projects.
    • 02:24:27
      We've talked about them a few different times.
    • 02:24:29
      And four new sightings, C, D, E, and F. Remember, C was relocated from its previous location to a new location in Taylorsville, outside of why I consider it still a new one.
    • 02:24:39
      They all just kicked off.
    • 02:24:41
      We are now working in earnest in 3% plans with the CSX team.
    • 02:24:46
      We're working on 30% plans with them now.
    • 02:24:48
      This is really the first time where we're starting to see more than a couple lines on paper, right?
    • 02:24:53
      So we're starting to see some cross sections.
    • 02:24:55
      We're starting to see some slope lines.
    • 02:24:57
      We're starting to get an understanding of right away impacts, but we still have a lot to learn.
    • 02:25:02
      We're still 30% is very, very early.
    • 02:25:06
      They currently represent over 12 miles worth of new third track.
    • 02:25:12
      All that being said, we are diligently working forward.
    • 02:25:15
      Field work is going on in here.
    • 02:25:16
      If you're up and down the corridor, I see folks off to the side.
    • 02:25:18
      They are doing non-valley work as far as wetland flagging and environmental studies.
    • 02:25:24
      We're doing additional topo work, so on and so forth.
    • 02:25:27
      All this is to get information to make the 60% of plans even better.
    • 02:25:30
      We've received one set of plans for siting C for Taylorsville.
    • 02:25:37
      We expect another one pretty much month on month over the next three months.
    • 02:25:40
      We are still digesting the seed in the mill that we got, so it's a first glance.
    • 02:25:46
      It's going through our tap process as far as estimate updates.
    • 02:25:50
      As you can imagine, costs are fluctuating all over the place with different things going on in the world, so we're still kind of churning through that.
    • 02:25:56
      I would suspect that these are all, like I said, step back and say all these numbers that are shown as budget numbers were based on zero percent design.
    • 02:26:04
      They were our best guess based on mile markers, what could be out there, what might be out there.
    • 02:26:08
      As we continue to learn and iterate
    • 02:26:10
      These numbers would be refined.
    • 02:26:12
      So again, 30% plans, very variable information still.
    • 02:26:16
      We will expect that we'll be back sometime late summer to talk about these again, but just wanted to give a heads up to the board.
    • 02:26:23
      We are making good progress, but likely we'll be revisiting the budgets on all four of these.
    • SPEAKER_04
    • 02:26:29
      At what percentage of the design completion do you feel comfortable about where we are from a budget pushback?
    • SPEAKER_13
    • 02:26:36
      When it's finished.
    • 02:26:37
      Yeah.
    • 02:26:38
      Yeah, I mean, in every iteration, really 60% starts to be where we have a lot of information that we can kind of chew on that I feel a little bit more comfortable.
    • 02:26:46
      30% starts to take a little bit of mud out in the water, but 60 starts to be a little bit better than 90, obviously, as we iterate above.
    • Michael McLaughlinChief Operating Officer
    • 02:26:54
      Oh, that's, yeah, very accurate.
    • 02:26:55
      Do you want to point out starting E and F, the Fredericksburg area, friends, those are down near your area.
    • 02:27:00
      E is going to be near the Brook Station.
    • 02:27:04
      A was Leland.
    • 02:27:07
      F is going to include
    • 02:27:09
      This thing is Summit.
    • 02:27:11
      It's going to have four quad gates we're putting in.
    • 02:27:13
      So that was a rail crossing elimination grant.
    • 02:27:17
      They give because it's in a project area.
    • 02:27:19
      So I know that's the area down that neck of the way.
    • 02:27:22
      So I do want to point out that those, those are included in that, in that cost estimate.
    • 02:27:27
      But yeah, 30, 30% of design, we feel better.
    • 02:27:30
      Again, we always feel better the further along you get.
    • 02:27:32
      Retaining walls, things of water, things of that nature are things there.
    • 02:27:38
      Utilities, thank you, right-of-way.
    • 02:27:41
      Figuring out if the design, as you get 30% design, what do we need to buy more right-of-way?
    • 02:27:46
      Is that going to delay the project?
    • 02:27:48
      If therefore it delays the project, the cost could increase.
    • 02:27:51
      Some projects you might ask me pleasant surprise, you don't need any more right-of-way, which makes us happy, makes Michael's team happy to acquire us right-of-way.
    • 02:27:58
      So we're still learning a lot of that information as we're all putting it out.
    • SPEAKER_04
    • 02:28:02
      And just to point out, so the sidings projects are legacy projects, and they were part of the original portfolio that we
    • 02:28:08
      we're blessed with in 2020-2021.
    • 02:28:10
      We made a decision early on, we found that we got to 30%, oh, we didn't account for this, that we were no longer going to put full project estimates into our budget until we were at least at 30%.
    • 02:28:22
      And that's why Richmond Labor Facility, for example, and some of the other projects that we have that were not part of that original list, we only have the design estimates.
    • 02:28:30
      And then when we get to a certain percentage, we come back and ask for the full project.
    • 02:28:34
      In hindsight, and this is hindsight,
    • 02:28:37
      2019-2020, we probably would have done that for all the projects because at 0% design you really don't know what you're doing now.
    • 02:28:47
      And 30% you can have a good understanding if and only if 30% is done where all the utilities are.
    • 02:28:57
      And that's actually mapped to the actual locations that you're looking at.
    • 02:29:04
      We've had a lot of challenges as we've talked about
    • 02:29:07
      We think the project is going to be right here and here's our limit of disturbance.
    • 02:29:13
      Oh, wait a second.
    • 02:29:14
      We don't own this.
    • 02:29:14
      I thought we did.
    • 02:29:15
      Well, the courthouse says you don't.
    • 02:29:17
      And that adds a lot of time, a lot of money, a lot of stress.
    • 02:29:20
      If you're 30% insured that all that stuff is accurate, you feel pretty good.
    • 02:29:25
      But if there's still a lot of unknowns that you're finding out between 30 and 60, and that's what Rob was very subtly alluding to, you can't commit to anything until you've got those things.
    • Patricia DoerschMember, Board of Directors
    • 02:29:37
      I just, I remember, I think I recall that when we decided that we could save money and speed things up, moving sidings, see, there's a great maps that shows here's different tracks for us.
    • 02:29:49
      These are just like dots on one line, right?
    • 02:29:53
      When we look at it, could we ever get one of those great maps again?
    • Michael McLaughlinChief Operating Officer
    • 02:29:56
      You say, so we showed you where we moved one project to another.
    • Patricia DoerschMember, Board of Directors
    • 02:30:00
      Because this isn't just a dot on a single line, right?
    • Michael McLaughlinChief Operating Officer
    • 02:30:05
      Three miles, yeah.
    • 02:30:06
      So, Siding C in this case is actually only two miles.
    • 02:30:09
      So, the other siding was right about here.
    • 02:30:15
      That was, we did want to rebuild Washington, Route 1, Washington Highway, that's what you're referring to.
    • 02:30:22
      We found out, so we went to CSX almost about two years ago now, these things take some time, and we found a location on Kings Dominion Highway, the road that goes into the amusement park,
    • 02:30:35
      CSX told people 20-something years ago, when you're building something new, widen it enough that we need to add another track we can.
    • 02:30:42
      That's the location you're referring to.
    • 02:30:43
      So we saved about $100 million.
    • 02:30:45
      As much as we like building new infrastructure for VDOT, I don't like spending $100 million to build a new infrastructure.
    • 02:30:51
      So we're going to go into Kings Dominion and we're not going to have to widen the piers there, as we're doing at Leland.
    • 02:30:57
      That's what we have to do with Leland.
    • 02:30:58
      That's why we did the road work there soon.
    • 02:31:00
      We can send that out.
    • 02:31:01
      We can follow up the people and send out that as a reminder to the board.
    • 02:31:04
      I know you presented that in the past.
    • SPEAKER_13
    • 02:31:06
      Yeah, and I'd say we definitely have the zoom in.
    • 02:31:10
      This is the darker versus the lighter, but we have a zoom in on our website for each of these landmarks.
    • 02:31:15
      But we also have aerial release.
    • SPEAKER_04
    • 02:31:18
      Yeah, and actually, I love that idea.
    • 02:31:19
      We should just include that every month in the EDR.
    • 02:31:22
      This is the project, we've got the same project, it's getting every month, we bold what's changed.
    • 02:31:26
      We can include those track charts at a more detailed level because if you haven't seen it for years, you don't remember.
    • Patricia DoerschMember, Board of Directors
    • 02:31:33
      Yeah, I just had a vague memory of it being a good idea, but when you look at it, it's like, oh, we moved the dot down too.
    • 02:31:39
      Like, why?
    • 02:31:39
      Because we didn't have to rebuild an entire highway going under the bridge, right?
    • 02:31:44
      By moving it a few feet down, two miles down.
    • SPEAKER_13
    • 02:31:47
      Yeah, a few miles.
    • 02:31:48
      And that bridge was substandard and needed to be improved.
    • Patricia DoerschMember, Board of Directors
    • 02:31:51
      And that would have been on us since we were touching it.
    • SPEAKER_13
    • 02:31:54
      For our projects.
    • 02:31:58
      Any other questions on signings?
    • 02:32:01
      See you in a couple months about that.
    • 02:32:03
      All right, Richmond layover facility.
    • 02:32:05
      So you heard a little earlier, I allude this is the Achilles heel of our program.
    • 02:32:10
      We need this in place before everything else.
