Central Virginia
  • Albemarle County
  • Architectural Review Board Meeting 8/18/2025
  • Auto-scroll

Architectural Review Board Meeting   8/18/2025

Attachments
  • Agenda.pdf
  • Final Action Memo.pdf
  • Final Action Memo Minutes.pdf
  • SDP2025-83 Cville Community Church Initial Staff Report.pdf
  • Attach. 1 SDP2025-83 Charlottesville Community Church Initial Site Plan.pdf
  • ARB2025-17 Northside Industrial Final Staff Report.pdf
  • Attach. 1 ARB2025-17 Northside Industrial Site Plan.pdf
  • Attach. 2 ARB2025-17 Northside Industrial Architectural Drawings.pdf
  • Attach. 3 ARB2025-05 Northside Industrial Initial Site Plan ARB Staff Report.pdf
  • ARB-2023-107 Barnes Lumber Mural Criteria Memo.pdf
  • Attach. 1 ARB-2023-107 Barnes Lumber proposal reviewed March 3 2025.pdf
  • Draft ARB Action Memo Minutes 08_04_2025.pdf
    • SPEAKER_04
    • 00:27:58
      We are now live.
    • Chris HenningsenChair, Architectural Review Board
    • 00:28:01
      All right.
    • 00:28:01
      It's just about 1 o'clock.
    • 00:28:06
      So I'm calling the August 18, 2025 meeting of the Albemarle County Architectural Review Board to order.
    • 00:28:14
      Could you call the roll, please?
    • SPEAKER_04
    • 00:28:16
      Yes.
    • 00:28:17
      Mr. Van Der Werf?
    • Chris HenningsenChair, Architectural Review Board
    • 00:28:19
      Here.
    • SPEAKER_04
    • 00:28:20
      Mr. Matsuno?
    • Chris HenningsenChair, Architectural Review Board
    • 00:28:21
      Here.
    • SPEAKER_04
    • 00:28:21
      Mr. Stoner?
    • Chris HenningsenChair, Architectural Review Board
    • 00:28:22
      Here.
    • SPEAKER_04
    • 00:28:23
      Mr. Hancock?
    • Chris HenningsenChair, Architectural Review Board
    • 00:28:24
      Here.
    • SPEAKER_04
    • 00:28:24
      Mr. Henningsen?
    • Chris HenningsenChair, Architectural Review Board
    • 00:28:26
      Here.
    • SPEAKER_04
    • 00:28:26
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 00:28:27
      Thanks.
    • 00:28:28
      Today's meeting is a hybrid meeting.
    • 00:28:30
      The public may access and participate in the meeting electronically.
    • 00:28:34
      Instructions for doing so are posted on the Albemarle County website at the Albemarle County calendar.
    • 00:28:40
      The public has real-time audio-visual access to this meeting over Zoom and real-time audio access over telephone.
    • 00:28:47
      Both is provided in the lawfully posted meeting notice.
    • 00:28:50
      This meeting is being recorded and will be made available on the county's website.
    • 00:28:55
      This meeting is a public record and subject to disclosure under the Freedom of Information Act.
    • 00:29:01
      All speakers, when it is your turn to speak, please first state your name for the record.
    • 00:29:06
      Applicants who are making presentations note that your presentation is limited to a total of 15 minutes, which you can divide among your team members.
    • 00:29:14
      Staff will let us know when the 15 minutes are up.
    • 00:29:18
      If applicants in the meeting room have team members attending virtually who will need to present, please make that known when you come to the podium.
    • 00:29:26
      Everyone who is participating virtually please mute your microphone until it is your turn to speak.
    • 00:29:33
      Do any ARB members have anything to disclose?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:29:36
      No.
    • Taro MatsunoMember, Architectural Review Board
    • 00:29:38
      Yes, I won't be participating in the work session, item seven, due to my firm's involvement in the project.
    • 00:29:47
      All right, thank you.
    • Frank StonerMember, Architectural Review Board
    • 00:29:49
      I have a similar conflict with item seven.
    • 00:29:53
      Okay, thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 00:29:54
      Oh, no.
    • 00:29:55
      Me either.
    • 00:29:57
      Are there any members of the public that want to make a comment about a project that is not on the agenda for review?
    • SPEAKER_04
    • 00:30:05
      I don't have anyone online.
    • Chris HenningsenChair, Architectural Review Board
    • 00:30:09
      All right, great.
    • 00:30:13
      We have one consent agenda item today, which is STP 2025-00083 Seville Community Church initial site plan.
    • 00:30:27
      Do any ARB members want to move this off of the consent agenda?
    • 00:30:34
      No, no, no, no.
    • 00:30:38
      and me neither.
    • 00:30:39
      So I guess I move to approve the consent agenda.
    • 00:30:44
      If I could get a second.
    • 00:30:45
      I'll second that.
    • 00:30:47
      All right.
    • 00:30:47
      We could put that to a vote.
    • SPEAKER_04
    • 00:30:50
      Mr. Henningsen.
    • Chris HenningsenChair, Architectural Review Board
    • 00:30:52
      Aye.
    • SPEAKER_04
    • 00:30:52
      Mr. Hancock.
    • Chris HenningsenChair, Architectural Review Board
    • 00:30:53
      Aye.
    • SPEAKER_04
    • 00:30:53
      Mr. Stoner.
    • Chris HenningsenChair, Architectural Review Board
    • 00:30:55
      Aye.
    • SPEAKER_04
    • 00:30:55
      Mr. Matsuno.
    • 00:30:56
      Aye.
    • 00:30:57
      Mr. Van Der Werf.
    • Chris HenningsenChair, Architectural Review Board
    • 00:30:58
      Aye.
    • SPEAKER_04
    • 00:30:58
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 00:30:59
      All right, thank you.
    • 00:31:01
      We have one regular review item today, which is ARB 2025-17 Northside Industrial.
    • Khris TaggartSenior Planner
    • 00:31:10
      Chris?
    • 00:31:10
      Yes.
    • 00:31:12
      Good afternoon, everybody.
    • 00:31:13
      The plan you're viewing today is for a final site plan, third review of architecture, to construct a 72,000 square foot warehouse with associated site improvements.
    • 00:31:25
      The site is located on the west side of Route 29 at the intersection with Northside Drive.
    • 00:31:30
      In December of last year and May of this year, the ARB provided comments on the architecture and site plans.
    • 00:31:39
      The design of the proposed warehouse remains largely the same as the one reviewed on May 5th, except for the addition of two clear-story windows on the north elevation, a change in paint color to warmer shades of gray, and from the floor pan, minimal wall projections.
    • 00:31:55
      In the previous review, staff made several recommendations that addressed scale, but they were eliminated from the items to be addressed with the final site plan submittal.
    • 00:32:04
      As currently proposed, the wall projections, color changes, scoring of the panels, and small windows partially address the building scale, mass, and plainness.
    • 00:32:13
      Revising the building design provided more variation in the projections would better reduce the building scale until the proposed landscaping matures and softens its appearance from the EC.
    • 00:32:26
      The landscape plan has been revised by a more irregular planting layout north and south of the parking row along the frontage.
    • 00:32:33
      Integrate evergreen trees for better screening of the building and adjust tree species to eliminate conflicts.
    • 00:32:39
      No large trees will be planted along Northside Drive due to utilities and easements, but the shrubs in the plant area and the frontage landscaping at the northeast corner will help blend the facility into the surroundings.
    • 00:32:54
      There are only a few minor revisions remaining because that staff recommends approval of the final site plan with the revisions listed in the staff report.
    • 00:33:02
      I'd be happy to answer any questions.
    • Chris HenningsenChair, Architectural Review Board
    • 00:33:05
      All right.
    • 00:33:05
      Thanks a lot, Chris.
    • 00:33:08
      Yes, we will start with Dade if you have any questions.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:33:11
      Sure, yeah.
    • 00:33:12
      Thank you, Chris.
    • 00:33:13
      I was trying to recall if the applicant intends to have any difference in texture of the precast panels, or are they all proposed to be the same?
    • 00:33:23
      And that might be a better question for the applicant.
    • 00:33:24
      I think that would be my recollection.
    • 00:33:27
      No further questions for me.
    • Taro MatsunoMember, Architectural Review Board
    • 00:33:31
      Tara?
    • 00:33:32
      Yes, I was trying to remember, Chris, with the renderings of the exterior, are those new for this submission?
    • Khris TaggartSenior Planner
    • 00:33:40
      Yes, that was one of the ARB comments about renderings.
    • 00:33:44
      You're talking about the perspectives that had the building design in it.
    • 00:33:48
      I just want to confirm that.
    • 00:33:49
      Yeah, thank you.
    • Frank HancockVice Chair, Architectural Review Board
    • 00:33:51
      Frank Stoner.
    • Frank StonerMember, Architectural Review Board
    • 00:33:52
      I don't have any questions.
    • Frank HancockVice Chair, Architectural Review Board
    • 00:33:54
      Thanks, Frank.
    • 00:33:55
      Could you go back to the previous slide real quick?
    • Chris HenningsenChair, Architectural Review Board
    • 00:34:06
      Thanks.
    • 00:34:06
      I don't have any questions.
    • 00:34:09
      I don't have any questions.
    • 00:34:12
      So it's time for the applicant's presentation, if they have one.
    • Keith LancasterDevelopment team land planner
    • 00:34:20
      Good afternoon.
