Central Virginia
  • Commonwealth Transportation Board
  • Action Meeting 7/17/2008
  • Auto-scroll

Action Meeting   7/17/2008

Attachments
  • Action_Agenda_July_2008.pdf
  • Meeting minutes.pdf
  • Naming of the _Deputy Jason Saunders Memorial Bridge_.pdf
  • Authorization to execute agreements with Washington, D.C., Water and Sewer Authority regarding crossings of the Potomac Interceptor.pdf
  • Location approval, I-264 ramps, London Bridge Road, Virginia Beach.pdf
  • Land conveyance, Route 120, Arlington County.pdf
  • Fiscal Years 2009-14 Six-Year Improvement Program transfers, June 1-July 8, 2008.pdf
  • Corridors of the Future Memorandum of Understanding between North Carolina, South Carolina, Georgia, Florida and Virginia (signatory states),.pdf
  • Commending Greater Richmond Transit Co..pdf
  • 460 Connector – Phase 1 Project.pdf
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:00:00
      Let's call the board for the July business session of the Commonwealth Transportation Board.
    • 00:00:05
      Is there anybody who wishes to address the Commonwealth Transportation Board?
    • 00:00:11
      Hearing none, is there a motion to approve the minutes?
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:00:15
      It will be approved.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:00:16
      Second All in favor?
    • 00:00:18
      Aye Action item 1 to a commemorative naming of U.S. Route 29 bridge near Alta Vista and the Tiffany Jason Saunders Memorial Bridge I move it, Mr. Chairman Second All in favor?
    • 00:00:36
      Aye Action item 2 is to execute easement agreements with the Washington, D.C. Water and Sewer Authority
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:00:45
      I so move, Mr. Chairman.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:00:48
      Second.
    • 00:00:49
      All in favor?
    • 00:00:50
      Aye.
    • 00:00:50
      Action item 3 is the location approval of I-264 Ranch to London Bridge Road in the City of Virginia Beach.
    • 00:01:00
      For who?
    • SPEAKER_00
    • 00:01:01
      Second.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:01:02
      All in favor?
    • 00:01:03
      Aye.
    • 00:01:05
      Action item 4 is action on the land and or easement conveyance on Route 120 in Arlington,
    • 00:01:14
      County, any questions?
    • 00:01:22
      All in favor?
    • 00:01:25
      Under programming division, this is your monthly transfer.
    • 00:01:30
      Ms. Busher is here.
    • 00:01:30
      Are there any questions before we entertain a motion?
    • 00:01:34
      Is there a motion?
    • SPEAKER_00
    • 00:01:37
      Second.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:01:37
      All in favor?
    • 00:01:40
      Aye.
    • 00:01:40
      Action item six, again to pick up the item that was just discussed, the Quarters of the Future and the authorization for signature authority pending future negotiation.
    • 00:01:52
      Are there any additional questions of Dr. Tisher?
    • 00:01:54
      Move the approval.
    • 00:01:57
      Okay.
    • 00:01:58
      All in favor?
    • 00:01:58
      Aye.
    • 00:02:00
      Action item seven is the resolution commending GRTC.
    • 00:02:04
      Mr. Tucker, did you want to explain that a little bit more?
    • SPEAKER_00
    • 00:02:10
      This was the resolution of the item that we discussed previously with GRTC to recognize them for their outstanding performance and to be designated as the best transit system for the job.
    • 00:02:23
      So, this resolution is for many GRTC for receiving that award.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:02:31
      We plan that DRPT will personally deliver that award to GRTC to revise for their support.
    • SPEAKER_00
    • 00:02:39
      I move it's approval.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:02:40
      All in favor?
    • 00:02:42
      And just on a personal note, you know, to me, one of the very interesting things is when we talked about public transportation historically, we talked Northern Virginia a little bit about Fredericksburg.
    • 00:02:56
      This year, think about this, Richmond has been designated the best mid-sized transit system in the country.
    • 00:03:02
      We broke ground on the Norfolk Light Rail Project.