    • 02:32:12
      This is equally as important as Long Bridge.
    • 02:32:14
      Maybe not as glamorous, but equally as important, right?
    • 02:32:17
      We can't start service down in the Richmond area and Main Street without this in place.
    • 02:32:21
      So this project is finally moving along a little bit better.
    • 02:32:26
      We've talked about grant funding opportunities that we have and we're chasing.
    • 02:32:30
      We are looking for, to close the gap on this.
    • 02:32:34
      We don't know the answer.
    • 02:32:35
      We will be back at some point to talk about.
    • 02:32:38
      So right now you'll see that it's a $10.4 million.
    • 02:32:40
      That's only for the final design funding.
    • 02:32:43
      We estimate the project to be over $76 million currently.
    • 02:32:46
      I heard DJ earlier, this one will have a pit, a canopy, lots of lights.
    • 02:32:51
      It's three layover tracks.
    • 02:32:53
      This is a big effort.
    • 02:32:55
      So that $76 million is in line.
    • 02:32:58
      We've got a commitment from Amtrak around the $30 million through IIJA, the $15 million for CDTA.
    • 02:33:04
      That leaves us with a gap.
    • 02:33:05
      What that gap is and what we will need to ask for is still undetermined, but we're working through it.
    • 02:33:10
      So just wanted to give the board a heads up and then we'll be back for this project as well.
    • 02:33:15
      Good progress.
    • 02:33:16
      Assigned the Final Design Task Order and we're re-firing up the design.
    • 02:33:20
      So excited to get going again.
    • 02:33:21
      I think that's it for me.
    • SPEAKER_11
    • 02:33:31
      Okay, so one project in Northern Virginia that we will likely be covering to the board later this year, later in the fiscal year around, it's our third track.
    • 02:33:39
      I know we've presented this many times to the board before, but just to recap, this project
    • 02:33:44
      Basically creates six miles of new mainline through track where it currently ends just north of the Franconia-Springfield BRE Station to just south of Wharton Road and Wharton BRE Station.
    • 02:33:55
      We'll also be replacing the railroad bridge at Povac Creek, widening the bridges at Accotane Creek and Wharton Road.
    • 02:34:02
      And also within the footprint of the project are the railroad bridges over Newington Road.
    • 02:34:08
      You'll see this in our budget documents and other places.
    • 02:34:10
      We track the Newington Road project as separate
    • 02:34:13
      from Third Track, but for all practical purposes, it is part of Third Track.
    • 02:34:17
      It's been designed as part of Third Track.
    • 02:34:19
      It will be constructed as part of Third Track.
    • 02:34:21
      However, it has some separate dedicated funding from VDOT and from an FRA state of good repair grant.
    • 02:34:27
      So we've always tracked it separately, but it will be part of one project that will be procured and constructed with CSX and LEED.
    • 02:34:37
      We are at 100% designed for this project.
    • 02:34:40
      We have started right-of-way acquisition.
    • 02:34:42
      They're well in advance.
    • 02:34:44
      We have 54 properties that are affected by this work.
    • 02:34:48
      We expect to have our properties in hand by the end of this summer.
    • 02:34:52
      And then we will be planning to get to work later this year.
    • 02:34:55
      The schedule that you see here is what our official program schedule shows.
    • 02:35:01
      It's a little bit conservative showing CSX
    • 02:35:03
      going out with their invitation for bid later this summer, getting a contractor on board by the end of the year and starting construction in 2027.
    • 02:35:11
      They are actually trying to be more aggressive with that, put the project out for bid either next month or in July, get a contractor on board and try to start some of that work in the 2026 construction season.
    • 02:35:25
      As I mentioned earlier in our updates, we have been doing some early work at C.P.
    • 02:35:30
      Beltway on this project, so we do have work underway.
    • 02:35:33
      And we're ready to keep it moving.
    • 02:35:36
      The budget that you see here, we have not made any changes to.
    • 02:35:39
      We are tracking on budget.
    • 02:35:41
      This is something that was put together at the 30% mark a few years ago.
    • 02:35:44
      So there are some things in terms of costs that we are watching.
    • 02:35:47
      You know, as Rob mentioned, there's volatility in the construction market, whether it's labor, materials, those sorts of things, the last three years that could come out in our pricing.
    • 02:35:57
      However, we have seen a lot of interest in this project.
    • 02:36:01
      CSX had a lot of bidders for Alexandria 4th Track.
    • 02:36:04
      There's a lot of interest in the corridor.
    • 02:36:06
      So we expect that this is going to be a very competitive procurement, which will be beneficial to our budget.
    • 02:36:11
      And then I guess I'll just leave it at that.
    • 02:36:15
      I think unless there are any other questions that wraps up our budget updates, our project updates.
    • Mariia ZimmermanChair, Board of Directors
    • 02:36:20
      All right.
    • 02:36:21
      Thank you, James.
    • 02:36:21
      So before we break for lunch, I would layer as an item that we would like
    • 02:36:27
      If folks can do another 15 minutes.
    • 02:36:32
      Alright, we have a motion to go into closed session.
    • SPEAKER_01
    • 02:36:38
      So moved.
    • 02:36:40
      I move that the board convene in a closed session.
    • Mariia ZimmermanChair, Board of Directors
    • 02:36:43
      Alright, I think you need to read the formal motion.
    • SPEAKER_01
    • 02:36:54
      I move that the Board convene in a closed session presented to Virginia Code Section 2.23711A7 and 8 for a briefing by staff members in consultation with legal counsel with respect to an asserted contract claim that may result in litigation and requires the provision of legal advice by counsel.
    • Mariia ZimmermanChair, Board of Directors
    • 02:37:14
      Can we get a second for a motion?
    • 02:37:16
      I'll second that.
    • 02:37:22
      And then
    • 02:37:23
      Can all in favor say aye.
    • 02:37:26
      Aye.
    • 02:37:28
      Thank you.
    • 02:37:29
      Those opposed say nay.
    • 02:37:32
      Anyone abstaining?
    • 02:37:34
      The ayes have it.
    • 02:37:39
      A working lunch as we go through our final items here on the extend desk.
    • 02:37:46
      Want to first start, we're going to have a
    • 02:37:50
      DRPT-101 and State Rail Plan update from Emily Stock, who is the Chief of Rail at the Department of Rail and Public Transportation.
    • 02:37:58
      So we will pull up that presentation and thank you, Emily, for coming up today.
    • SPEAKER_08
    • 02:38:05
      I've got all kinds of time now.
    • 02:38:07
      I'm writing back with everybody else at three o'clock.
    • 02:38:10
      Hopefully that train time will work.
    • Mariia ZimmermanChair, Board of Directors
    • 02:38:13
      So yeah, I'm demonstrating the beauty of the flex option when working on infrastructure.
    • SPEAKER_08
    • 02:38:21
      So Emily Stock, Chief of Rail Transportation.
    • 02:38:23
      I haven't been on a train in a while, so coming up here and seeing all the construction was really exciting.
    • 02:38:29
      Thank you, VPRA, for all the progress that you're making.
    • 02:38:35
      So I'm going to give a DRPT 101.
    • 02:38:38
      I'll touch on transit also, not just rail.
    • 02:38:41
      And I've got a lot to cover, a lot of space to cover in short amount of time.
    • SPEAKER_10
    • 02:38:47
      So I'm not going to get to every part.
    • SPEAKER_08
    • 02:39:04
      But I can't go over this slide, not these smiling faces.
    • 02:39:07
      This is our who is DRPT rail team slide.
    • 02:39:12
      And from left to right, we have the planning team, the planning side of the house, and then the grant program side of the house on the right hand side.
    • SPEAKER_07
    • 02:39:21
      Brandon Selleck is our director of rail planning and environmental.
    • SPEAKER_08
    • 02:39:25
      Taylor Holden is a rail planning and data manager.
    • 02:39:31
      Mike Todd is our director of rail program.
    • 02:39:34
      And Linda Fallerson is our
    • 02:39:37
      Rail Capital Program Manager, and all the way to the right is Janet Nineveh, the newest member of the team, who is our rail data support specialist.
    • 02:39:46
      So if you see them around, say hello.
    • 02:39:49
      DRPT is way more than the rail team though, of course.
    • 02:39:53
      We're 66 employees, and we work to connect and improve the quality of life for Virginians through innovative transportation solutions.
    • 02:40:02
      The 1992 General Assembly established us as an independent agency, apart from VDOT.
    • 02:40:10
      What do we do?
    • 02:40:11
      We allocate state and federal funding, we conduct rail and transit studies, we plan and pick funding services and projects, and provide leadership advocacy and funding oversight for rail and transit projects.
    • 02:40:27
      How do we do it?
    • 02:40:28
      We do it by parts with lots of different agencies throughout the state, including VPRA.
    • 02:40:34
      And I'm not going to read through all of these boxes.
    • 02:40:38
      I'm going to move on to public transportation slides.
    • 02:40:42
      You can take a look at our reach for public transportation agencies in Virginia.
    • 02:40:50
      Our transit partners have a huge impact and of course, cover all corners of the state.
    • 02:40:56
      The ridership for transit in Virginia in 2025 was over 150 million trips and that's a 9% year-over-year increase and a 126% increase since 2020.
    • 02:41:13
      And I'll point out some of the agencies that we work with, the types of agencies that we work with,
    • 02:41:19
      throughout the state.