    • 00:34:21
      I'm Keith Lancaster.
    • 00:34:22
      And with me is Charlie Armstrong.
    • 00:34:24
      We also have our landscape architect.
    • 00:34:26
      And our architect, I believe, is virtually.
    • 00:34:28
      Oh, do you need?
    • SPEAKER_04
    • 00:34:30
      I'm sorry.
    • Keith LancasterDevelopment team land planner
    • 00:34:31
      Currently.
    • 00:34:32
      As we met and discussed the final four comments that were provided to us, our team got together
    • 00:34:43
      and Chris is pulling up on the screen.
    • Khris TaggartSenior Planner
    • 00:34:47
      Would you want me to try to help the floor plans?
    • Keith LancasterDevelopment team land planner
    • 00:34:52
      Yeah, yeah, yes sir.
    • 00:34:55
      So we first wanted to address the projections along the face of the wall facing the corridor and we went back and tried to, because
    • 00:35:08
      Originally, it was just an overlap of the wall panel.
    • 00:35:12
      And so we're now showing a true projection off the main wall with our towers along the frontage of this project.
    • 00:35:22
      Actually, is Matt on by chance?
    • SPEAKER_04
    • 00:35:26
      He is.
    • 00:35:26
      He's raised his hand.
    • Keith LancasterDevelopment team land planner
    • 00:35:27
      He might be able to explain the changes we did to the.
    • SPEAKER_04
    • 00:35:32
      Yeah, if you'll just unmute.
    • SPEAKER_01
    • 00:35:36
      OK. Hello, can you hear me?
    • SPEAKER_04
    • 00:35:43
      We can hear you just fine.
    • SPEAKER_01
    • 00:35:44
      OK, great.
    • 00:35:46
      Yes, thanks, Keith.
    • 00:35:48
      The comment for increasing the projection in the updated exhibit that we've shared here today, we have along the primary facade where we have four main entrances, we've revised the lap panels at these
    • 00:36:06
      Darker gray accent panels to be true projections.
    • 00:36:12
      So those will be formed up and poured as a monolithic three dimensional panel that will project off of the main facade by two feet.
    • 00:36:24
      We had the the width there in the sidewalk to allow for that increased projection.
    • 00:36:31
      And that two foot projection puts us
    • 00:36:35
      basically at our minimum sidewalk width for the current civil design.
    • 00:36:42
      So, you know, viewing the building from kind of an oblique angle, it'll be a nice undulation.
    • 00:36:49
      You'll get some nice shadow lines there to, again, address the staff comments.
    • 00:36:57
      In addition to that, on the elevations we've provided, the
    • 00:37:04
      LED downlights to show in addition to the photometric plan that was provided, we have included those on the elevations to show where those fixtures will fall relative to the current design.
    • 00:37:26
      In addition to respond to, I believe, comment number four, we sent Chris a grading plan to address that fourth comment.
    • 00:37:40
      And I believe that addressed each of the four comments.
    • Keith LancasterDevelopment team land planner
    • 00:37:48
      Yeah, there was a little confusion because we have a site plan, WPO plan, all running
    • 00:37:54
      together and unfortunately we didn't group that grading plan that shows the contour lines with it so we provided that to Chris as well.
    • Chris HenningsenChair, Architectural Review Board
    • 00:38:08
      All right, I guess we'll see if any board members have questions for the applicant.
    • 00:38:14
      I guess we'll start with Frank Stoner.
    • Frank StonerMember, Architectural Review Board
    • 00:38:18
      Yeah, thanks for the presentation.
    • 00:38:21
      Quick question for clarification.
    • 00:38:23
      The warmer brown that appears to be around the entrances and runs up the side, what is that and where is it in the plane?
    • 00:38:33
      And it may be on here, but it's too small for me.
    • 00:38:35
      Sure.
    • Keith LancasterDevelopment team land planner
    • 00:38:37
      Matt, you want to take that one?
    • SPEAKER_04
    • 00:38:39
      Go ahead, Matt.
    • SPEAKER_01
    • 00:38:42
      Absolutely.
    • 00:38:43
      Yes, that material is
    • Frank StonerMember, Architectural Review Board
    • 00:38:46
      It actually shows up on these, but doesn't show up on there.
    • Charlie ArmstrongVice President of Land Development
    • 00:38:49
      We lost Matt.
    • 00:38:49
      It's an aluminum panel with a mahogany color finish to it.
    • 00:38:53
      Oh, there he is.
    • 00:38:54
      Matt, can you guys hear me?
    • 00:38:56
      Yes.
    • SPEAKER_01
    • 00:38:57
      Oh, thanks.
    • 00:38:58
      Yeah, that is an extruded aluminum that has a wood texture printed on it.
    • 00:39:05
      And it's basically a longboard plank is the manufacturer.
    • 00:39:10
      but it's a very sharp looking product that has a very convincing wood grain finish that obviously has more benefits over true wood and just the maintenance and longevity.
    • 00:39:25
      That system, it's a fairly tight system.
    • 00:39:29
      It would project off the wall an inch and a half to two inches and we would incorporate it into the
    • 00:39:38
      Profiles and trims around the storefront area.
    • 00:39:43
      So there is there is a slight basically change in profile there around the entrances where we're utilizing this this kind of premium product.
    • Frank StonerMember, Architectural Review Board
    • 00:39:57
      My other question is, where do you guys envision signage going?
    • 00:40:01
      I assume you could have multiple tenants in the building and
    • Charlie ArmstrongVice President of Land Development
    • 00:40:05
      Yeah, I expect we will have multiple tenants.
    • 00:40:08
      And we haven't yet developed a signage plan.
    • 00:40:11
      I think that'll be something we have to come back to you for a separate review.
    • 00:40:14
      Once we've fleshed that out, it'll take a lot of tenant input.
    • 00:40:17
      So right now we don't have, I'll call it an anchor.
    • 00:40:22
      When we do, it'll be probably the right time to come to you all.
    • 00:40:27
      Gotcha.
    • Frank StonerMember, Architectural Review Board
    • 00:40:27
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 00:40:28
      All right.
    • 00:40:28
      Thanks.
    • 00:40:29
      Dave?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:40:31
      Sure, thank you for the development today.
    • 00:40:32
      I appreciate the additional depth in the projection.
    • 00:40:36
      I guess as one follow up question, I think staff noted both considering increasing the depth and the number of projections or recesses.
    • 00:40:44
      Are there any other areas in the facade that you've considered either recessing or doing anything to adjust plane and scale further?
    • Charlie ArmstrongVice President of Land Development
    • 00:40:56
      So this revision addresses all of the projections on the front of the building.
    • 00:41:01
      So then we won't come out, but we haven't found other places that would be appropriate.
    • 00:41:06
      Matt can speak to some things we've looked at, including whether we should move them to corners and things like that, or add to corners.
    • 00:41:13
      Matt, you want to give your opinion on that?
    • SPEAKER_01
    • 00:41:18
      Sure.
    • 00:41:18
      Can everyone still hear me?
    • 00:41:20
      Yeah.
    • 00:41:21
      Great.
    • 00:41:21
      Yeah, we did look at that and with this site there are some constraints, particularly on the north elevation where we also have some of these elements.
    • 00:41:36
      Unfortunately, it's
    • 00:41:37
      It's going to be difficult to get that same projection at those areas just with some of the site and civil layout constraints particularly a retention pond very close off the edge of the building where we do have some grading.
    • 00:41:55
      So the hope was that we focus these moves on the primary elevation and really just maintain the lap panel condition, which there are two lap panels on that north elevation.
    • 00:42:12
      that would still give a little bit of a shadow line.
    • 00:42:16
      But again, on that constrained elevation, really just utilizing the two lap panels and decorative reveals along with changes in paint.
    • 00:42:29
      So that facade can sort of kind of take a backseat to the primary facade where we really have utilized the longboard plank and the two foot projections.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:42:44
      Thank you, and can you describe the proposed planar relationship between the tall portion of longboard plank and the projections, how those sit relative to one another?
    • SPEAKER_01
    • 00:42:56
      I believe the question is referring to the two-inch projection of the longboard at the head of the storefront systems, is that correct?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:43:09
      Well, I guess in the updated elevations that you've shared printouts of today, the long vertical extent that's shown immediately to the side of the deeper precast projections, that goes the full height of the facade.
    • SPEAKER_01
    • 00:43:24
      Oh, absolutely.
    • 00:43:25
      You're looking at the document noted as option B, correct?
    • 00:43:30
      Yes.
    • 00:43:31
      OK.
    • 00:43:32
      Yes, that would continue up through to the top of the facade where we would incorporate that into the coping detail.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:43:44
      And what's its relationship to the precast that it's next to?
    • SPEAKER_01
    • 00:43:49
      It would be basically the primary wall would be zero.
    • 00:43:55
      That material would be two inches out.
    • 00:43:58
      And the product comes with a kit of parts that would have extrusions to give a nice edge to that.
    • 00:44:08
      And then basically the system, the longboard would butt up against the two foot projection.
    • 00:44:16
      So essentially you're looking at a 22 inch projection if you're starting from the face of the longboard panel.
    • 00:44:27
      It's all a rain screen system, so the reality is we would flash over the top of that system, but it's not essentially watertight.
    • 00:44:36
      It's sitting outboard of the precast, or I'm sorry, the cast in place concrete.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:44:43
      Okay, thank you.