    • 00:03:05
      The world is changing and those are the important steps forward and it's very important when we get out and talk to the positive and to note the good news that is out there despite the long economic situation.
    • 00:03:19
      H. T. Taylor III, John T. Taylor III, John T. Taylor III,
    • 00:03:39
      A fair bit of work, and I know there is one item on the RAP 460 project in the Bristol District that we're going to move to the very end for some brief discussion.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:03:50
      Yes, sir.
    • 00:03:52
      The first item, page one, the order number 819, City of Alexandria, this is a bridge deck replacement project, significant amount of interest in that project.
    • 00:04:04
      This is route 236 over 395.
    • 00:04:10
      We've received good bids.
    • 00:04:12
      One of the things that we are seeing is steel escalation, asphalt and fuel prices making their way into bids.
    • 00:04:23
      We do not believe we'll get a better bid on this project and we recommend it's approved.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:04:29
      I'll move it to approve, Mr. Shirley.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:04:30
      Second?
    • 00:04:31
      All in favor?
    • 00:04:33
      Page 2.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:04:34
      Page 2.
    • 00:04:35
      First project, A86, is regional traffic signal and modification of signal projects
    • 00:04:44
      This is a contract which we establish bid prices, unit prices, and then we enact a new location as needed over time.
    • 00:04:58
      Again, we received three bids on this project, good bids, and we do recommend its approval.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:05:06
      Is there a motion?
    • 00:05:07
      I move to approve, Mr. Chairman.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:05:09
      Second.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:05:11
      All in favor?
    • 00:05:12
      Aye.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:05:12
      The next project, A-87, is a very similar project, but in the Spotsylvania, King George, and Stafford County regional area.
    • 00:05:21
      Four bids were received on this project.
    • 00:05:25
      We believe these are good bids.
    • 00:05:26
      We might get better prices, and we recommend their approval.
    • 00:05:31
      So moved, Mr. Chairman.
    • SPEAKER_00
    • 00:05:31
      Second.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:05:32
      All in favor?
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:05:34
      Aye.
    • 00:05:36
      Next project, A-93,
    • 00:05:38
      is a paving milling guardrail upgrade in Fairfax County.
    • 00:05:44
      This is a maintenance funding project.
    • 00:05:47
      Again, three bids were received on this project, very competitive pricing on these three bids, and we recommend its approval.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:05:57
      Move its approval, Mr. Chairman.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:05:59
      Second.
    • 00:06:00
      All in favor?
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:06:05
      Aye.
    • 00:06:06
      Page 3.
    • 00:06:07
      is an additional asphalt patching contract, a bit different than our normal paving contracts, maintenance funded, significant interest by bidders, and these prices are very good.
    • 00:06:24
      Again, we do not believe we will receive better prices in this market.
    • 00:06:36
      Page 4.
    • 00:06:37
      The next project is by the town of Blacksburg.
    • 00:06:43
      Brandon Steele will hear from the town if we have some additional need for discussion.
    • 00:06:50
      This project is for the improvements, safety and pedestrian enhancements, and improving traffic flow along Crisis Fork Road and various intersections.
    • 00:07:01
      See for bids on this project.
    • 00:07:04
      We've analyzed them.
    • 00:07:06
      We believe they're very good bids and recommend some proof.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:07:10
      Second.
    • 00:07:12
      All in favor?
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:07:12
      Aye.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:07:13
      Page 5.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:07:16
      I would like to leave this project to the end.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:07:20
      We'll move this page 5 if you pull it out of the black and we'll take this up to the very end.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:07:28
      Page 6, this is a City of Fairfax Public Works project representative of the city is here should we have some additional questions.
    • 00:07:42
      Various improvements, this is a revenue sharing project.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:07:49
      You'll notice that there's significant interest, 11 bids on this project.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:07:57
      and we've analyzed those prices, recommend their approval.
    • 00:08:02
      I recommend its approval.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:08:03
      Second.
    • 00:08:05
      I would like to acknowledge the presence of Mr. Garosa here from the city.