    • 02:41:21
      The map shows areas in darker blue with the traditional fixed route, bus service, and transit service that includes Wamata, BRE, the Tide light rail service in Hampton Roads, and Virginia Bree's inner city routes are in pink, and I'll get into more details about the Breeze in a second.
    • 02:41:44
      You'll see kind of in light blue, I guess it turns out gray on this screen,
    • 02:41:48
      Rural areas of Virginia have demand response service, which is often operated by human service providers that kick up based on passenger requests rather than on a set schedule or timeline.
    • 02:42:03
      And that includes paratransit and microtransit in this category.
    • 02:42:08
      And I wanted to touch on this because this is a little different from what we're used to in the rail world and of course in Northern Virginia, but it means a lot to the people.
    • 02:42:18
      The Breeze, you know we talked a little bit about about extending rail down to Brannadford and Bristol to Southwest Virginia and I wanted to highlight this service that DRPT funds that is really relevant to what VPRA does as you look to expand rail service into different markets.
    • 02:42:43
      Virginia Breeze has provided state-funded intercity bus service,
    • 02:42:47
      since 2017, and it fills the gaps for areas of the state where intercity passenger rail currently doesn't.
    • 02:42:57
      So the beauty of this service aside from the trips that it provides is also the data that it provides.
    • 02:43:04
      You may notice that the routes near our current and future passenger rail routes and DRPT is capturing the ridership numbers, which can shed light on potential future ridership demand, which is really exciting.
    • 02:43:17
      So for reference, 68,000 trips were taken statewide on the Virginia breeze last year.
    • 02:43:23
      And it's really exciting.
    • 02:43:25
      We just added a new route in spring this year, the Tidewater-Pleasant route, which goes east-west.
    • 02:43:34
      And what's wonderful is that those corridors that we're looking at for expansion potentially in the future,
    • 02:43:44
      The east-west corridor follows what's known as the Commonwealth Corridor, and then in the western rail corridor, this service already serves Radford, Woodville, and Bristol.
    • 02:43:57
      So it's an exciting precursor to potential future rail service.
    • 02:44:05
      So this is a map of the freight rail network, which you all are probably already familiar with.
    • 02:44:09
      Of course, Norfolk Southern is in the blue lines, CSX is in green, and then we have short lines in purple.
    • 02:44:16
      We have nine short lines that operate in Virginia, and they provide vital last mile service and switching services for Virginia businesses.
    • 02:44:25
      My next few slides touch on DRPT's freight funding programs and their iterations of these programs have been around
    • 02:44:33
      It's before DRPT existed as a standalone agency.
    • 02:44:38
      And the reason for this is because we recognize the value of freight rail to Virginia.
    • 02:44:45
      We do this because shipping by rail runs the truck, avoids 1.5 billion miles of truck travel in Virginia, leading to $85 million annually in pavement maintenance savings.
    • 02:44:59
      So this is a huge value to Virginia.
    • 02:45:04
      How do we pay for projects in our freight rail sector?
    • 02:45:10
      We do it through the Commonwealth Rail funds for the most part.
    • 02:45:13
      According to Virginia Code, DRPT does spend 93% of the Commonwealth Rail funds revenue to VPRA, but we keep 7% for ourselves and use it for freight rail grants and rail planning.
    • 02:45:29
      So this is a snapshot of the six year improvement program that we're working
    • 02:45:33
      right now for 2027 to 2032.
    • 02:45:37
      We update our SIP along with VDOT every spring, and Mariia, the VDOT Commissioner, and the Secretary Donahue have been good spots in the state for the past few weeks to prevent this plan in every district of Virginia.
    • 02:45:54
      The left side shows the full picture of FY27 to 32, and the right side of the slide shows FY2027,
    • 02:46:03
      The STIP also includes VPRA-programmed projects, which total over $100 million for FY 2027.
    • 02:46:11
      You'll see at the bottom right of the screen.
    • 02:46:14
      And the CTB will vote on this package in June.
    • 02:46:21
      DRPT is proposing a number of new branch-funded projects in the STIP.
    • 02:46:26
      And this gives you a flavor of the great projects that we're recommending.
    • 02:46:32
      And the first is Hubsprat Middle near Winchester, which has plans to expand an onsite rail yard.
    • 02:46:40
      Shenandoah Valley Railroad is working on the programmatic track and roadbed upgrades in Augusta and Rockingham Counties.
    • 02:46:50
      The Norfolk-Portsmouth Beltline is doing bridge, rail, and tie upgrades.
    • 02:46:55
      and the Buckingham Branch Railroad is doing some improvements that are actually, some of those are on the property that BPRA owns or will own.
    • 02:47:04
      There are three crossover projects that we're proposing for funding in Goshen, Charlottesville and Dodd as well.
    • 02:47:13
      And then also bridge improvements along the Richmond and Allegheny Division for Buckingham Branch.
    • 02:47:21
      So this slide shows the locations of those projects, all funded through DRPT rail programs, which are 100% state funded.
    • 02:47:32
      They're application based with carload performance requirements of up to 15 years.
    • 02:47:38
      So we make sure that there are common carrier requirements that exist with these agreements that we have with railroads
    • 02:47:48
      And we want to make sure that the projects that we find stay in use.
    • 02:47:52
      And so we make sure that their carload performance that the companies agreed to at the beginning of the project are maintained throughout the life of the project.
    • Michael McLaughlinChief Operating Officer
    • 02:48:02
      Good question.
    • 02:48:02
      On the Buckingham branch, is that double?
    • SPEAKER_08
    • 02:48:05
      So there's a, there is a cross, there are three new crossovers, one in Goshen,
    • 02:48:16
      I mean, I can give you any details.
    • Michael McLaughlinChief Operating Officer
    • 02:48:18
      Thank you.
    • 02:48:19
      And just to remind everyone, so we bought from CSX Richmond, Allegheny Division for Court of Preservation, the agreement we have with Bucking, the operator of record, they will maintain.
    • 02:48:30
      So even though we own the track and the land underneath, they have many benefits.
    • 02:48:35
      They can now run tourist service if you haven't seen it.
    • 02:48:37
      It's great, by the way.
    • 02:48:40
      And one of the trade-offs that they happily took on is they'll cover maintenance, and they often do work with DRPT on that.
    • SPEAKER_08
    • 02:48:47
      Sure.
    • 02:48:48
      And our programs resulted in 10.6 million trucks diverted from Virginia roads last year.
    • Patricia DoerschMember, Board of Directors
    • 02:48:57
      I'll just ask one question.
    • 02:48:58
      The Hubscrap Metal, are they a shipper or are they a short line railroad?
    • SPEAKER_08
    • 02:49:04
      Oh, they are a shipper.
    • 02:49:06
      So it's an industry yard.
    • 02:49:12
      So our freight program is one of the three
    • 02:49:17
      Great Rail funding programs that DRPT manages.
    • 02:49:21
      This is for capacity improvements, and that's what HUB Scrap Battle is using to expand its yard.
    • 02:49:28
      These are for projects that are construction ready.
    • 02:49:30
      They must have 30% design already sewn up in order to qualify.
    • 02:49:36
      And the freight program leverages private matching funds.
    • 02:49:40
      Projects with a higher percentage of private match in their applications do score better
    • 02:49:45
      And each project must achieve state transportation goals that are established in the state's multimodal transportation plan.
    • 02:49:57
      And funding for this program comes from the Commonwealth Rail Fund.
    • 02:50:01
      Second program is the Rail Preservation Fund.
    • 02:50:04
      The purpose of rail preservation is to keep the short line railroad network in a state of good repair.
    • 02:50:11
      And so that's what Buckingham Branch is using for
    • 02:50:15
      for the Richmond Allegheny Projects.
    • 02:50:18
      And a 30% private match is required when it makes, and so it makes this a true partnership with short-line railroads who have skin in the game.
    • 02:50:29
      And we get $4 million annually for this program through the biennial budget.
    • 02:50:36
      And the program is very oversubscribed.
    • 02:50:39
      Of all of our programs, this one is the most oversubscribed
    • 02:50:44
      Over the past few years we've worked with the General Assembly to allow for flexibility and now we can flex up to 50% of our portion of the Commonwealth Rail Fund every year to rail preservation projects if we need to.
    • 02:51:00
      The next program is the Rail Industrial Access Program.
    • 02:51:04
      It's our economic development incentive that funds rail sidings for growing businesses
    • 02:51:11
      that are adding jobs and capital investment in the Commonwealth.
    • 02:51:14
      The program gets $5.5 million annually out of the VDOT construction fund.
    • 02:51:20
      And that amount is shared with VDOT's sister economic development program for roadway access.
    • 02:51:26
      And so we do go to the CTB.
    • 02:51:29
      This program really meets the needs of witnesses.
    • 02:51:32
      So it's funded on a rolling basis as projects come along.
    • 02:51:39
      and we did have an uptick in RA applications after the pandemic and after we did a marketing campaign since 2022.
    • 02:51:49
      Since then we've had 17 projects, over 3,000 jobs have been committed to as part of this program and over 51,000 trucks have been diverted.
    • Beth RhinehartMember, Board of Directors
    • 02:52:04
      So now I'm moving over to... Just a real quick question on the access program.
    • 02:52:12
      Would that have any play or factor into, for example, a little report?
    • 02:52:17
      Or would that be outside of that fund, I guess, if they're already connected for an annual report?
    • SPEAKER_08
    • 02:52:25
      So one of the factors that would
    • 02:52:30
      that may preclude something like that is that it's a $750,000 cap per project.