    • 00:44:45
      Last question is I think overall the modulation of proportion shown at least graphically is nice.
    • 00:44:53
      One question I had was the areas that are I guess white, there are four of them and they're roughly square in the facade.
    • 00:45:00
      Whether it would be feasible to recess those at all from the primary plane of precast to further modulate the scale of the elevation?
    • SPEAKER_01
    • 00:45:09
      Unfortunately, the system that this building would be tilt up construction where the panels are generally about eight inches.
    • 00:45:23
      You can sometimes do like an inch or possibly an inch and a half recess.
    • 00:45:31
      But I would argue that it's not enough to really move the needle, so to speak, from a visual standpoint.
    • 00:45:42
      There is another scenario where you actually do a lab condition there, but that would be cutting into the rentable area of the building, essentially.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:45:59
      Well, thank you.
    • 00:46:00
      Appreciate your answers.
    • Chris HenningsenChair, Architectural Review Board
    • 00:46:02
      Great, thanks.
    • 00:46:03
      Frank Hancock?
    • 00:46:05
      I don't have any questions.
    • Taro MatsunoMember, Architectural Review Board
    • 00:46:06
      Thanks.
    • 00:46:07
      Tara?
    • 00:46:08
      Yes, I'm wondering, so I think the east elevation, the logic is pretty clear.
    • 00:46:15
      Could you tell us a little bit, I think that the mid-gray color is basically designating like the tower element, correct?
    • 00:46:23
      Correct.
    • 00:46:23
      And that's 16.8 with
    • 00:46:29
      Correct.
    • 00:46:31
      And then on the west elevation, it looks like those panels are 23.
    • 00:46:35
      That's correct.
    • 00:46:39
      And then on the south, it looks like they're 20.
    • 00:46:43
      Correct.
    • 00:46:44
      And then on the north, they're 20.
    • 00:46:47
      Correct.
    • 00:46:48
      Is there any reason for the change in width?
    • SPEAKER_01
    • 00:46:52
      Yes, it generally depends on specific constraints for each elevation.
    • 00:47:00
      To start with the west elevation, the spacing of the dock doors there is driving that panel width
    • 00:47:12
      With the tilt up construction, generally any panel over about 28 feet kicks in sort of some structural construction gymnastics, not to kind of get into it, but it sometimes requires larger cranes.
    • 00:47:30
      And so we generally, to keep things economical, keep these panels to about 27 feet.
    • 00:47:38
      So with that west elevation where you have the dock equipment, these panels, in order to be efficient and logical, they generally take on a more, let's say, uniform size in about that 27 foot dimension.
    • 00:47:58
      The front wall, the east elevation,
    • 00:48:01
      where we have the primary entrances.
    • 00:48:04
      The tower elements, they wanted to skinny up just proportionally with the top of the wall at 29 feet.
    • 00:48:14
      The way that the white accent panel above the entrance is reading, it just proportionally felt better to the eye in our opinion to skinny them up a little bit.
    • 00:48:26
      And then on the end walls,
    • 00:48:29
      the south and north elevation this is a similar case to the dock wall where you're dealing with basically splitting panels between the column grids which you know in this case are 40 feet so we again divided that by you know divided that in half
    • 00:48:54
      that's not to say that the south and north elevation we couldn't you know using that 27 foot max we could skinny up those those gray panels in that case but in our opinion it was it was something that you know was adding actually some some visual interest to have these tower elements
    • 00:49:17
      vary a little bit depending on the scenario.
    • 00:49:23
      You look at the dock wall where they are hosting these fire access doors with the platforms and visually they feel different and therefore kind of lend themselves to a slightly different module, in our opinion.
    • Taro MatsunoMember, Architectural Review Board
    • 00:49:43
      And can you talk about the differences in the clear story windows?
    • SPEAKER_01
    • 00:49:47
      Absolutely.
    • 00:49:48
      The clear story windows on the west elevation, the dock wall elevation are, I guess for a lack of a better phrase, the true light emitting
    • 00:50:03
      You know, they have a utility, not to say that the others don't, but the others, this being an industrial use, the area behind that dock wall is what they call speed bay, which is generally open and free from racking.
    • 00:50:20
      And so you have this large
    • 00:50:22
      Generally open area that allows that natural light to filter into the space.
    • 00:50:30
      The other windows across the building are generally, you know, not behind as much of an open area.
    • 00:50:40
      So those are are not as utilitarian from a lighting capacity within the building.
    • 00:50:49
      That's not to say that they're not letting in natural light to enhance that interior space, but they were added for primarily visual interest from the exterior of the building.
    • 00:51:05
      Therefore, they are a different size and similar to the logic of the towers.
    • 00:51:14
      They are a different module.
    • 00:51:18
      for visual interest, but also just being cognizant of cost, to be honest, not making those too large.
    • Taro MatsunoMember, Architectural Review Board
    • 00:51:30
      What size are the windows?
    • SPEAKER_01
    • 00:51:32
      The windows, give me a second here.
    • 00:51:42
      Scale.
    • 00:51:44
      Sorry, I'm pulling a dimension.
    • 00:51:54
      So the ones along the front of the building are 18 inches wide and their height is four feet.
    • 00:52:10
      The ones along the dock wall that again are providing more light into the building are five feet tall by three feet wide.
    • Taro MatsunoMember, Architectural Review Board
    • 00:52:24
      So you were talking about the cost between an 18 inch window that's 4 feet tall and a 5 foot window that's 3 feet tall?
    • SPEAKER_01
    • 00:52:34
      I wouldn't say that cost is essentially inhibiting us to enlarge those windows, but if you look at the east elevation, all of the elements are tied together and the four foot by 18 inch window just feels nice as far as this small gesture on that tower.
    • 00:52:59
      I would argue as soon as you size that window up to the five by three, it's no longer this little gesture on the tower.
    • 00:53:10
      I guess to make the point, in my opinion, all the proportions are right now very tied to each other.
    • 00:53:20
      And I would argue we would not want to size up those windows on the primary elevation.
    • 00:53:28
      They are in contrast right now to the storefront openings, and that, in my opinion, is what's lending itself to the visual interest and the overall composition to keep that clear story on the east elevation smaller, if that makes sense.
    • Chris HenningsenChair, Architectural Review Board
    • 00:53:50
      OK, thank you.
    • 00:53:52
      All right, thanks.
    • 00:53:54
      I don't have any questions for the applicant.
    • 00:53:56
      So are there any members of the public that want to make a comment?
    • SPEAKER_04
    • 00:54:02
      No, sir.
    • Chris HenningsenChair, Architectural Review Board
    • 00:54:04
      All right, in that case, the ARB will now go into discussion.
    • 00:54:08
      We'll start with Taro if you have any comments.
    • Taro MatsunoMember, Architectural Review Board
    • 00:54:11
      Thanks.
    • 00:54:12
      Yes.
    • 00:54:12
      I mean, I think the preliminary, the east facade as shown in this drawing on our desks is certainly more developed than the previous ones.
    • 00:54:24
      And I understand that there are a lot of constraints that go into designing a primarily industrial building.
    • 00:54:29
      And I think generally speaking, an industrial use is pretty appropriate or is a sort of desirable thing for the county and that
    • 00:54:38
      incorporating the requirements of this type of space is something that is important.
    • 00:54:45
      I think that there are a couple of places where, I mean, I think that the thing that's interesting about industrial buildings is that they have a really consistent design, like that you have a module, it gets repeated and it creates a pretty significant thing.
    • 00:55:02
      And so I would have to disagree with
    • 00:55:05
      the applicant that the modulations and the proportions of the middle gray bay sort of add visual interest to the composition.
    • 00:55:15
      I think, you know, both from the guidelines aim at making the consistent and uniform appearance or a consistent appearance around the space of the building and sort of the logic of an industrial building that
    • 00:55:32
      changing the widths of these mid-gray bays.
    • 00:55:36
      I don't think it's doing the building a ton of favors, especially on the side elevations, which I think the applicant mentioned were secondary.
    • 00:55:48
      But I think from the perspective image that they showed, I can't remember if it's the south or the north.
    • 00:55:58
      I think it's the north elevation.
    • 00:56:00
      is pretty prominent in the building facade.
    • 00:56:04
      And so I think at the very least, making sure that the module that you're using, if you're gonna use it on those side facades, it should be the same width, you know?
    • 00:56:16
      Because you're gonna be able to tell the difference between the proportion of that shape.
    • 00:56:21
      And logically, there's not a whole, like it doesn't make a ton of sense why that area on the right-hand side would be,
    • 00:56:29
      20 feet versus the
    • 00:56:32
      one on the left being 18.6 or 16.8.
    • 00:56:36
      I think, you know, as an industrial building you pick your module and you stick with it, you know?
    • 00:56:40
      And I think in that respect, I mean, the applicant could also just not include those bays on that face and choose a different system.
    • 00:56:50
      But I think this sort of in-between language of like sometimes it's a 16.8 bay with a two foot projection.
    • 00:56:55
      Sometimes it's a painted area of 20 feet.
    • 00:56:58
      Sometimes it's a painted area of 23 feet.
    • 00:57:01
      is not helping the building.
    • 00:57:06
      You know, if you wanted to change the side bays to light gray on the top, dark gray on the bottom, followed by white on the top, dark gray on the bottom, followed by light gray on the top, dark gray on the bottom, like that would also have a logic to it.
    • 00:57:22
      But there's something about this switching around the different mid-gray sections that I think detracts from its consistency as an industrial building.