    • 00:08:09
      Welcome.
    • 00:08:10
      Good to see you again, Alex.
    • 00:08:12
      There's a motion and a second.
    • 00:08:13
      Is there, everybody, all in favor, please say aye.
    • 00:08:17
      Aye.
    • 00:08:18
      Page 7.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:08:20
      Page 7 is a Project 875.
    • 00:08:24
      This is in Albemarle County.
    • 00:08:25
      This is a federal maintenance paving project on I-64.
    • 00:08:31
      You'll note that this project is from April.
    • 00:08:35
      There were some issues concerning some DBE goals and issues, subcontractor issues that we needed to work through.
    • 00:08:44
      A little bit over our estimate, however, we believe that the good prices, and we have through minimum agreement, locked those in and recommend it's approval.
    • SPEAKER_00
    • 00:08:54
      Move approval.
    • 00:08:56
      Second.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:08:56
      All in favor?
    • 00:09:00
      Page 8.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:09:02
      Page 8, A-81, Sendidwini County, maintenance-funded
    • 00:09:08
      Asphalt Concrete Overlay Project for patching and guardrail repair on Interstate 85.
    • 00:09:15
      We did receive two bids on this project, and they were very close.
    • 00:09:21
      We believe it's of good value and representative.
    • 00:09:24
      Recommend is approved.
    • SPEAKER_00
    • 00:09:25
      Move approval.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:09:27
      Second.
    • 00:09:28
      All in favor?
    • SPEAKER_00
    • 00:09:30
      Page 9.
    • 00:09:30
      Chairman, I would like to be marked as abstaining on that last one, the branch and companies on my board.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:09:40
      Page 9.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:09:45
      Next project V07 is in the cities of Chesapeake and Norfolk at various locations.
    • 00:09:54
      Asphalt overlay and some traffic safety items.
    • 00:09:59
      There was only one bidder on this project.
    • 00:10:02
      We've discussed this project in detail with the contractor, analyzed his bids.
    • 00:10:08
      I do not believe we'll get any better prices on this project with re-advertisement and recommend its approval.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:10:21
      All in favor?
    • 00:10:24
      Aye.
    • 00:10:26
      Let's turn to the pink sheets, beginning with page 10.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:10:31
      Page 10, this is the first renewal of a TAMS contract.
    • 00:10:36
      This is the first of the current generation of TAMS contracts that we've seen.
    • 00:10:44
      This, Robby Prezioso is here if we wish to delve into it in depth.
    • 00:10:53
      Indications are with the evaluation on this first term, we've seen improvements, we've seen the contractor perform as indicated and as planned and we're recommending that this contract be renewed.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:11:15
      Any questions?
    • SPEAKER_00
    • 00:11:16
      Could you just refresh my memory anyway?
    • 00:11:19
      When was this?
    • 00:11:20
      Is this the firm that has the contract now, I gather?
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:11:26
      This is the same firm, yes sir, that has that section.
    • 00:11:30
      This is east of Richmond and into Hampton Roads.
    • 00:11:41
      Yes, from about close 200 to 268, roughly a 68-mile section from Richmond going east.
    • SPEAKER_00
    • 00:11:52
      And they have met all your expectations?
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:11:55
      Yes, sir, they have and the payment conditions, etc., the evaluations of the area supervisors and the several residencies are that they have met or exceeded our expectations and all recommended renewal.
    • SPEAKER_00
    • 00:12:15
      And this is for three years plus another three years?
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:12:20
      This is for one three-year renewal and I believe at that point
    • 00:12:39
      Welcome, Mr. Prezioso.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:12:43
      The initial contract term was for three years and expires next month.
    • 00:12:47
      And this is for renewal for an additional three years.
    • 00:12:50
      And the original invitation for bid laid it out for there to be two three-year renewals if we continue to want to work with this company on this corridor.
    • SPEAKER_00
    • 00:13:01
      And you have to come back each time at that point?
    • 00:13:03
      Yes, sir.