    • 02:52:36
      And so if there's a business that is coming in that's associated with an inland port, I'm sure that this would be applicable.
    • 02:52:45
      But for a larger project like that, it's not necessarily, it's not necessarily gonna do perfect.
    • 02:52:51
      Now, there could be some flexibility.
    • 02:52:54
      We are looking at some flexibility in this program.
    • 02:52:59
      So stay tuned.
    • 02:53:01
      But if you have any, call me and I'll let you know for sure.
    • 02:53:06
      Because there, yeah, the cap is, we've had it raised from $450,000 per project to $750,000
    • 02:53:15
      But usually those are smaller scale projects than a full-blown inland port.
    • Mariia ZimmermanChair, Board of Directors
    • 02:53:22
      Yeah, often it's like, you know, they're going to add 1200 feet to connect to the short line or something, or they do that siding for it.
    • 02:53:30
      So they tend to be smaller projects, but they're a rolling basis, so someone can apply at any point.
    • 02:53:37
      And so definitely reach out to the team if there's interest, because I think
    • 02:53:42
      It is a small but mighty little program, and I think the more we can kind of get awareness, hopefully we can also educate about, we know the costs for construction have really gone up, and so $750,000 doesn't get you very much.
    • 02:53:57
      And so, you know, are there opportunities in the future to maybe revisit?
    • 02:54:00
      That would be a question for the General Assembly.
    • SPEAKER_08
    • 02:54:05
      Yeah, we can show demand.
    • 02:54:07
      That always helps.
    • 02:54:09
      So I'll move over from grant programs to planning initiatives.
    • 02:54:13
      This is a relatively new planning initiative for us, the DRPT rail crossing initiative since the dawning of FRA's rail crossing elimination program that came along with IIJA.
    • 02:54:27
      We've been successful at partnering with localities that have high priority crossings to apply for planning projects to determine what type of crossing improvements might be needed
    • 02:54:39
      and as a first step to getting additional funding to actually build a, you know, a grade separation if it's warranted or some other safety measure at the crossing.
    • 02:54:50
      So, DRPT provides technical assistance for grant applications and state matching funds toward the projects.
    • 02:54:58
      and we're fortunate that we expect the program to continue to be funded through the next federal re-authorization.
    • 02:55:06
      That's what it looks like from this proposal, the Build America 250.
    • 02:55:13
      And for, there is a, it's out right now for rail crossing elimination and for Christie, as you all are probably aware, DRPT is working with the Hampton Roads Transportation Planning Organization
    • 02:55:28
      to propose a multi-jurisdictional application for this round, which is focused on the Port of Virginia.
    • 02:55:35
      So it's a little different for us this time since we're not going to a bunch of different localities individually.
    • 02:55:40
      But I think this will be a good project to show how we can look at a system of crossings and propose solutions so that we're not just doing spot changes, spot improvements.
    • 02:55:55
      And DRPT is also expanding this work beyond just an RC program to develop a rail crossing toolkit.
    • 02:56:04
      So that's a planning initiative that we're going to be starting this summer that could be a resource for localities.
    • 02:56:11
      And I got into this work for the first time doing the DC to RBA NEPA work.
    • 02:56:16
      You know, there are so many crossings in that corridor, not just from DC to RVA, but also the study that went down to North Carolina.
    • 02:56:25
      And of course, Virginia and North Carolina had different ideas about what treatments might be necessary, but we were forced to look at a system of crossings.
    • 02:56:34
      We couldn't just look at them in isolation.
    • 02:56:36
      So I think that's a good way to look at this now, too.
    • 02:56:42
      So before I get into DRPT's biggest rail planning initiative, the statewide rail plan, here is a slide that outlines DRPT and VPRA responsibilities side by side.
    • 02:56:54
      And the big takeaway from this slide is that VPRA is responsible for all aspects of passenger rail and all those categories with the exception of statewide rail planning.
    • 02:57:04
      And the idea is that DRPT sets long range plans for passenger rail expansion
    • 02:57:10
      with a tie to VPRA through its director, who chairs the VPRA board, and VPRA designs and builds according to those plans.
    • 02:57:20
      So that's our link of tying it all together.
    • 02:57:23
      So the Virginia Statewide Rail Plan, FRA provides guidance for the rail plan, which encourages states to update rail plans every four years.
    • 02:57:34
      and so DRPT started its effort this year and we hope to have it wrapped up by the end of 2026.
    • 02:57:42
      The guidance directs us to establish existing conditions and progress and report on progress since the last rail plan.
    • 02:57:50
      It includes a six year and 20 year planning horizon for funded and unfunded projects.
    • 02:57:58
      And the guidance has remained stable since 2013, which has allowed us to compare
    • 02:58:04
      The data that we collect year to year and also seeking to escape, which is kind of nice.
    • 02:58:14
      Every year I think FRA is going to update that guidance and it doesn't.
    • 02:58:17
      And chapter two is the very longest chapter, but it's nice to be able to compare things and to keep it stable.
    • 02:58:24
      So what goes into the statewide rail plan?
    • 02:58:27
      We put funded and unfunded projects in, like I mentioned, and we work with our partners, the railroads, VPRA, of course, VRE and Amtrak to establish that project list.
    • 02:58:41
      And we analyze public input in the form of survey results.
    • 02:58:46
      We do trans search, we do purchase trans search data, and we look at current and projected freight movements.
    • 02:58:54
      And we assess historic and current ridership and OTP as well.
    • 02:59:00
      And the end result is a group of investment recommendations, benefit cost analysis on those recommendations, and also an identification of funding needs going forward.
    • 02:59:14
      So the rail plan will update our assessment of the value of mode shift for rail in Virginia as well.
    • 02:59:20
      Our standard metric for Virginia is one freight car to 3.4 trucks off the road.
    • 02:59:27
      And so all of those trucks off the road stats I was giving you before are based on this metric.
    • 02:59:33
      And I may be preaching to the choir here with this slide, but these benefits encapsulate why DRPT rail division does what it does, because rail transport is safer, cleaner, and cheaper.
    • 02:59:46
      and overall in the 2022 rail plan, we assess that $2.1 billion was saved by diverting freight to rail rather than trucks and the roadways.
    • 03:00:03
      And we expect those numbers to be even more impressive for the 2026 plan when we update these numbers.
    • 03:00:12
      So the rail plan requires plenty of coordination
    • 03:00:14
      and I'll focus on VPRA coordination here.
    • 03:00:18
      Of course, Transforming Rail in Virginia, it's considered an existing condition for this plan, all phases and all Transforming Rail in Virginia projects are included in the short and long-term project list through our VPRA coordination.
    • 03:00:34
      The VPRA leadership were included in some high-level interviews and staff responded to our stakeholder survey.
    • 03:00:41
      Thank you very much for that.
    • 03:00:43
      That helps.
    • 03:00:44
      And we also will be having some stakeholder group meetings in the next few months that will meet four times each.
    • 03:00:52
      And so be on the lookout for invitations.
    • 03:00:56
      You know who you are.
    • 03:00:58
      We also have regular coordination with VPRA throughout the year, even when we're not doing a rail plan, we have monthly DRPT, VPRA planning meetings.
    • 03:01:08
      We're also actively involved in the station policy
    • 03:01:13
      guidance document that Laura mentioned in her presentation that's underway right now.
    • 03:01:21
      And also we meet on a regular basis to talk about federal programs like Corridor ID.
    • 03:01:31
      So our goal for this rail plan is to build on the successes of our 2022 rail plan, which was the first in the nation to be developed using the ArcGIS story map format.
    • 03:01:43
      And so we're going to continue that in this rail plan.
    • 03:01:45
      We do have a beefed up public involvement element this year.
    • 03:01:50
      We're working with UVA's Institute for Engagement and Negotiation on that.
    • 03:01:55
      And we just got finished with our first round of surveys.
    • 03:01:59
      We got over 2,000 responses.
    • 03:02:02
      and I'll give you a preview of the results.
    • 03:02:06
      I don't think this will surprise you very much though.
    • 03:02:09
      There was a lot of support for and strong demand for increased connectivity and system growth in passenger rail and freight rail.
    • 03:02:18
      With regard to passenger rail, there was a strong preference for expanding rail access.
    • 03:02:23
      and service to more destinations.
    • 03:02:25
      But those destinations, people favored expanding travel within Virginia and DC rather than expanding to more destinations.
    • 03:02:35
      So into out-of-state destinations, I should say.
    • 03:02:40
      So lots of support for in-state travel.
    • 03:02:43
      And the 60%
    • 03:02:48
      supported a balanced approach that includes both new routes and enhanced service on existing lines.
    • 03:02:55
      So the plan will also look at trends, the unique and changing landscape of rail in Virginia related to rail funding, technology, market forces.
    • 03:03:09
      Last time we focused a lot on pandemic issues and precision railroading and how that changed the base of
    • 03:03:17
      of the rail landscape.
    • 03:03:20
      And this iteration I expect will also be very merger issues and some of the same things that are on the list here.
    • 03:03:30
      IIJA reauthorization, infrastructure resources.
    • 03:03:35
      So corridor ID in Virginia, I'm not sure how much you talked about this with BPRA folks.
    • 03:03:43
      It's a long range planning process.
    • 03:03:46
      Yes.
    • 03:03:47
      Okay.
    • 03:03:47
      So it's been a couple of years.
    • 03:03:48
      So it provides a framework.
    • 03:03:50
      It's FRA's framework for long range passenger rail planning in Virginia.