    • 00:57:31
      You know, I think that there are ways that the applicant, I'd like to see what the site constraints are on the side facade because they alluded to some issue of a stormwater detention facility that's preventing them from introducing the two-foot projection.
    • 00:57:49
      If they could speak to that a little bit more, it might help decide whether or not it makes more sense to just turn those towers onto the side facade.
    • 00:57:57
      and continue them on from there, or if it makes sense to just change the language entirely.
    • 00:58:01
      I think that there's some promising developments.
    • 00:58:09
      I think it needs a little work, but I'm interested to hear what my co-board members would have to say about it.
    • 00:58:19
      Yeah, that's kind of where I'm at.
    • Chris HenningsenChair, Architectural Review Board
    • 00:58:21
      All right, thank you.
    • 00:58:23
      Frank Hancock?
    • Frank HancockVice Chair, Architectural Review Board
    • 00:58:24
      Sure.
    • 00:58:26
      Thank you for the presentation and the updated visualizations.
    • 00:58:32
      I think they're very nice and give a good sense for what the building is going to look like.
    • 00:58:38
      I appreciate the new color palette, although it's not drastically different.
    • 00:58:45
      I do think it's effective.
    • 00:58:48
      A little warmer, perhaps.
    • 00:58:54
      And then let's see, I do agree with Taro on kind of that northeast corner.
    • 00:59:01
      I'm maybe less concerned that the, you know, repeated forms all match all the way around, especially if we can't see them.
    • 00:59:14
      But I do think there is maybe some further study needed on that corner.
    • 00:59:20
      And you know, if that,
    • 00:59:23
      could have a similar projection on the north elevation that we had on the east.
    • 00:59:30
      I see the grading maybe is what's the constraint there, but all in all, I think it's a nice application.
    • 00:59:39
      I think the applicant is, you know,
    • 00:59:43
      done a lot of the things we would ask for.
    • 00:59:44
      I think the landscaping, the berming is all going to be really important on this one as far as, yes, as far as kind of minimizing visibility.
    • 00:59:58
      But yeah, I would be open to a little bit more focus on that corner.
    • 01:00:03
      And I don't think it's big.
    • 01:00:04
      I don't think it's wholesale changes.
    • 01:00:06
      I think it's some of the moves that you guys have already done that maybe you're just brought around to that north elevation.
    • 01:00:13
      Thanks.
    • Chris HenningsenChair, Architectural Review Board
    • 01:00:17
      All right.
    • 01:00:17
      Thank you.
    • 01:00:17
      Dade?
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:00:19
      Sure, yeah, thanks to the applicant for the updated presentation materials and the adjustments to the color palette and the increased depth at the tower-like projections.
    • 01:00:31
      I agree with what Frank and Taro have observed.
    • 01:00:34
      I do think it would be worth studying a bit more the northeast corner or just the corners in general at the north and the south in terms of how that real rigorous facade resolves and then transitions to the
    • 01:00:49
      to the end elevations.
    • 01:00:52
      I do think it would be helpful if it was possible to incorporate an additional change in plane, typically on the east facade.
    • 01:01:04
      If, for example, the bays with the current white treatment and the entries and the wood look material were recessed, for example, eight inches, it would further break the cornice line and I think do a great deal to break down the scale of that long facade.
    • 01:01:19
      I think similarly that might be something to consider at the north and the south in terms of after the facade turns is there any change in plane at the north and south elevations that might allow the Corns Line to break and to break down the scale of the building even subtly.
    • 01:01:36
      Sensitive of course to leasable area, you know, I think those white areas are about 25 feet wide.
    • 01:01:42
      There are four of them.
    • 01:01:43
      If they were recessed eight inches, that would be about 65 or 66 square feet across the facility.
    • 01:01:48
      So I appreciate the applicant sharing the details on the Woodlook material.
    • 01:01:56
      I think, personally, the application of it in the original material, where it's sort of contained at the entrance below the band,
    • 01:02:05
      has more appeal and seems more rational to me than extending it up the precast as in the other exhibit we were provided today, but you're just offering that observation.
    • 01:02:17
      But again, my thanks to the applicant for the updated presentation and materials.
    • Chris HenningsenChair, Architectural Review Board
    • 01:02:23
      All right, thank you.
    • 01:02:24
      Frank?
    • Frank StonerMember, Architectural Review Board
    • 01:02:27
      Yeah, well, I tend to agree with a lot of the comments that others have made.
    • 01:02:35
      In particular, the scale of the projections on the northeast corner.
    • 01:02:45
      I tend to think that micromanaging the design in this case isn't going to do a lot to change the overall feel of the building.
    • 01:02:57
      I do agree with Dade.
    • 01:02:58
      I'm not sure you're getting a lot of value out of running the wood strip up the side and the rendering actually didn't show it running up the full height of the building.
    • 01:03:09
      In general, you know, it's I think the the rhythm and the color scheme feel pretty good.
    • 01:03:17
      Not necessarily in agreement with the comment about the window sizes, but again, not inclined to sort of micromanage that.
    • 01:03:27
      All in all, I think with the landscaping plan that's been submitted, I think it'll be a nice project.
    • 01:03:33
      And we're not going to see a lot of, you know, once the stuff matures, you're not going to see much anyway.
    • 01:03:38
      So I'd be inclined to approve it.
    • Chris HenningsenChair, Architectural Review Board
    • 01:03:41
      All right.
    • 01:03:44
      Thank you.
    • 01:03:45
      And I also agree.
    • 01:03:49
      I think it's an improvement over the initial submission and I appreciate that and I think at this point it's really just down to some tweaks I think like Frank I'm
    • 01:04:05
      Satisfied with where it is now, then would support it.
    • 01:04:10
      But I certainly think some of the comments that have been made are really valid.
    • 01:04:16
      And I think a little bit more refinement certainly couldn't hurt.
    • 01:04:24
      So if we could take a look at the recommended motion.
    • Margaret MaliszewskiPlanning Manager
    • 01:04:56
      The recommended action is a motion for approval of the certificate of appropriateness with the items that were listed in the staff report.
    • 01:05:04
      There was four items there.
    • 01:05:07
      You've also been discussing consistent proportions and the design of the northeast corner.
    • 01:05:15
      If you want to have some additional wording on that, we'd be happy to take that for you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:05:26
      Yes.
    • Charlie ArmstrongVice President of Land Development
    • 01:05:29
      Thank you, Charlie Armstrong.
    • 01:05:30
      Tari, I just wanted to step up and address your question about the constraints on the north side, particularly.
    • 01:05:36
      It's actually constraints on both the north and south.
    • 01:05:39
      We've already shrunk the width of the building as much as we are able.
    • 01:05:44
      There's a large setback on the south side because it's closer to a residential zoned area.
    • 01:05:50
      And on the north is the logical place for stormwater management.
    • 01:05:56
      and obviously a lot of impervious so there's significant stormwater management necessary.
    • 01:06:03
      We're feeling some push and pull from various places in the county itself because engineering is asking us to push that
    • 01:06:11
      Stormwater area as far from the road as possible for safety.
    • 01:06:15
      VDOT I think would want the same, but they're less adamant than engineering.
    • 01:06:20
      And so it has pushed it to the building.
    • 01:06:23
      And we also have a sewer line that has to get up through there.
    • 01:06:26
      There's a natural gas line.
    • 01:06:28
      existing between the pond and the road as well.
    • 01:06:32
      And sewer, of course, ACSA wants nice flat area and distance from everything to the pipe.
    • 01:06:39
      So we've got a real fine needle to thread.
    • 01:06:43
      And even a two foot change on that side would introduce either a small retaining wall adjacent to a sewer easement to hold up the building or sub walls, which make it
    • 01:06:57
      aesthetically appear taller or something like that.
    • 01:07:00
      So we're hoping that this is the best solution to all those.
    • 01:07:08
      And it's a compromise a little bit for everybody.
    • 01:07:11
      Engineering's not getting the distance they want from the road either in favor of architecture.
    • 01:07:16
      So hope that helps with a little context.
    • Taro MatsunoMember, Architectural Review Board
    • 01:07:18
      Yeah, that's helpful.
    • 01:07:19
      Thank you.
    • Charlie ArmstrongVice President of Land Development
    • 01:07:19
      And I'll point out again that landscaping is our primary effort.
    • 01:07:25
      here and will be as we install.
    • 01:07:29
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:07:29
      All right.
    • 01:07:30
      Thank you.
    • 01:07:33
      Yes, I have a question.
    • 01:07:36
      The two-foot projection, is that a response to this comment or was that the original submission?
    • Khris TaggartSenior Planner
    • 01:07:43
      No, that is a response to the comment.
    • 01:07:46
      I don't think it sounded like it didn't project at all before the comment.
    • 01:07:52
      All right.
    • 01:07:52
      Thank you.
    • Frank StonerMember, Architectural Review Board
    • 01:07:56
      So how many of these can we eliminate?
    • 01:07:59
      We have grades, right?
    • Frank HancockVice Chair, Architectural Review Board
    • 01:08:01
      I think all of them, right?
    • Frank StonerMember, Architectural Review Board
    • 01:08:02
      Yeah.
    • 01:08:04
      Our proposed fixture locations, we have those.
    • Chris HenningsenChair, Architectural Review Board
    • 01:08:11
      I think we could strike four, right?