    • 00:13:03
      Okay.
    • 00:13:04
      I'd move approval then.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:13:06
      There's a motion.
    • 00:13:07
      Is there a second?
    • 00:13:08
      Second.
    • 00:13:10
      Would it be fair to say, Mr. Coburn, this is the oldest of the TAMS contracts?
    • 00:13:14
      Is this the very first one?
    • 00:13:16
      As I recall, when these were set up, we established some baselines in terms of cost of doing this work in-house, and there were some performance measures that we could look at, and now we've got three years of experience.
    • 00:13:31
      Is that appropriate at a time for us to begin?
    • 00:13:34
      Embarking on that process, not to hold up the contracting processes.
    • 00:13:40
      And I would, Commissioner, if I could make that request prior to the vote with a clear understanding of the board that while there was a legislative mandate to outsource interstate maintenance, I guess we're about 85, 90% complete in that process, we did set up some very clear benchmarks.
    • 00:14:00
      The CTB adopted some clear benchmarks so we knew
    • 00:14:04
      What would be the estimated cost if it was done using in-house resources and so that we could have a real-world comparison on a contract-by-contract basis?
    • 00:14:13
      So at the appropriate time in September, October, November, if we could start to see, you know, some of those evaluations, I think would be extremely helpful.
    • 00:14:26
      And I think the board is looking for absolutely neutral objective information.
    • 00:14:33
      In any contract like this, there are probably going to be strengths but there are probably also going to be weaknesses and it would be helpful if we had that very balanced view of this, the oldest of our outsourcing attempts through the TAMS contract.
    • 00:14:48
      Okay, there's a motion and a second.
    • 00:14:49
      All in favor?
    • 00:14:53
      Page 11.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:14:57
      This project is from bids received May 21.
    • 00:15:01
      The City of Waynesboro, and this is the replacement of a railroad bridge CSX now operated by Buckingham Branch over Route 340 Delphine Avenue.
    • 00:15:13
      Five bids were received on this project.
    • 00:15:17
      The project has
    • 00:15:18
      been reduced in scope from what was originally in the Six-Year Plan.
    • 00:15:25
      And so you see that there's some money changes there.
    • 00:15:29
      We've been, part of the delay has been identifying all the funding, appropriate categories, etc.
    • 00:15:36
      We've done that, we've completed that, have a memorandum of agreement proposed, and with those things in place, recommend this approval.
    • SPEAKER_00
    • 00:15:46
      I move approval.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:15:48
      Page 12 is a project undertaken by Allegheny County.
    • 00:16:01
      John Lowman is here from Allegheny County this morning should we need further discussion but this is the reconstruction of a bridge over the Jackson River which will allow access into
    • 00:16:24
      Public utility plant that needs reconstruction and the county is undertaking this project.
    • 00:16:31
      We've analyzed the bids and they are good bids.
    • 00:16:37
      We expect everything to go well with this project.
    • 00:16:41
      We've seen all those plans.
    • 00:16:43
      We recommend it's award.
    • SPEAKER_00
    • 00:16:45
      I move approval.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:16:48
      Mr. Sterling?
    • 00:16:49
      Yeah, just real quick.
    • 00:16:50
      The sufficiency rating on this particular bridge, you know, it's an old bridge.
    • 00:16:54
      The way this is drafted is to make space available for the wastewater treatment plant, but do you know what condition of the bridge is, otherwise?
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:17:03
      I do not.
    • 00:17:05
      I failed to say that.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:17:07
      Yeah, it's an old truss bridge.
    • 00:17:09
      Yeah, I see that.
    • 00:17:10
      It must be.
    • 00:17:12
      Great.
    • 00:17:15
      Do we know if it's knocked off one of those in the replacement project list or otherwise?
    • 00:17:21
      It's a double whammy.
    • SPEAKER_00
    • 00:17:22
      Yes, ma'am, let me see.
    • 00:17:28
      Now, I know that it's old trust done, being replaced by the two lanes, temporary in the meantime.