    • 03:03:54
      And it will be the, the efforts that Virginia is taking on will be incorporated in the rail plan.
    • 03:03:59
      As the map here shows, these corridor ID, corridors really near the existing rail that we have and planned rail that we're, that we're looking at.
    • 03:04:11
      So the Commonwealth corridor, east west,
    • 03:04:14
      D.C. to Bristol, Charlotte to D.C., and Cardinal Daily Service.
    • 03:04:19
      That's one that's led by Amtrak to get daily service.
    • 03:04:23
      Or were you going to say something like that?
    • Michael McLaughlinChief Operating Officer
    • 03:04:24
      Yeah, since Emily asked, we briefed you all.
    • 03:04:27
      So our program preceded the court ID program, and we've been working through that with FRA over the past few years.
    • 03:04:34
      How do we, we want to move forward with you.
    • 03:04:37
      We love the idea for future planning.
    • 03:04:39
      and FRA staff to their benefit and have understood that we're not starting at step zero.
    • 03:04:47
      We're already at step seven or eight, 30% design construction.
    • 03:04:51
      So we're working with them, but some of these like DC to Charlotte is what we just talked about for the last four hours, as far as the DC to Richmond Park.
    • 03:05:02
      And part of DC to Bristol, we're already New River Valley.
    • 03:05:05
      We're already one way there.
    • 03:05:06
      So we are working with FRA and they're working
    • 03:05:09
      involved with us to try to figure out what is a good step for us to be involved in this.
    • 03:05:13
      So I don't want to make it sound as though we haven't talked with you all, but a lot of our work is already way ahead of Corridor ID and FRA acknowledges that and knows that.
    • SPEAKER_08
    • 03:05:21
      And that's a very good point.
    • Beth RhinehartMember, Board of Directors
    • 03:05:23
      Oh, sorry.
    • 03:05:26
      You may get to this.
    • 03:05:27
      Thank you.
    • 03:05:29
      How does this play into how this is all overlaying from Central and FRA's longest of facts, the Houston of the DC and beyond?
    • 03:05:38
      How do those communicate or work in the culture with, or do they at all?
    • SPEAKER_08
    • 03:05:46
      So I, and I, because these were all, well, some of these were interest state, like the North Carolina, Virginia.
    • 03:05:57
      I don't know how the, I think that was more of an Amtrak led study.
    • 03:06:02
      So, and whereas this is an FRA program,
    • 03:06:05
      But I did, I was looking at the 250, so the Build America 250 Act, the proposed reauthorization and it did mention that Amtrak long distance would still be considered and that this program would still be part of the mix too and still funded.
    • 03:06:26
      Were you going to say something?
    • SPEAKER_15
    • 03:06:28
      Yeah, if I may add, so Amtrak was also eligible for the CID program, and they did apply to a lot of people.
    • 03:06:34
      So, CID was allowed to do that, which was all the way to Chicago as an Amtrak and CID application, which they were allowed to work for.
    • 03:06:42
      And some of these corridors do overlap with other state CID projects as well, but that's just, you can see, they don't go out to the property.
    • Mariia ZimmermanChair, Board of Directors
    • 03:06:52
      And so, for the FRA CID program,
    • 03:06:55
      For their program, it's a four-phase program.
    • 03:06:57
      The phase one, which we are in, is the planning phase.
    • 03:07:01
      And then the hope from FRA is as corridors move in phases, you would prioritize to figure out which corridors really are the most realistic and feasible to actually be able to put into service.
    • 03:07:16
      And so I think it's kind of like with IJA creating this program from scratch,
    • 03:07:22
      There was, a lot of states put in a lot of potential quarters to look at.
    • 03:07:26
      I forget how, we have four in Virginia, North Carolina has what, nine or something like that?
    • 03:07:31
      12.
    • 03:07:33
      So like, so there was kind of throwing spaghetti at the wall in some ways.
    • 03:07:36
      I mean, there were some determinations there, but I think being able to do these feasibility studies, which is part of the statewide rail thing too, like looking at the costs, the benefits, you know, what's all entailed with that.
    • 03:07:48
      And as we move from kind of this planning,
    • 03:07:52
      As it gets more real, it also moves into VPRA.
    • 03:07:55
      If we say, okay, this is a corridor we want to be developing for, as Mike noted, some of this, we already were committed and it's well underway.
    • 03:08:03
      And so we are a little bit unique from some of our peers with this, but I think it's the FRA's perspective is like as corridors move through these phases, they become more real and would fit into a national rail network plan.
    • SPEAKER_04
    • 03:08:19
      Yeah, I think that's done right.
    • 03:08:21
      I think the challenge is that every single CIB award goes to a state or to an entity, Amtrak, whoever it was, and every single one of them thinks that their quarter is going to keep going through the process and for this to be successful.
    • 03:08:34
      FRA's got to pare down and say, okay, we awarded whatever the number is, we need to pare that down to 20.
    • 03:08:39
      And then after that, we need to pare it down to 8.
    • 03:08:42
      Or else it's going to be a lot of C papers and not a whole lot of A papers.
    • 03:08:46
      And FRA knows, and to my point,
    • 03:08:48
      They've worked well with us and others.
    • 03:08:51
      They need to find a smaller number of A quarters, A plus quarters, A minus quarters that they can move forward for this program to be successful.
    • 03:08:59
      And the larger-length fact that they're not A quarters.
    • SPEAKER_08
    • 03:09:03
      And that long distance that you were talking about, the long distance study, I think I know what you mean.
    • 03:09:07
      You're talking about the Houston, New York, Houston route?
    • 03:09:10
      Yes, that specific route has overlaps with CIDs all over the place.
    • 03:09:15
      So we can look at that and see where those overlaps are.
    • 03:09:19
      So that's something I can follow up with you about because we need to touch on that in the rail plan.
    • 03:09:24
      I mean, at least to just document exactly the question that you're asking.
    • 03:09:28
      One more point I'll make about CIB before we move on.
    • Mariia ZimmermanChair, Board of Directors
    • 03:09:32
      You want to know at the time?
    • SPEAKER_08
    • 03:09:34
      Yeah.
    • 03:09:35
      Okay, okay.
    • 03:09:36
      I'll just keep going.
    • 03:09:41
      So, Virginia North there, Carolina Interstate High-Speed Rail Compact is another effort.
    • 03:09:47
      It started in 2004, not, oh, this one's still saying 1992, yes, so there's a typo there.
    • 03:09:55
      But much has changed in 20 years.
    • 03:09:58
      This group has formed the Southeast Rail corridor in 2019 and has brought in states from all over the Southeast.
    • 03:10:08
      And it also received a grant recently to do some network analysis in the region.
    • 03:10:18
      with partners throughout the Southeast.
    • 03:10:21
      And so what's great about this is that we can support each other's projects.
    • 03:10:25
      Obviously, in order to get to the Northeast corridor for any of these Southeastern states, they have to go through Virginia.
    • 03:10:30
      So they've all been wonderful supporters of the Long Bridge project.
    • 03:10:36
      So what's next?
    • 03:10:37
      The Rail Plan Schedule.
    • 03:10:38
      As I mentioned before, we plan to wrap things up by the end of the year.
    • 03:10:43
      We do have a public meeting June 1st.
    • 03:10:47
      If you want information about it, I can help you out with that.
    • 03:10:51
      We'll be talking about our survey results.
    • 03:10:57
      And I mentioned that we've been reaching out to stakeholders, doing more public involvement as the summer goes on.
    • 03:11:03
      And so hopefully you'll stay in touch with us and I'm happy to provide an update probably through the director's report at another VPR meeting.
    • 03:11:13
      That's all I've got.
    • Mariia ZimmermanChair, Board of Directors
    • 03:11:15
      Thank you.
    • 03:11:17
      Thank you, Emily.
    • 03:11:20
      Yeah, and I will also just mention with the interstate rail compact, the hope is that for the first time in two years, we would have legislators meeting from both states.
    • 03:11:31
      We'll see if we can pull that off.
    • 03:11:33
      But we have been doing some briefings for the new members that have been assigned and senators and we've been doing that together from the VPRA and our DRPT team.
    • 03:11:44
      So it's been a good opportunity to also just kind of keep always talking to the General Assembly about the good work that's happening in the VPRA and continued work we hope to do going forward.
    • 03:11:58
      Thank you.
    • 03:12:00
      All right, so we'll now turn to item 16 on the agenda for those who are following along.
    • 03:12:04
      So thank you.
    • SPEAKER_15
    • 03:12:07
      Good afternoon, everyone.
    • 03:12:09
      I know you all are in Germany.
    • 03:12:13
      He's on vacation and I hope he's not see through this thing.
    • 03:12:17
      So I'm the Senior Manager of Passenger Operations for VPRH and I'm here to talk about how service is performing.
    • 03:12:27
      Also, you've heard a lot about construction, ongoing construction on the corridor.
    • 03:12:31
      And so what, from an operational perspective, to coordinate with the construction and engineering teams, and also given the reduction in service that we had to implement recently, what are we doing to mitigate that service reduction?
    • 03:12:46
      So starting off with VRE service in Virginia, to orient everyone, VRE runs two lines in Virginia.
    • 03:12:53
      The red one, Fredericksburg line,
    • 03:12:55
      Ransone CSX Mainline, 8 daily round trips on that route.
    • 03:13:00
      Manassas Line is the one in blue.
    • 03:13:02
      It operates on the Ennis Mainline.
    • 03:13:04
      Again, the daily round trips on that line as well.