    • 01:08:14
      Just start.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:08:15
      Well, I guess Margaret's staff hasn't really had a chance to review.
    • 01:08:21
      I don't know if this was sent ahead of the meeting or.
    • 01:08:24
      It was just brought to the meeting.
    • Khris TaggartSenior Planner
    • 01:08:26
      It was, and it probably should also be just included in complete site plan versus the sheets separately.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:08:34
      So if we left them, it's been addressed, but we wouldn't want to strike them.
    • Margaret MaliszewskiPlanning Manager
    • 01:08:38
      Yeah, so these comments
    • 01:08:43
      or these recommended conditions are related to the submittal that was reviewed for this staff report.
    • 01:08:49
      So the real recent changes that were discussed here, it sounds like everybody's good with them and they would address these, but the record can show that, but just for the review to track through our system, it would be best to keep these here and just acknowledge that they've been addressed with what was submitted today.
    • Taro MatsunoMember, Architectural Review Board
    • 01:09:23
      Should we change one to say like increase the depth to two feet, for instance, just showing that they've met that criteria for the review?
    • Chris HenningsenChair, Architectural Review Board
    • 01:09:36
      Sure.
    • 01:09:36
      I mean, yeah.
    • 01:09:38
      Or at least on that one on the east elevation.
    • Taro MatsunoMember, Architectural Review Board
    • 01:09:42
      Yeah.
    • 01:09:46
      And then I think on the projections,
    • 01:09:52
      I can't remember if it's north or south, but I accept the, I think the applicant makes a good case for why those projections are not continued.
    • 01:10:02
      So I don't, for the record, I don't have a particular issue with that.
    • 01:10:06
      I think I do have an issue with the proportions on that facade, but I think that can be addressed through painting, different painting strategy, lack of consistency.
    • 01:10:16
      I would, I know we don't want to get too deep into it,
    • 01:10:23
      I do feel like, say, consider.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:10:28
      Are you asking for the north elevation?
    • Taro MatsunoMember, Architectural Review Board
    • 01:10:32
      Yeah, just that they use the name they, and if it just, you either make it match or don't match.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:10:38
      Like horizontal dimension?
    • 01:10:40
      Yeah, yeah.
    • 01:10:40
      Of that element that projects on the east elevation, should that should match?
    • Taro MatsunoMember, Architectural Review Board
    • 01:10:45
      No, I don't think they, either they should match or they should be totally different, is my personal opinion.
    • 01:10:51
      is like this sort of in-between thing where it's not quite the right same size and not quite the same projection as it is on the front.
    • 01:10:59
      Like it might just be cleaner if they just- Eliminate it entirely?
    • Frank StonerMember, Architectural Review Board
    • 01:11:02
      Yeah.
    • 01:11:02
      Is that what you're saying?
    • Taro MatsunoMember, Architectural Review Board
    • 01:11:03
      Yeah, I would be fine with that.
    • Margaret MaliszewskiPlanning Manager
    • 01:11:10
      I didn't hear that last- Okay, anyway.
    • Taro MatsunoMember, Architectural Review Board
    • 01:11:12
      Just he suggested to eliminate it completely.
    • SPEAKER_04
    • 01:11:14
      All right, Matt has his hand up.
    • 01:11:16
      Is he allowed to speak?
    • 01:11:19
      That has a hand up.
    • 01:11:19
      Is he allowed to speak again?
    • Frank HancockVice Chair, Architectural Review Board
    • 01:11:21
      Oh, yeah.
    • SPEAKER_04
    • 01:11:21
      All right, Matt, go ahead.
    • 01:11:26
      Just unmute yourself.
    • Frank StonerMember, Architectural Review Board
    • 01:11:29
      Can everybody hear me?
    • 01:11:31
      Yes.
    • 01:11:31
      Yes.
    • SPEAKER_01
    • 01:11:32
      I have two comments.
    • 01:11:35
      One after
    • 01:11:36
      Reviewing our drawings as we speak here.
    • 01:11:39
      We can absolutely make both the north and south elevation match the 16 foot eight.
    • 01:11:47
      All the tower elements are consistent.
    • 01:11:51
      Absolutely.
    • 01:11:52
      I think it's a great comment.
    • 01:11:54
      That said, I would argue that the west wall where we have the dock equipment
    • 01:11:59
      and the larger windows and a different application with the door being a separate facade.
    • 01:12:04
      If we could keep those at the 23 foot so that we basically ironed it out so that we have two different towers, one at 16 foot eight and one at 23.
    • 01:12:19
      We can absolutely do that and I think it helps the design to have those tower elements on that north elevation personally.
    • 01:12:29
      The other comment I just wanted to make and thank you for letting me speak here again is that we actually have two exhibits that were provided today.
    • 01:12:40
      One was
    • 01:12:43
      Really a primary one and that is without the wood running all the way up the building.
    • 01:12:49
      And I tend to agree with to the gentleman here who argued that it wasn't really moving the needle visually or in my opinion, it helps to focus that material around the entrances where it has more impact and feels a little more intentional.
    • 01:13:07
      So I just wanted to clarify that there was another option B that was brought to the table here just as in a way as kind of a workshop if there were comments that you guys wanted to see that material carrying higher or et cetera.
    • 01:13:26
      So I just wanted to clarify which way we wanted to go.
    • 01:13:32
      So thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:13:42
      All right, thanks for that.
    • Margaret MaliszewskiPlanning Manager
    • 01:14:14
      I've just added a condition, make the tower widths consistent on the north, east, and south elevations.
    • 01:14:23
      I understand that correctly, but does that suit everyone?
    • Chris HenningsenChair, Architectural Review Board
    • 01:14:27
      Is that satisfactory to everybody?
    • 01:14:30
      Yes.
    • Margaret MaliszewskiPlanning Manager
    • 01:14:32
      I'm not clear on, is it option A or option B that you're all
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:14:37
      Well, and I guess option A is the original application with the Woodlook material just at entrances and below the data.
    • 01:14:45
      Yes.
    • Margaret MaliszewskiPlanning Manager
    • 01:14:46
      Yeah.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:14:47
      And so that would be consistent with what was reviewed so we could be silent about it in the motion.
    • 01:14:53
      And that would be.
    • 01:14:55
      Yeah.
    • Khris TaggartSenior Planner
    • 01:14:55
      The only difference is noting the projection and actually making the projection.
    • 01:15:02
      The printout is just being reviewed today.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:15:07
      You all right?
    • Frank StonerMember, Architectural Review Board
    • 01:15:10
      Sorry.
    • Chris HenningsenChair, Architectural Review Board
    • 01:15:15
      All right.
    • 01:15:16
      Well, if no one has any additional tweaks, would anybody like to make a motion?
    • Frank HancockVice Chair, Architectural Review Board
    • 01:15:26
      I'll move for approval of the certificate of appropriateness for ARB-2025-17 Northside Industrial with the conditions listed in the staff report amended as follows.
    • 01:15:41
      Add two feet to item one and add an item number five, make the tower widths consistent on the north, east, and south elevations.
    • Chris HenningsenChair, Architectural Review Board
    • 01:15:53
      I'll second.
    • 01:15:55
      Thank you.
    • 01:15:56
      If we could put that to a vote.
    • SPEAKER_04
    • 01:15:59
      Mr. Van Der Werf?
    • Chris HenningsenChair, Architectural Review Board
    • 01:16:01
      Aye.
    • SPEAKER_04
    • 01:16:01
      Mr. Matsuno?
    • Chris HenningsenChair, Architectural Review Board
    • 01:16:02
      Aye.
    • SPEAKER_04
    • 01:16:03
      Mr. Stoner?
    • Chris HenningsenChair, Architectural Review Board
    • 01:16:04
      Aye.
    • SPEAKER_04
    • 01:16:04
      Mr. Hancock?
    • Chris HenningsenChair, Architectural Review Board
    • 01:16:06
      Aye.
    • SPEAKER_04
    • 01:16:07
      Mr. Henningsen?
    • Chris HenningsenChair, Architectural Review Board
    • 01:16:08
      Aye.
    • SPEAKER_04
    • 01:16:08
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:16:09
      All right.
    • 01:16:09
      Thanks a lot.
    • 01:16:12
      All right, so we have one work session today, which is a discussion on ARB-2023-17, Barnes Lumber.
    • 01:16:23
      And, Margaret, a few of the presentation.
    • Margaret MaliszewskiPlanning Manager
    • 01:16:26
      Sure.
    • 01:16:27
      Yes, as you know that this is a work session.
    • 01:16:29
      It's to finalize the countywide certificate of appropriateness design criteria for the Barnes Lumber development.
    • 01:16:35
      You last reviewed this proposal in March of this year, and at that time, you approved the criteria with some conditions.
    • 01:16:42
      After the March 3rd meeting, the applicant submitted a revision to address the conditions.
    • 01:16:47
      We've been working through that material.
    • 01:16:49
      There remains one outstanding issue, and that has to do with murals.
    • 01:16:54
      But as a reminder, the overall proposal is based on establishing visual connections from the Route 240 entrance corridor into the site, consistent with the block pattern of the development.
    • 01:17:05
      The criteria include transparency and articulation requirements for the facades of buildings visible from the entrance corridor.
    • 01:17:13
      And the criteria include landscaping on the entrance corridor side of the development between the development and the railroad tracks at the western half of the frontage where the topography of the site makes the development more visible.
    • 01:17:25
      So the text in the box at the top of this slide is the applicant's proposal on murals.