    • Warner B. "Byron" CoburnScheduling and Contract Division Administrator
    • 00:17:39
      I do not have that piece of information available, but I will provide it to you.
    • SPEAKER_00
    • 00:17:44
      Let's email back to you.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:18:03
      There's a motion and a second.
    • 00:18:04
      All in favor?
    • SPEAKER_00
    • 00:18:06
      Aye.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:18:08
      Let's turn to the Route 460 project which is on page 5.
    • Malcolm T. KerleyChief Engineer
    • 00:18:20
      Carol is going to pass out to you some more information.
    • 00:18:27
      A little bit about the project.
    • 00:18:28
      This is a design-build project on 460.
    • 00:18:33
      It's phase 1 of the connector coming out of Kentucky.
    • 00:18:37
      It's going to go through the brakes at International Park.
    • 00:18:40
      This was the design-build project that was put out and advertised as a best value project.
    • 00:18:46
      We put out a request for qualification and received six people putting their qualifications in.
    • 00:18:53
      We shortlisted those six people to three and asked those three people to present their technical and cost proposals for the project.
    • 00:19:04
      We evaluated the project based on a technical and cost with the technical aspect of the project.
    • 00:19:11
      In other words, who are you going to have working on the project, what do you plan to do, how do you plan to design, and what do you plan to give us is 30%.
    • 00:19:19
      And then we weighted the cost of the project at 70%.
    • 00:19:27
      So we've had three people that we shortlisted put in.
    • 00:19:32
      I am making a recommendation to you to award it to Bizak today.
    • 00:19:38
      We did receive a protest from the second ranked firm, and I would like to point out to you the second ranked firm was the lowest cost firm by about $4.5 million.
    • 00:19:51
      We received a protest from them.
    • 00:19:52
      We looked at the protest.
    • 00:19:54
      I talked with staff.
    • 00:19:55
      I reviewed what staff did.
    • 00:19:56
      I talked with our attorneys, and we rejected their protest.
    • 00:20:03
      I directed staff, since we only did this, I believe, on Tuesday, I directed staff to call the firm to let them know that I would be rejecting their protest.
    • 00:20:14
      We received a letter.
    • 00:20:15
      You have a copy of a letter that was sent, I believe, yesterday to the chairman.
    • 00:20:20
      with copies to each member of the board indicating that they plan to seek judicial review of our decision.
    • 00:20:30
      I also provided you what we also received last night from the attorneys of the ZACH indicating their support for our decision.
    • 00:20:41
      I am recommending to you that although there is a
    • 00:20:50
      A protest that we could go to court with, that we award the contract and move forward, and I have a Jeff Allen of the Attorney General's Office here that could brief you if you'd like to exactly on what this particular section of the code allows the board to do.
    • SPEAKER_00
    • 00:21:07
      Mr. Chairman, we need a motion now.
    • 00:21:09
      I would move it's approval.
    • 00:21:11
      Second.
    • 00:21:13
      Motion was, what was the motion?
    • 00:21:16
      Approve.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:21:18
      Everybody understands.
    • 00:21:20
      There is protest, and there may be legal action down the road, but if we wait 60 days, the inflationary cost, it's a real devil's dilemma.
    • 00:21:32
      The protests have been reviewed by the chief engineer and by the office of the attorney general, and we believe we have a very strong case and will prevail if there is to be subsequent litigation.
    • 00:21:43
      But the process is there's a claim.
    • 00:21:45
      The claim has been denied.
    • 00:21:48
      And so we move forward on this large contract.
    • SPEAKER_00
    • 00:21:51
      One quick one, Mr. Secretary.
    • 00:21:53
      I assume this is a project that location and everything has long since been approved by somebody.
    • 00:21:58
      Because I thought I heard you say it was going through a state park.
    • Malcolm T. KerleyChief Engineer
    • 00:22:02
      No, it will tie to a state park.
    • 00:22:04
      Breakers State Park tied to it.
    • 00:22:07
      And access to it.