    • 03:13:09
      So for VRE performance, I'm going to go anti-clockwise starting up top.
    • 03:13:14
      The way on time performance is measured for VRE.
    • 03:13:18
      A train is considered on time if it arrives at the last station within six minutes of scheduled arrival.
    • 03:13:25
      So if you look at the chart on the left, the two bars in gray, that's the April year over year performance.
    • 03:13:33
      April of 2026 was a little lower than April of 2025, daily minutes went up.
    • 03:13:42
      The chart on the top compares the two lines, Fredericksburg versus Manassas, Manassas line did a little bit better than Fredericksburg line.
    • 03:13:50
      But the main thing here is the top 10 daily causes you'll see
    • 03:13:55
      Maintenance of wave work, that's the biggest theme, or was the biggest theme in spring and April specifically.
    • 03:14:02
      In Virginia, CSX was doing a lot of intense maintenance of wave work on our corridors on the RFMP, and that created a lot of congestion on the corridors.
    • 03:14:13
      You'll see train interference, slow orders, that are symptoms of the maintenance of wave work pushing freight into the daytime work windows.
    • 03:14:22
      So the most frequent and most impactful delays were all related to the maintenance of rail work.
    • 03:14:28
      The good news is that most intense work is done now and we are ready for the summer season where passenger volumes go up and also heat orders kick in.
    • 03:14:39
      Moving on to Amtrak service, again to orient everyone, the dark blue lines are Amtrak Virginia's trains.
    • 03:14:47
      So, six daily round trips.
    • 03:14:48
      That is down from eight daily round trips that we had until January of this year.
    • 03:14:53
      We had to reduce service because of Long Bridge North package.
    • 03:14:57
      We did start two mountain roads and two Richmond round trip bus routes.
    • 03:15:03
      The lines in Orange round trip are long distance trains, so six daily trains, five of which go over the Long Bridge.
    • 03:15:09
      And then the one in Carolinian Blue is the North Carolina supported train that also goes to Virginia.
    • 03:15:18
      So for Amtrak Virginia performance, those are the dark blue lines.
    • 03:15:22
      Starting from the top, an Amtrak train is considered on time if it arrives within 15 minutes of scheduled arrival at all stations and not the same.
    • 03:15:34
      The chart on the left, you see the two bars in grey.
    • 03:15:37
      April of 2026 was marginally better than last year.
    • 03:15:43
      Delay minutes went down.
    • 03:15:45
      Of the three routes, Roanoke Route performed the best.
    • 03:15:49
      Again, we know RFMP, CSX was doing maintenance of their work.
    • 03:15:54
      And the top 10 relay causes freight interference or train interference in general as a symptom of freight being pushed into the daytime work windows, passing congestion on the corridor, which are also related to the maintenance of their work.
    • 03:16:10
      Amtrak Long Distance Performance.
    • 03:16:12
      So long distance trains are also, their on time is also measured in the same way as state supported trains.
    • 03:16:17
      The only difference is they have longer distance to travel and more chances to get tripped up by service.
    • 03:16:24
      Long distance performance also does a little bit compared to last year.
    • 03:16:29
      You'll see Floridian with the worst performance of the three trains.
    • 03:16:33
      Floridian again has the longest distance to travel and again, more chances to get messed up.
    • 03:16:38
      Same team curve, train interference, freight interference, slow orders were all symptoms of the CSX work that was happening on the RFP.
    • 03:16:48
      One thing you notice weather related delays are starting to show up as the summer season kicks in, heat orders will kick in and trains will start slowing down.
    • 03:16:59
      But there is a good news story.
    • 03:17:01
      And our shining star is Washington Union Station through the service performance work with CSX Amtrak and VRE.
    • 03:17:08
      We're putting a great emphasis on Washington Union Station.
    • 03:17:11
      So the chart on the left, you'll see April of 2026.
    • 03:17:14
      It's one fourth of what the delays we were seeing at Union Station last year.
    • 03:17:20
      And to Amtrak's credit, they put a lot of emphasis on improving Union Station.
    • 03:17:26
      And this gives us, the Virginia Service, a chance to do better down south here.
    • 03:17:32
      So once Union Station is taken care of, things do have a chance to succeed down south.
    • 03:17:37
      The chart on the right talks about the specific trains.
    • 03:17:41
      Again, Peridian is the most impacted train because more chances to get tripped up.
    • 03:17:47
      With Union Station being fixed and being a success story, we are moving our focus to Alexandria now.
    • 03:17:53
      and this chart shows passenger holds and ADA delay minutes at Alexandria.
    • 03:17:59
      So this data is for the last four years and you'll see a pattern in the delays.
    • 03:18:07
      So the tall peaks are all in the high passenger dealing months, November, December are the mountaintops, January, February lower ridership months are the valleys.
    • 03:18:18
      April of 2026 at Alexandria was a little bit
    • 03:18:23
      worse than last year.
    • 03:18:25
      Delay minutes are picking up.
    • 03:18:27
      We know there's construction going on.
    • 03:18:29
      And so we are watching this really closely and this has become our focus right now for passenger operations.
    • 03:18:38
      As you heard earlier before, earlier today, there's intense construction going on, three projects in the Alexandria Station area.
    • 03:18:48
      The success story out of this is the temporary platform that you see in the center and the right image.
    • 03:18:55
      That track was never utilized for passenger or rarely utilized for passenger service.
    • 03:19:00
      And with the temporary platform there, it has become a primary loading location for passengers.
    • 03:19:05
      So this is an improvement, although temporarily during construction, this is an improvement for over what, how things work.
    • 03:19:14
      So what are we doing on the operation side?
    • 03:19:18
      As I mentioned, we are coordinating closely with engineering and construction teams.
    • 03:19:23
      This is a snapshot of scope charts that we have created.
    • 03:19:27
      The main thing to note is we are looking at each construction phase.
    • 03:19:32
      For example, this is an outage that happened earlier in May this year.
    • 03:19:37
      This talks about which tracks are out of service.
    • 03:19:39
      But the main thing is we are talking about, and this is at Alexandria, but we are evaluating customer impact.
    • 03:19:46
      So if tracks are out of service, what does it mean for the customer?
    • 03:19:50
      And we are looking at what do we need to coordinate with Amtrak with, with their stations team, with their transportation team, what do the crew and conductors need to know about this construction?
    • 03:20:01
      What kind of notices have to be sent out for passengers?
    • 03:20:03
      So all of this is top of our mind.
    • 03:20:06
      We are in training phase mode right now.
    • 03:20:14
      A lot of more intense construction is coming up and we are learning and making sure that our customers are taken care of during this construction activity.
    • 03:20:23
      On that being said, we are also watching schedules closely.
    • 03:20:29
      A lot of projects will come online and spring and summer of 2027, we are almost to the point of
    • 03:20:36
      maybe creating t-shirts to say Summer of 2027.
    • 03:20:39
      We're not paying for those, by the way.
    • 03:20:46
      It's going to be a lot, a lot of projects under construction all at the same time.
    • 03:20:50
      And so by learning with the Alexandria Project, we are preparing on how to manage all of that coming up.
    • 03:21:00
      And then the biggest thing here is, as you've heard before today,
    • 03:21:05
      Long Bridge work window, which is a time when there's no scheduled train service on the corridor.
    • 03:21:15
      Went up from 8.15 to 1 p.m.
    • 03:21:18
      Earlier it used to close at 11.45.
    • 03:21:22
      We have extended it to 1 p.m.
    • 03:21:24
      So all the scheduled trains, commuter as well as passenger trains, have been scheduled to not interrupt this window so that the project teams can get time to work on the corridor, do track-fouling activities,
    • 03:21:36
      With the exception of Cardinal, that's the Amtrak long distance train, 51.
    • 03:21:41
      And Cardinal runs three times a week, and only two days a week it will disrupt the work window.
    • 03:21:47
      We tried a lot to work with CSX to find a better schedule for Cardinal.
    • 03:21:53
      It didn't work.
    • 03:21:54
      So only that train is allowed to the work window twice a week.
    • 03:21:58
      And with that, I'm going to turn it over to Ian to talk about how the work window's up in your context.
    • SPEAKER_19
    • 03:22:04
      Thank you, Ashwini.
    • SPEAKER_11
    • 03:22:05
      Good afternoon again.
    • SPEAKER_19
    • 03:22:07
      So a lot of the activities that we do during the work window we've already highlighted earlier today.
    • 03:22:14
      However, I wanted to take a little time and highlight how train traffic impacts these activities and why this is so necessary, right?
    • 03:22:24
      So on the left-hand side, you have a micropile rig that's building out the foundation elements in Main Avenue.
    • 03:22:32
      This has gone very smoothly.
    • 03:22:35
      That piece of equipment has a mast that at times extends up to about 40 feet, right?
    • 03:22:42
      Should something catastrophic happen with this equipment and any of this equipment here, it has the potential to lay into the tracks, right?
    • 03:22:49
      We don't want that to happen as the train passes.
    • 03:22:53
      So performing that activity, the micro-pile, is important to perform during the work window.
    • 03:23:01
      And as you can see, it's probably a little difficult, but the timestamp, they're running all the way up to one o'clock, right?
    • 03:23:07
      They're using every available minute they can during the work window to get as much done as they can.
    • 03:23:13
      On the right hand side, we have the drill shaft rig, which has about 90 feet of boom in it.
    • 03:23:20
      Again, very sizable piece of equipment that has potential to foul should an issue arise.