    • 01:17:30
      I've tried to sort of parse out each criterion in the table at the bottom of the slide, and we'll take you through it one at a time.
    • 01:17:37
      In these next three slides, I have some images that just show the general view from the entrance corridor into the site across the railroad tracks.
    • 01:17:45
      Then I've also just popped in a few images of murals.
    • 01:17:49
      These are not specific to the development.
    • 01:17:50
      They aren't proposed.
    • 01:17:51
      It's just to sort of get you thinking about murals.
    • 01:17:55
      So on facades facing the entrance corridor street, when the facades will be visible from the entrance corridor, the proposal is that murals will be allowed and that ARB review is required if they occupy 20% or more of the facade area.
    • 01:18:13
      That means that on those facades facing the entrance corridor street and visible from the street, murals would be exempt from ARB review if they occupy less than 20% of the facade area.
    • 01:18:27
      on facades that don't directly face the entrance corridor street.
    • 01:18:31
      The proposal is that murals would be allowed to occupy any percent of the facade area and those murals would be exempt from ARB review.
    • 01:18:42
      There's the general proposal again.
    • 01:18:44
      I've got just a rough diagram I put together to show maybe what 20% of the facade facing the entrance corridor would look like.
    • 01:18:52
      Fossil colored those end elevations just to highlight those.
    • 01:18:56
      We did list some questions in the memo that was posted last week.
    • 01:19:01
      Generally, they're asking you if you're OK with the proposal as it is.
    • 01:19:08
      If murals can be exempt from ARB review, what percentage of the facade is appropriate to be exempt?
    • 01:19:17
      So we could step through each of those questions one at a time or you could go right to discussion or if you have questions.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:19:24
      Can I ask a question before we go to the questions?
    • 01:19:28
      In terms of the overall plan for the area, what is the
    • 01:19:32
      Longest extent of facade that we would be considering a percentage of 20%?
    • 01:19:38
      Like, is it 100 feet?
    • 01:19:39
      Is it 1,000 feet?
    • 01:19:40
      Is it?
    • Margaret MaliszewskiPlanning Manager
    • 01:19:43
      That is a good question, and I'm not sure that I can answer it.
    • 01:19:49
      You're asking what that block length is?
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:19:51
      I guess so.
    • 01:19:52
      But the percentage and context, because that has an impact on what the potential scale of a mural might be.
    • Margaret MaliszewskiPlanning Manager
    • 01:19:59
      Sure.
    • 01:20:02
      Ask the applicant to answer that question for you.
    • Kurt KeeseckerBRW Architects
    • 01:20:13
      Hey, I'm Kurt Kiesecker, BRW Architects, representing the applicant.
    • 01:20:18
      The longest block length on a diagram in the package on my PDF page 39 of 40
    • 01:20:25
      which was just a reference diagram is about 400 feet is the longest distance from one visual connection to the next.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:20:33
      And the maximum height for the building, I guess if it's five stories is the maximum as I recall.
    • Kurt KeeseckerBRW Architects
    • 01:20:40
      I think the minimum height is two, the maximum I believe is four and you can get a special use permit or the county's equivalent to go up to six.
    • 01:20:50
      I'm sorry.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:20:50
      Okay.
    • 01:20:52
      So you could potentially have like a 400 foot long facade, 60, 70, 70.
    • 01:21:01
      I just want to look at the 20% factor.
    • Kurt KeeseckerBRW Architects
    • 01:21:10
      That's right.
    • 01:21:14
      By the math.
    • 01:21:15
      Yes.
    • 01:21:15
      OK.
    • Kurt KeeseckerBRW Architects
    • 01:21:16
      I'll hang out on the front.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:21:19
      OK, thank you.
    • 01:21:26
      So it'd be close to, I mean, the maximum envelope might be close to 30,000 square feet, is that right?
    • 01:21:30
      So you might be able to have like up to a 6,000 square foot barrel at 20%.
    • Chris HenningsenChair, Architectural Review Board
    • 01:21:39
      According to my calculation, so it'd be pretty big.
    • 01:21:42
      Pretty big.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:21:46
      Just wanted to contextualize it.
    • 01:21:49
      And I guess also from that discussion that the measure of a facade would be not necessarily
    • 01:21:56
      projections in plane, but a building mass or?
    • 01:21:59
      I'm sorry, I think there are requirements in the model code about how you have to have some articulation at twice the height.
    • 01:22:14
      So again, would any mural be assessed within like a zone of articulation or several zones of articulation would constitute a facade?
    • Margaret MaliszewskiPlanning Manager
    • 01:22:31
      I think that we would be looking when the buildings come in we would be looking at them individually and so whatever that building elevation is that's what we would be looking at in terms of the size and the percentage that would be used.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:22:58
      And I'm sorry, I guess the other question I recall in very early discussions about murals, some members of the board, I think myself included, expressed some headsy about having any role in reviewing murals to the extent that they are really not architecture, but are potentially art or expression.
    • 01:23:21
      Is it clear in what we're, is there some threshold where murals would be subject to our review?
    • 01:23:29
      Would we have criteria to use for them or is there, how would the board be instructed to review murals if we did indeed need to?
    • Margaret MaliszewskiPlanning Manager
    • 01:23:42
      These are all really good questions.
    • 01:23:46
      I think we'd be looking for your input as well on what criteria you would use if you were going to review them.
    • 01:23:57
      I think that
    • 01:24:01
      It's been expressed that the actual content of the mural is not something that you want to review, but we might be able to work through some additional criteria that would evaluate if the mural is somehow
    • 01:24:27
      impacting the architectural design.
    • 01:24:29
      I'm not sure what that would be.
    • 01:24:31
      We haven't had that discussion, but if that's something that you want to look into further, we can schedule that.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:24:41
      And murals currently, are they subject to any review or permitting or they're just sort of as a variety, if you've got a building, you can paint it?
    • Margaret MaliszewskiPlanning Manager
    • 01:24:52
      Well, in the entrance quarters, if it's a building that has a previous ARB action on it, you wouldn't be able to just paint a mural because the building would no longer be consistent with the ARB approval.
    • 01:25:09
      Other than that, I think as long as the mural can't be defined as a sign, then it can probably happen.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:25:22
      Thank you, sorry to introduce questions at the beginning.
    • 01:25:28
      It may be that if maybe there are murals and they do become subject to review in some ways that maybe the sign guidelines might present a template or an example to think about in terms of like approving sort of the area and the colors, but without approving the content.
    • 01:25:47
      Okay, well, thank you.
    • 01:25:49
      Appreciate you considering those questions.
    • Chris HenningsenChair, Architectural Review Board
    • 01:25:55
      And I guess, thank you, Dade, because I had a couple of questions that you actually covered in your question.
    • 01:26:05
      So I guess we'll start with Frank Hancock, if you have any comments or thoughts.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:26:13
      I don't really.
    • 01:26:14
      I mean, I think Dade's point is, what's our purview?
    • 01:26:21
      And then how do we evaluate it?
    • 01:26:24
      if it's not in the guidelines.
    • 01:26:27
      What's the action?
    • 01:26:31
      Are we just saying yay or nay on this percentage or this criteria for this countywide is to give the applicant guidance?
    • Margaret MaliszewskiPlanning Manager
    • 01:26:41
      Yeah, as I say, this is the last sort of issue to be resolved before we can approve the criteria for this development.
    • 01:26:51
      So yeah, we're trying to figure out
    • 01:26:54
      what the percentage is, if there is one, how you want to proceed on this issue.
    • 01:26:59
      And I think we probably should have a motion.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:27:03
      Did the applicant, is they incorporating murals into the project?
    • 01:27:15
      Is that the, or is this just in case this ever happens?
    • Margaret MaliszewskiPlanning Manager
    • 01:27:22
      I think there's sort of a general interest out there in being able to use murals.
    • 01:27:28
      I don't think, I haven't seen any specific designs or proposals yet.
    • Chris HenningsenChair, Architectural Review Board
    • 01:27:32
      Thank you.
    • 01:27:41
      Thanks, Dave.
    • 01:27:41
      Do you have any additional?
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:27:45
      No, thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:27:51
      Yeah, and I share some of the hesitancy about the thought of us reviewing mural content.
    • 01:28:04
      So it would really just be a matter of like, where is the mural?
    • 01:28:09
      How big is the mural?
    • 01:28:13
      How does it relate to other permanent elements of the building?
    • 01:28:22
      which is all a little bit in the absence of content or theoretically like knowing what is depicted in the mural.
    • 01:28:32
      It seems a little bit ambiguous.
    • 01:28:39
      I guess all that's to say that I'm okay with
    • 01:28:47
      but the applicants, you know how they've worded that restriction.
    • 01:28:57
      They're happy with it.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:29:05
      Yeah, I guess I wonder if we might say relative to ARB review required, if right now, at least I'm not comfortable adopting that we're required to review a mural, it might be easier at the moment just to say that
    • 01:29:18
      You know, murals up to X percentage of facades are permitted.
    • 01:29:23
      And then we might just ask that as a future work item or something, staff consider some, if it is necessary to think about taking on review of murals, staff developing some criteria and scope for those reviews and mural criteria that would be subject to our oversight.
    • 01:29:49
      There are certainly a lot of great examples in Crozet of murals that have been developed on existing buildings.
    • 01:29:57
      But in many cases, those are buildings that have some blankness that I think our own guidelines try to avoid.