    • SPEAKER_00
    • 00:22:08
      Mr. Chairman, if I may, this is also connecting on to, there's a timeline on servicing the traffic coming out of Kentucky
    • 00:22:17
      on Route 460 because they're scheduled for completion and they're going to be dumping 460 traffic in on that section of the 460.
    • Malcolm T. KerleyChief Engineer
    • 00:22:25
      The previous board, sir, has approved an agreement, allowed the commissioner to enter an agreement between Kentucky and Virginia and part of it is time in this particular phase of this project.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:22:38
      Okay.
    • 00:22:38
      Is motion a second?
    • 00:22:39
      Any other questions?
    • 00:22:40
      All in favor?
    • 00:22:41
      Aye.
    • 00:22:42
      Any opposed?
    • 00:22:44
      No.
    • 00:22:45
      Okay, the next item on the agenda is new business.
    • 00:22:50
      Is there any new business that comes before the board?
    • 00:22:55
      Unfortunately, I would observe under new business that we're dealing with a lot of old business.
    • 00:23:01
      And I think we've heard in several presentations today a couple of things.
    • 00:23:07
      One is we don't know where we are with federal revenues.
    • 00:23:11
      We will, as soon as we get information on that, this being a week year or an Olympic year, it may be a little slower than coming out than is normally the case.
    • 00:23:25
      We will have revenue indications by August.
    • 00:23:30
      And there's a lot of work to be done with the Rail Enhancement Fund, the Statewide Rail Plan, and some tough choices in that context.
    • 00:23:42
      So, what I would like to say is, everyone, I hope you get a chance for a little bit of family time over the next couple of months.
    • 00:23:52
      I hope those of you who have an opportunity to communicate directly to the Governor, whether you're riding or if you see them in a minute,
    • 00:23:59
      Governor Caine for his absolutely rock-solid support for transportation funding.
    • 00:24:08
      And while the legislative effort was not successful, I think a couple things came out of that, which is simply maintaining our existing network is an inescapable cost.
    • 00:24:21
      And then secondly, something we didn't spend a lot of time on was the Governor's proposal for the Transportation Change Fund.
    • 00:24:29
      And I would ask if Nick Donahue is still here, that we get at least that piece of the legislation sent out to the CTB, because what that does is it ties together
    • 00:24:42
      B. Doolittle III, John C. Doolittle III
    • 00:25:02
      So please be thinking along those lines.
    • 00:25:06
      We need every ounce of creativity and hard work simply to survive and to make these difficult choices over the coming months.
    • 00:25:13
      Mr. Koelemay.
    • J. Douglas KoelemayMember, Commonwealth Transportation Board
    • 00:25:14
      Mr. Chairman, I wanted to make one other observation.
    • 00:25:17
      Years ago when the signage went up along 81, you were now entering the Chesapeake Bay watershed and so forth, began to make people aware of those things.
    • 00:25:29
      On the way down from Northern Virginia today, the digital signage on 95,
    • 00:25:35
      noted that there was an ozone advisory for the Greater Richmond area and advised telework, carpooling, take transit.
    • 00:25:44
      I think that's an important part of what we're doing here is letting the public know that these problems are interrelated and the solutions probably are too.
    • 00:25:54
      So I was encouraged, although I felt guilty.
    • 00:25:59
      I wish I'd had the rail link at that point.
    • 00:26:03
      It's something that we're going to have to do and increasingly, as you've heard me say before, our Department of Transportation and Rail and Public Transportation are in the information and service business.
    • 00:26:15
      And that's an important part of helping people make the changes that are necessary, is helping them stay informed about alternatives, problems, things that are going on.
    • 00:26:23
      So I like the signage.
    • 00:26:26
      I like the attention.
    • Pierce R. HomerChair, Commonwealth Transportation Board
    • 00:26:28
      Thank you.
    • 00:26:29
      Any other comment?
    • 00:26:30
      If not, I hope everyone enjoys the August recess and please drive safely.
    • 00:26:36
      Thank you, the meeting is adjourned.