    • 03:23:31
      Moving into some of the more recent activity on the left-hand side, that's the supportive excavation pile driving wall construction that they're performing at Ohio Drive, just south of the Washington Channel.
    • 03:23:48
      These pile, as they are driven, actually are inside the clearance envelope of a train, right?
    • 03:23:55
      You could not pass a train while this operation is going on, right?
    • 03:24:00
      Without this work window, this activity, instead of taking weeks, would probably be up to three or four months, right?
    • 03:24:10
      The size of window required, you probably are only going to see that on Saturdays, right?
    • 03:24:16
      And again, we can't work overnight due to this being a noisy activity.
    • 03:24:22
      On the right-hand side, you see the trussle construction across Washington Channel.
    • 03:24:25
      Looking from the East Potomac side into DC, the portals area across Main Avenue, this crane here has 105 feet of boom in it.
    • 03:24:37
      And even though it's 50 or 60 feet from the tracks, remember, if something goes wrong, there's potential that this crane would lay over across the tracks.
    • 03:24:48
      And actually where it's at would lay even farther than that towards 14th Street.
    • 03:24:55
      So at the operation that as they're moving sizable loads, we're driving 110 feet worth of pile here.
    • 03:25:05
      You have to splice two sticks of pile together.
    • 03:25:08
      It requires the trains aren't passing during that time.
    • 03:25:13
      Again, both activities have been extremely efficient.
    • 03:25:20
      All right, and to wrap up, I will touch briefly on our noise variance efforts, right?
    • 03:25:26
      We have been working very closely with the Advisory Neighborhood Commission, which is the hyper local elected officials within the district, the neighborhood really, in the area we're working in, in order to breach some agreement where we can get after hours permits, right, where we can go out and do activity.
    • 03:25:50
      Again, that aren't that noisy.
    • 03:25:52
      It's not like we can go out and drive pile overnight, 3 a.m., that sort of thing, but where we would be able to do limited activity overnight.
    • 03:26:03
      So do want to make the point, emphasize that should we achieve getting an after hours permit, that will not reduce the need for this during the day.
    • 03:26:17
      Any questions on
    • SPEAKER_11
    • 03:26:20
      and the North activity.
    • SPEAKER_15
    • 03:26:27
      Thank you, Ian.
    • 03:26:29
      So, as I mentioned before, we did have to reduce two ground trips, so four daily trains to accommodate this one window.
    • 03:26:39
      Before we did the reduction in service, we did it in front of the public or gently over-fending, we had part-time people
    • 03:26:46
      that they do want to still continue taking trains and if there were options, they would continue to do that.
    • 03:26:52
      We are seeing travel patterns shifting, so this is a picture from 5.30 in the morning, train 86 at Richmond, routinely we are seeing 100 plus people board this train every morning.
    • 03:27:02
      So kudos to our passengers for still sticking with us and just understanding that for progress, a short-term pay is necessary.
    • 03:27:14
      So based on the feedback, we did start thinking about mitigation measures.
    • 03:27:20
      The first thing we did was bus service.
    • 03:27:22
      So when we reduced service on January 12th, we added bus routes from Hampton Roads to DC.
    • 03:27:29
      This is an express service that goes from Virginia Beach to Norfolk, Newport News, and then direct to DC.
    • 03:27:34
      And then on March 7th, we added express service to Richmond.
    • 03:27:38
      So Staplesman and Main Street Station, direct bus to DC and back.
    • 03:27:43
      The chart on the left, dark blue, is the express bus ridership, January to April, so cumulative for that period compared to the train ridership that's in light blue.
    • 03:27:56
      I want to emphasize that buses have been greatly utilized and it just shows that people do want to take that option if, you know, given the option that they are ready to ride the bus, but this is a great cost effective way to supplement the reduction in ridership.
    • 03:28:13
      So, we keep hearing about, you know, we need to expand bus service.
    • 03:28:21
      I'm just thankful that we could do this in a short amount of time implemented for our customers.
    • 03:28:27
      I do want to give a shout out to Avie Daughey, the project manager for Virginia Brieze.
    • 03:28:33
      Avie has been a great resource.
    • 03:28:35
      Whenever I had questions about the bus,
    • 03:28:37
      Contract as a pick up the phone, talk to Avery, and he has helped out tremendously.
    • 03:28:42
      So thank you for the partnership that's working with us.
    • 03:28:47
      The other, the second thing we did, so to orient everyone, and I know Laura touched a little bit on this during the budget update, but our consists to date pre-January 12th, five coach cars, one business car, and one cafe car.
    • 03:29:02
      That was a standard consist, even if the train was longer.
    • 03:29:06
      And that goes with one conductor and one assistant conductor.
    • 03:29:11
      So for staffing, you can staff five coaches, one business and one cafe, of course with an LSE, but with a conductor and an assistant conductor.
    • 03:29:22
      Virginia trains, since they originate on the NEC, we do not get to dictate our concert size, so the trains are longer depending on where the train is originating from.
    • 03:29:33
      But we had deadheads on our trains.
    • 03:29:35
      So to open up the deadhead, we had to add a second assistant conductor.
    • 03:29:39
      So that was the budget piece that Laura talked about, about $4.5 million to add a second assistant conductor that we could open a sixth coach, which happened on April 27.
    • 03:29:50
      And we are working on opening the remaining deadhead coaches on our trains.
    • 03:29:55
      I don't have a date yet, but that's going to happen.
    • 03:29:58
      And again, with the second assistant conductor, we can achieve that.
    • 03:30:02
      So we are trying everything to increase capacity to mitigate the reduction in service, and this is a boon that we can open up capacity in Virginia.
    • Michael McLaughlinChief Operating Officer
    • 03:30:12
      If I can real quick, keep in mind that our ticket pricing, like airlines, so the less seats you have, the more expensive it is.
    • 03:30:19
      So the average ticket I've been seeing was 20, 30 bucks from Richard McDonald's, Andrea.
    • 03:30:23
      It's gone up, it's been double that.
    • 03:30:25
      It's been 50, $60, and I know there's affordability is a big term we all talk about.
    • 03:30:30
      So by opening up the extra cars,
    • 03:30:32
      We're lowering that price.
    • 03:30:33
      It is adding some cost to us, but we think we're doing our part in the overall transportation network by taking some cars off the road.
    • 03:30:40
      My earlier DJ showed only 8% decrease in ridership on their six state supported trains compared to eight last year.
    • 03:30:47
      People are still, it shows that people are still riding because we reduced a lot, only 8% decrease.
    • 03:30:53
      People still want to ride.
    • 03:30:55
      We want to give them more options and keep those ticket prices low, especially in times of high gas prices.
    • SPEAKER_15
    • 03:31:01
      That's a great point, Mike.
    • 03:31:02
      Thank you for that.
    • 03:31:03
      Yeah, we are working really closely with the Amtrak pricing revenue management team to make sure that our prices are fair and stay affordable for everybody.
    • 03:31:12
      So this is something we are, but the additional capacity given is that ability to also keep the fares low.
    • SPEAKER_03
    • 03:31:18
      On the staffing, is the staffing requirement an FRA safety requirement or is it a CPA requirement?
    • SPEAKER_15
    • 03:31:30
      Apart from the service mitigation, we are also working on how to promote the service.
    • 03:31:38
      So, Amtrak Virginia is the official travel partner of VA-250.
    • 03:31:42
      We did a USA Rail pass sale for $250.
    • 03:31:46
      That was a special that ran for some time.
    • 03:31:50
      But what we are doing here specifically is promoting Virginia destinations with the VA-250 pilot.
    • 03:31:57
      And this gives us the ability to prevent the service
    • 03:32:00
      Partner with localities and put great emphasis on how we are moving people and moving, you know, celebrate to stay 250 years.
    • Mariia ZimmermanChair, Board of Directors
    • 03:32:09
      And I have a question.
    • 03:32:12
      So first off, very excited to see that on the the Virginia 250.
    • 03:32:19
      Darien knows I've been like, we got to do all the modes.
    • 03:32:23
      So the governor's office is also working as part of Virginia 250 of kind of how do we package together
    • 03:32:30
      Amtrak, Virginia Breeze, local transit service so that people who are coming to DC or Williamsburg or whatever can like, we want visitors from out of state to come as well as folks who are local, but not to be adding to already very heavily congested 95 interstate.
    • 03:32:51
      So there will be more coming out of kind of how do we cross promote this and how do we support this, but we appreciate VRPT or excuse me, VRPA,
    • 03:32:59
      taking a lead in the work with Amtrak on this.
    • 03:33:02
      DRPT, we do have, it's called Connecting VA and it's an app and we're gonna be doing more things to kind of, again, how do we get all the multi-modes so that folks are hopefully not at already congested freeways and interstates as part of hopefully experiencing this.
    • 03:33:20
      But I do have a question, given earlier slides that talked about the summer is gonna be intense in terms of construction,
    • 03:33:28
      We know there's always issues that come into play and delay things at the same time that we have a lot of people coming here for FIFA for Virginia 250 events in June, July, and August.
    • 03:33:42
      Is there going to be any pause in the construction window during some of these peak times?
    • 03:33:46
      How are we thinking about that?
    • 03:33:48
      How are we communicating that?
    • 03:33:49
      And what's the status of that which is coming, which I think
    • 03:33:54
      In another different scenario, we'd be like, wow, this is great.
    • 03:33:58
      We have all this wonderful stuff happening.
    • 03:34:00
      But this year, it seems like it's all hitting us.