    • 01:30:02
      So I think in some ways, what would be clearest to me and most consistent with the guidelines we operate under would be to, I think I'm comfortable personally with the idea of,
    • 01:30:16
      Facades not facing the EEC being quite free but it seems like it creates this whole other category to
    • 01:30:25
      When a lot of what we've been trying to do throughout the county is avoid blankness and create articulation and architecture.
    • 01:30:32
      I don't know exactly how murals on otherwise blank walls fit into that consistently, as much as they are a local vernacular part of the fabric in Crozet.
    • Chris HenningsenChair, Architectural Review Board
    • 01:30:52
      I guess I'm reassured it's not on here, but I recall seeing some language that murals are not a substitution for blankness requirements.
    • 01:31:09
      So I think if considering that that is already set forth as a requirement, then I guess
    • 01:31:22
      Whatever wall in question that would be receiving the mural necessarily would not have blankness in the first place.
    • Margaret MaliszewskiPlanning Manager
    • 01:31:33
      Sorry, if you were
    • 01:31:42
      Comfortable with the applicant's proposal enough to accept that today, we could continue to work on the more specific guidelines for ARB review of that category of murals that might come to view for review.
    • 01:31:59
      We wouldn't have to wait until the submittal comes in.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:32:05
      What if we just didn't do anything?
    • 01:32:07
      but if we just didn't do anything like if you know murals aren't in our purview you know I know the applicant's trying to get some certainty but by us saying we're gonna review something that's not in our purview might get us into more trouble of like you know and then we could be presented with something
    • 01:32:34
      that we weighed into something way outside of our purview.
    • 01:32:39
      I like it.
    • Margaret MaliszewskiPlanning Manager
    • 01:32:40
      So you're suggesting just take all of the language related to murals out of the proposal?
    • Frank HancockVice Chair, Architectural Review Board
    • 01:32:47
      I mean, unless there's something in the guidelines that really tells us how to review it and like, then it's, I mean, I know this is a county-wide certificate of appropriateness, so we're trying to get everything in here because we're not going to get the chance to review this.
    • 01:33:05
      But at the same time, how long have we operated without saying anything about murals?
    • 01:33:14
      And we haven't.
    • Margaret MaliszewskiPlanning Manager
    • 01:33:16
      Right.
    • 01:33:16
      But I do think that they've become more popular in recent years, and I think at some point
    • 01:33:24
      You're going to have to address it.
    • 01:33:29
      If all of this comes out of the proposal, then the site plans will come in and we'll review them and then at some point somebody's going to want to put a mural on one of those buildings and it'll bring it to you because the building would no longer be consistent with the previous approval and
    • Frank HancockVice Chair, Architectural Review Board
    • 01:33:54
      What happened to the Starbucks mural in 29?
    • 01:33:57
      Did they ever actually do a mural?
    • Margaret MaliszewskiPlanning Manager
    • 01:34:00
      No, they withdrew that idea because they wanted to get the project approved quickly and we were going to need a little more time to set up those guidelines.
    • Khris TaggartSenior Planner
    • 01:34:28
      I guess my thought would, I'm not a muralist, I'm saying myself, but the building design would likely, in my mind, dictate the design of a mural.
    • 01:34:39
      So the building would be designed, if the building is designed appropriately, the entrance quarter guidelines would have detailing that would likely limit the available space for a mural.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:34:52
      Exactly, like the window requirements.
    • Khris TaggartSenior Planner
    • 01:34:58
      There's probably instances you have painted there over a window, but I think in a new construction, it'd probably be less likely.
    • Margaret MaliszewskiPlanning Manager
    • 01:35:09
      That would be an example of one of the guidelines that could add.
    • 01:35:17
      No painting over windows or that sort of thing.
    • Khris TaggartSenior Planner
    • 01:35:31
      Is it a percentage or is it to be determined guidelines that would be better?
    • 01:35:40
      Vision just says ARB review is required if over a certain percentage, but I see larger murals being okay as long as they don't cover windows.
    • 01:35:54
      and any other architectural detailing that's not coming up to mind that shouldn't be obscured.
    • Chris HenningsenChair, Architectural Review Board
    • 01:36:01
      I guess just a clarification, this discussion just applies to the Barnes-Lumber project.
    • 01:36:16
      Aside from the general kind of consensus that we need a little bit more kind of
    • 01:36:23
      Come up with some kind of plan for murals like in the future.
    • 01:36:26
      Right.
    • Margaret MaliszewskiPlanning Manager
    • 01:36:27
      Yeah.
    • 01:36:28
      We're just trying to resolve this one issue for this for the criteria for the Barnes-Lumber development.
    • 01:36:36
      But yes, I think we'll have to look at it on a broader scale at some point.
    • Kurt KeeseckerBRW Architects
    • 01:36:51
      I have an idea.
    • 01:36:52
      I think I appreciate the idea that we want to make this more enforceable and understandable for future applicants.
    • 01:36:59
      That's the whole idea behind the county-wide certificate.
    • 01:37:03
      And I really appreciate the drive for clarity.
    • 01:37:10
      One idea, and I haven't spoken to our client about whether this would be acceptable or not, but one idea for making the enforcement of this language more easy would be that there are no murals on the facade facing the entrance corridor.
    • 01:37:27
      Whatever paint is applied to that facade in the future is just part of the architectural color scheme, which is somewhat of the entrance corridor review anyway.
    • 01:37:38
      It just happened on the,
    • 01:37:40
      Industrial building a second ago where we were asking about the shades of the color of the paint.
    • 01:37:46
      But murals would be allowed on the side streets, the side elevations without any regulation.
    • 01:37:52
      So that would maybe make it a little clearer and there would be no percentage triggering some kind of review of mural language that doesn't exist.
    • 01:38:01
      It's just essentially paint whatever you want to on the side elevations and have the one face in the corridor reviewed.
    • 01:38:09
      I don't, you know, we don't have any applications for specific buildings in mind.
    • 01:38:13
      There's no purchaser or anything that I know of.
    • 01:38:16
      And so I don't think anybody's trying to make a mural district.
    • 01:38:20
      It's just a way of making the Barnes-Lumber site interesting for folks that pass by.
    • 01:38:25
      And my 400 foot long dimension is from Centerline of Centerline, you know, so
    • 01:38:32
      I don't think anybody envisions a 400 foot long building that's not within character.
    • 01:38:38
      We're trying to break that down obviously, so if that helps.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:38:55
      Well, so maybe was the applicant just proposing basically keeping the bottom term about facades not facing the E.C.
    • 01:39:03
      street and striking the two above?
    • Charlie ArmstrongVice President of Land Development
    • 01:39:05
      Yes.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:39:06
      OK. That would work for me and then we have more time to come up with criteria if they're ultimately necessary.
    • Chris HenningsenChair, Architectural Review Board
    • 01:39:23
      I'm comfortable with that also.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:39:26
      Yeah, I don't think we need to say that.
    • 01:39:40
      But if we did, I mean, I think that's kind of how it is now.
    • 01:39:43
      Right?
    • 01:39:44
      Like, someone did a mural on
    • 01:39:48
      If someone did a big mural in Crozet that had peaches and said Crozet, like it didn't come to us, it's there.
    • 01:39:58
      Everyone likes it.
    • Chris HenningsenChair, Architectural Review Board
    • 01:40:03
      I'm okay with this.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:40:04
      I don't want to like set us up for how do we review it then and, you know,
    • 01:40:12
      I just feel like if you start putting 20% and what's visible and what's not, then like we haven't done the pre-work to be able to do any of that.
    • 01:40:24
      I feel like otherwise, and we would then be the art and architecture review board, which is what the state has.
    • 01:40:32
      And we're not that.
    • 01:40:35
      We would need our DHR representative.
    • 01:40:37
      We would, we would need an artist.
    • 01:40:40
      to expand the membership.
    • Margaret MaliszewskiPlanning Manager
    • 01:40:43
      So just make sure I understand what you just said.
    • 01:40:50
      You support the applicant's revised proposal to just have murals occupying the side elevations not facing the entrance quarter street, and that would be exempt from Airbnb review.
    • 01:41:02
      And that would be the extent of the mural proposal.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:41:05
      Yeah, my hunch is that there's nothing restricting them from doing that now.
    • 01:41:09
      I guess we're writing this specific code for this development, but... Well, there would... Generally speaking in the county, couldn't anyone do that?
    • Margaret MaliszewskiPlanning Manager
    • 01:41:23
      Except for the reasons that we...
    • 01:41:25
      There's a building that has an A or B action on it that did not
    • 01:41:31
      Allow for a mural and it could not be done without your approval because it would be a change to the ARB approved design.
    • 01:41:41
      And so without any of this in the county-wide criteria, we would just be approving the architectural design.
    • 01:41:53
      Staff would not feel comfortable approving a mural
    • Frank HancockVice Chair, Architectural Review Board
    • 01:42:01
      Maybe I misunderstood.
    • 01:42:02
      So the mural I described, yes, that building doesn't have an ARB action on it.
    • 01:42:09
      It predates the corridor.
    • Margaret MaliszewskiPlanning Manager
    • 01:42:11
      I cannot explain the three of that.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:42:19
      But that is in my head because that is, you know, textually relevant.
    • 01:42:28
      But
    • 01:42:30
      Yeah, I would be okay with this bottom.
    • 01:42:38
      I don't want to be anti-mural.