    • SPEAKER_04
    • 03:34:02
      Yeah, so just back to Ashwini's slide, the t-shirt summer that we're not buying t-shirts for, that's 2027, so that really gets hectic in 2027.
    • 03:34:12
      That said, there's a lot we're coordinating this summer, with the FIFA, with the 250 and everything.
    • 03:34:17
      We've worked with the district, they have, we have come to an agreement that there are some weekends for driving those where we're not going to have construction.
    • 03:34:26
      So we're very conscious of when the crowds are going to be there,
    • 03:34:30
      That said, we also had to set some limits.
    • 03:34:32
      We went to the district.
    • 03:34:33
      The district has been a great partner.
    • 03:34:34
      Don't misquote me on that.
    • 03:34:36
      The district has been a great partner.
    • 03:34:37
      The district has been a great partner.
    • 03:34:40
      When we talked to them about when they're going to be high riderships and events, when should we kind of curtail construction, they came back and they said, well, how about these 46 weekends?
    • 03:34:48
      We're like, wait a second, 46 weekends out of 52, we can't do that.
    • 03:34:51
      We've come to an agreement where there's a, there are a handful of weekends where we're going to do that.
    • 03:34:55
      So yes, we're watching that.
    • 03:34:57
      Thank you.
    • 03:34:58
      Please forgive me if this is our thing.
    • 03:35:00
      Will there be extra trains around 2.50, around 4th of July?
    • 03:35:05
      We don't intend to have extra trains.
    • 03:35:07
      We may make the trains longer if possible.
    • 03:35:09
      Equipment is really, really tight.
    • 03:35:12
      So when the route is going to be longer, we would.
    • 03:35:14
      Amtrak's
    • 03:35:16
      Desperately looking for equipment everywhere, so we don't think that's going to be an option for us.
    • 03:35:21
      That said, if you're easy on firework trains and so on and so forth.
    • Dallas Richards
    • 03:35:24
      I mean, actually train on Saturday to the fireworks.
    • 03:35:26
      We're running the firefighter train on both blocks, but that's the line on there.
    • 03:35:31
      Hertzbergsburg Line, tickets go on sale June 1.
    • 03:35:34
      So you don't have the roads in Hertzberg?
    • 03:35:36
      No, we don't go that far yet.
    • SPEAKER_04
    • 03:35:38
      Yeah, that's exactly what we're looking for, though.
    • 03:35:42
      When Long Bridge ends,
    • 03:35:45
      Then we'll have 13 daily state support trains.
    • 03:35:48
      At that same time, all of the aerotrains will be here and will be there.
    • 03:35:53
      Luxury.com would to use some of the existing AFRIN equipment, so we will have surplus equipment.
    • 03:35:57
      Right now, there's just no equipment to be adding.
    • 03:36:00
      We, the passenger rail nation, don't have flexibility to add.
    • 03:36:06
      But that's where we want to get.
    • SPEAKER_03
    • 03:36:08
      Is there going to be interoperability in terms of ticketing?
    • 03:36:12
      across the various agencies, right, to have the equivalent tap right there.
    • Mariia ZimmermanChair, Board of Directors
    • 03:36:19
      Sadly, no.
    • 03:36:20
      Okay.
    • 03:36:20
      Yeah.
    • Mariia ZimmermanChair, Board of Directors
    • 03:36:21
      Sadly.
    • Michael McLaughlinChief Operating Officer
    • 03:36:22
      Well, there is the Amtrak step-up programs.
    • 03:36:24
      You can go on my VRE app and I've done many, many times, but it's just because the price is very high and I can purchase a seat for just $4.
    • Mariia ZimmermanChair, Board of Directors
    • 03:36:37
      I do maintain my big hope and maybe it will happen in 2030.
    • 03:36:47
      LaMotta now has tap and go.
    • 03:36:49
      But like if you go to London, if you go to Paris, if you go to these places, you can get like the Paris pass, the London pass.
    • 03:36:56
      and like it literally is like giving you access to regional rail, to the local transit, to the museums, coupons for a restaurant, you know, all this stuff.
    • 03:37:05
      And it's like, if we can move towards having a Virginia pass or a DC pass or whatever it might be, but I hope that we will continue to move closer as our technologies on transit with BRE with Amtrak, you know, but so, so yeah, you can't book the whole ticket, but through the Connecting Virginia
    • 03:37:25
      We are trying to make it easier.
    • 03:37:27
      At least there's one place where you can get comparable scheduling information and all that.
    • SPEAKER_04
    • 03:37:34
      We're focused on the bypass.
    • Patricia DoerschMember, Board of Directors
    • 03:37:39
      But to DJ's point right now, like I said, good luck coordinating Virginia, DC, Maryland.
    • 03:37:43
      I totally agree.
    • 03:37:44
      Whatever happened to Mark coming across the river?
    • SPEAKER_04
    • 03:37:46
      Talk about it all the time.
    • 03:37:47
      That's a big issue.
    • 03:37:49
      And we are in the process of working with them.
    • 03:37:52
      We know there's a lot of ticketing that has to take place.
    • 03:37:55
      Yeah, cost allocation, that through traffic will be such an advantage to travelers because you can get on a train in Rockville and not have to change three times to get to Alexandria.
    • 03:38:08
      That's not going to happen until Long Bridge is done, but we know that those conversations have to start now and we've begun those conversations.
    • 03:38:14
      There's a whole group of folks in Amtrak, the District, MARC, Maryland DOT, us, VRE, that are beginning that conversation.
    • Patricia DoerschMember, Board of Directors
    • 03:38:23
      And VRE is okay with it, doesn't view Mark as a threat?
    • Dallas Richards
    • 03:38:27
      Not for ridership, probably competitors.
    • 03:38:29
      It's us going that way and them coming this way.
    • 03:38:30
      In fact, there's people that ride both today though.
    • 03:38:34
      The biggest concern to us is, it is the bottom.
    • 03:38:39
      It is the place where you just can't get through.
    • 03:38:42
      Virginia and the first three tunnels, rather, will be the long bridge of 2035.
    • 03:38:48
      But we're already looking at ways to improve
    • 03:38:52
      Throughput.
    • 03:38:55
      But until that's done, you know, they can't put that many more trains.
    • SPEAKER_04
    • 03:39:01
      First returns the bottleneck once Long Bridge is done.
    • 03:39:03
      Right now Long Bridge is done.
    • 03:39:04
      That's right.
    • Dallas Richards
    • 03:39:05
      After Long Bridge, it becomes a new thing.
    • 03:39:09
      But people are making investments and looking at that for it.
    • SPEAKER_03
    • 03:39:14
      Can we go back to the bit about staffing in the CPAs, right?
    • 03:39:20
      Do we have any flexibility there, right?
    • 03:39:21
      I mean, like, are we
    • 03:39:22
      We, the authority, are not a party to the CPA, but Amtrak is, right?
    • 03:39:27
      Do we have flexibility in terms of the relationship between Austin and Amtrak?
    • Dallas Richards
    • 03:39:33
      We do the same thing with our consist.
    • 03:39:36
      When we go from six to eight cars in the consist, we have to go from two to three conductors to CPA.
    • Patricia DoerschMember, Board of Directors
    • 03:39:46
      Rail labor.
    • Dallas Richards
    • 03:39:48
      It's not unreasonable either because you're asking that person to basically manage that number of cars, stick it in, but it's also from a safety standpoint, safety and security, right?
    • 03:40:01
      That's why they're doing it.
    • 03:40:03
      You have a certain number of people that, maybe by virtue of number of cars, that they can manage in situations.
    • Patricia DoerschMember, Board of Directors
    • 03:40:09
      And how many doors can open for people to get off and on, right?
    • SPEAKER_15
    • 03:40:14
      The new number of doors open has definitely helped with our station's value.
    • 03:40:18
      So we are seeing benefits to having the third connect onboard as well.
    • 03:40:24
      Just last slide.
    • 03:40:26
      And before I get to this, I do want to say a shout out to Rayleigh Glenn for identifying the VA 250 partnership and working on it and making sure that Amtrak VIA is an official travel partner in chief.
    • 03:40:36
      I know Mariia, she's working with other agencies to bring them on under the VA 250 balance.
    • 03:40:42
      So
    • 03:40:44
      Last but not the least, under the USA 250, there are other events around Virginia and Sail 250, you know, there'll be sail ships coming to Norfolk from all over the world.
    • 03:40:57
      So we are using these kinds of partnerships with localities and specific events to promote Amtrak Virginia outside of the popular 4th of July travel weekend.
    • 03:41:07
      So we are finding opportunities and putting the word out wherever possible.
    • 03:41:13
      Any questions?
    • Mariia ZimmermanChair, Board of Directors
    • 03:41:19
      Thank you.
    • 03:41:21
      That was very informative.
    • 03:41:23
      Thank you.
    • 03:41:24
      Alrighty, that was the last item on our agenda.
    • 03:41:28
      Unless there's any official new business or member comments otherwise, we will move to adjourn.
    • 03:41:38
      I just want to thank everyone again for your flexibility today.
    • 03:41:42
      and look at us, we're getting done a little bit ahead of schedule for our on-time performance here.
    • 03:41:47
      So thank you everyone, we will come back in August and I also know you will be getting some emails from me over the summer as we are going to be doing some performance review tips for our own executive director, so stay on the lookout for that and I do want to thank him and all of the staff here for continuing to do really excellent, excellent work, so thank you everyone.
    • 03:42:11
      Thanks for running and safe travels back.