    • 01:42:40
      I don't want to be seen as anti-mural.
    • Khris TaggartSenior Planner
    • 01:42:43
      To Frank's point, though,
    • 01:42:45
      I think what Frank's point is, besides not facing the entrance quarter street, regardless if they had ARB review, they would still be able to put a mural on it, it's not facing, but would we still just need to look at it and say it's not visible from the entrance quarter, even if it had ARB review?
    • Margaret MaliszewskiPlanning Manager
    • 01:43:10
      So the way I envision this working is that the applicant makes a proposal for a building.
    • 01:43:17
      It's got a site plan and it's got an architectural design and it's an application for a county-wide certificate under this particular category.
    • 01:43:29
      And so it's a new building.
    • 01:43:31
      So there's, you know, it doesn't, I don't,
    • 01:43:40
      If an existing building comes in under that for a change, I suppose, I guess that could happen too.
    • Kurt KeeseckerBRW Architects
    • 01:43:53
      I'm following your example and trying to think through the scenarios that would unfold.
    • 01:43:58
      So in a new building, somebody comes along and I think what we've realized all along is that staff can ask for any application under the countywide to be reviewed by the board.
    • 01:44:10
      So if an applicant came forward with a building that had some kind of architectural and
    • 01:44:16
      painted facade that staff rendered uncomfortable at that time they could put it before the board facing the corridor but if they came forward with an application that had a paint scheme that was on the side elevations not facing the corridor even if it made staff uncomfortable they couldn't ask the board to review it and so and if an applicant came forward with a paint scheme facing the
    • 01:44:43
      Entrance corridor that staff deemed reasonable under whatever criteria, whether it's a mural or not, just as part of the design, they could say okay to that application under the countywide, correct?
    • 01:44:59
      So this is really just a triggering mechanism for what kind of paint scheme facing the corridor needs to be reviewed by the board.
    • 01:45:08
      Is that what we're after?
    • Margaret MaliszewskiPlanning Manager
    • 01:45:11
      I would expect an application coming in under this category of countywide certificate to not propose a mural on the entrance corridor facing elevation.
    • Kurt KeeseckerBRW Architects
    • 01:45:22
      Right.
    • 01:45:23
      And the definition of the mural is hard to put your finger on because it has images or stripes or all kinds of different patterns.
    • 01:45:32
      You know, it could be Argyle, who knows?
    • 01:45:34
      But at some point that's going to
    • 01:45:37
      be uncomfortable at some point, and there's gonna have to be consensus around what's acceptable on a new building, but you'd have to deal with that on any new building in the county entrance quarters now, regardless of county-wide or not.
    • 01:45:55
      So it does seem that the 20% criteria seems, in language here, seems to confuse things.
    • 01:46:00
      It'd either be on or off, and you know,
    • 01:46:06
      Let the artists have a great time on the side walls and the ones that face the corridor may require more scrutiny depending on what's presented, who knows what it'll be in the future.
    • 01:46:18
      But the idea was there'd be some flexibility for creativity that could be applied.
    • 01:46:24
      So that's all.
    • 01:46:27
      Thanks.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:46:29
      Isn't the goal of the countywide so the applicant doesn't have to come back to the ARB a lot and then it's administratively as long as it meets the countywide, the guidelines?
    • Margaret MaliszewskiPlanning Manager
    • 01:46:43
      Yes.
    • Kurt KeeseckerBRW Architects
    • 01:46:50
      But I think it has to meet the guidelines at the time that the application comes forward.
    • 01:46:54
      So if the guidelines change in the future and there is more
    • 01:46:59
      guidance to staff on murals or whatever you want to call it in the future, you'd be able to apply that, you and the staff would be able to apply that review at the countywide level at that time.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:47:11
      Or is it based on like the code, is code of development the right word?
    • 01:47:19
      It's not based on all of the planning work that we've met on multiple times.
    • 01:47:23
      It's based on the entrance corridor guidelines as they adapt or if they adapt.
    • Margaret MaliszewskiPlanning Manager
    • 01:47:30
      So an application comes in under any of the categories of countywide certificate.
    • 01:47:37
      When those plans come in, we review those plans against the approved countywide criteria.
    • 01:47:46
      So there'll be a table.
    • Frank HancockVice Chair, Architectural Review Board
    • 01:47:48
      Like this specific plan, like the Barnes-Lumber countywide certificate of appropriateness.
    • 01:47:56
      Criteria, yep.
    • 01:47:57
      Or criteria.
    • Kurt KeeseckerBRW Architects
    • 01:48:17
      It's fascinating, really.
    • Margaret MaliszewskiPlanning Manager
    • 01:48:26
      All right, it's taking me a minute to.
    • 01:49:07
      So this is a draft of the sort of thing that we would use to review a proposal that's submitted.
    • 01:49:21
      This just summarizes what the criteria are, and we just use it as a checklist.
    • 01:49:26
      Is the first thing done?
    • 01:49:28
      Is the second one done?
    • 01:49:29
      Is the third one done?
    • 01:49:30
      If not, then we work with the applicant to get the proposal to meet the criteria listed here.
    • Kurt KeeseckerBRW Architects
    • 01:49:42
      And I guess for some reason the applicant doesn't feel like they can fall within those criteria.
    • 01:49:49
      They could just come to the board with your help, with staff help, you know, just make a full application.
    • 01:49:55
      So it gives you that kind of consistency of, you know, applying the county wide criteria and having a more direct line for certificate of appropriateness.
    • 01:50:05
      But otherwise, if it gets complicated, you can come to the board and have the public discussion.
    • 01:50:14
      which seems very fair.
    • 01:50:18
      Sit down.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:50:52
      Sorry, the red text today would be updated just to say not facing an entrance corridor.
    • Chris HenningsenChair, Architectural Review Board
    • 01:51:47
      That looks good to me.
    • Margaret MaliszewskiPlanning Manager
    • 01:51:57
      It would be good to have a motion to approve that mural criteria as amended today.
    • Chris HenningsenChair, Architectural Review Board
    • 01:52:11
      I'll move to approve as amended.
    • 01:52:14
      I'll second.
    • 01:52:18
      All right, if we could put that to a vote.
    • SPEAKER_04
    • 01:52:22
      Okay, Mr. Van Der Werf?
    • Chris HenningsenChair, Architectural Review Board
    • 01:52:24
      Aye.
    • SPEAKER_04
    • 01:52:25
      Mr. Matsuno?
    • 01:52:29
      Aye.
    • 01:52:31
      Mr. Stoner?
    • Frank StonerMember, Architectural Review Board
    • 01:52:32
      Abstain.
    • SPEAKER_04
    • 01:52:32
      Abstain.
    • 01:52:33
      Mr. Hancock.
    • Frank StonerMember, Architectural Review Board
    • 01:52:35
      Aye.
    • SPEAKER_04
    • 01:52:35
      And Mr. Henningsen.
    • Frank StonerMember, Architectural Review Board
    • 01:52:37
      Aye.
    • SPEAKER_04
    • 01:52:38
      I just wanted to make sure I had it right.
    • 01:52:39
      I had it written down, but I was like, did I really get right?
    • Frank HancockVice Chair, Architectural Review Board
    • 01:52:42
      I forgot.
    • 01:52:42
      You were abstaining.
    • 01:52:43
      I kept looking at Tara.
    • 01:52:44
      I was like, I almost said, are you getting away, Tara?
    • 01:52:47
      It's so long ago.
    • Chris HenningsenChair, Architectural Review Board
    • 01:52:52
      All right.
    • 01:52:54
      Well, we're moving to other business.
    • 01:52:58
      First is
    • 01:52:59
      Approval of the August 4, 2025 minutes.
    • 01:53:04
      I was not there at the meeting, but I felt like I was after reading those minutes.
    • 01:53:13
      So I'll move to approve.
    • 01:53:16
      I'll second.
    • 01:53:19
      If we could put that to a vote.
    • SPEAKER_04
    • 01:53:21
      Mr. Van Der Werf?
    • Chris HenningsenChair, Architectural Review Board
    • 01:53:23
      Aye.
    • SPEAKER_04
    • 01:53:23
      Mr. Matsuno?
    • Chris HenningsenChair, Architectural Review Board
    • 01:53:25
      Aye.
    • SPEAKER_04
    • 01:53:25
      Mr. Stoner?
    • Chris HenningsenChair, Architectural Review Board
    • 01:53:26
      Aye.
    • SPEAKER_04
    • 01:53:27
      Mr. Hancock?
    • 01:53:28
      Aye.
    • 01:53:28
      Mr. Henningsen?
    • Chris HenningsenChair, Architectural Review Board
    • 01:53:29
      Aye.
    • SPEAKER_04
    • 01:53:30
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:53:30
      All right, thank you.
    • 01:53:32
      So the next ARB meeting is scheduled for Tuesday, September 2nd, 2025.
    • 01:53:41
      Do we have any members who know or think they may not be able to attend?
    • Frank HancockVice Chair, Architectural Review Board
    • 01:53:49
      All right.
    • 01:53:50
      I'm planning to attend.
    • Chris HenningsenChair, Architectural Review Board
    • 01:53:52
      I plan to attend.
    • 01:53:55
      I believe I can attend.
    • 01:53:58
      All right.
    • 01:53:58
      So as far as we know right now, we'll have a quorum.
    • 01:54:02
      So this concludes the August 18th meeting of the Albemarle County ARB.