Architectural Review Board Meeting   11/20/2023

Attachments
  • Final Agenda.pdf
  • Final Action Memo.pdf
  • Final ARB Action Memo Minutes.pdf
  • ARB202300092 Dunlora Park Staff Report.pdf
  • Attach. 1 ARB2023-92 - Elevations and Exterior Selections for Lots 29-31.pdf
  • Attach. 2 ARB2023-92 - Elevations, Floor Plans, and Structure Plans for Lots 29-31.pdf
  • Attach. 3 ARB2023-92 - Poplar I Architecture Plans.pdf
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:00:27
      Take two.
    • Chris HenningsenChair, Architectural Review Board
    • 00:00:33
      It is 1-0-1 and I'm calling the November 20th, 2023 meeting of the Albemarle County Architecture Review Board to order.
    • 00:00:46
      Could we call the roll, please?
    • SPEAKER_01
    • 00:00:50
      Mr. Stoner.
    • 00:00:51
      Here.
    • 00:00:52
      Mr. Matsuno.
    • Chris HenningsenChair, Architectural Review Board
    • 00:00:54
      Here.
    • SPEAKER_01
    • 00:00:54
      Mr. Van Der Werf?
    • Chris HenningsenChair, Architectural Review Board
    • 00:00:55
      Here.
    • SPEAKER_01
    • 00:00:56
      Mr. Henningsen?
    • Chris HenningsenChair, Architectural Review Board
    • 00:00:57
      Here.
    • SPEAKER_01
    • 00:00:58
      And Mr. Hancock is absent.
    • 00:01:00
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 00:01:01
      All right.
    • 00:01:01
      Thanks a lot.
    • 00:01:03
      Today's meeting is a hybrid meeting.
    • 00:01:05
      The public may access and participate in the meeting electronically.
    • 00:01:10
      Instructions for doing so are posted on the Albemarle County calendar website at the Albemarle County calendar.
    • 00:01:17
      The public has real-time audiovisual access to this meeting over Zoom and real-time audio access over telephone.
    • 00:01:24
      Both is provided in the lawfully posted meeting notice.
    • 00:01:28
      This meeting is being recorded and will be made available on the county's website.
    • 00:01:33
      This meeting is a public record and subject to disclosure under the Freedom of Information Act.
    • 00:01:40
      All speakers, when it is your turn to speak, please first state your name for the record.
    • 00:01:46
      Applicants who are making presentations, note that your presentation is limited to a total of 15 minutes, which you can divide among your team members.
    • 00:01:55
      Staff will let us know when the 15 minutes are up.
    • 00:01:58
      If applicants in the meeting room have team members attending virtually who will need to present, please make that known when you come to the podium.
    • 00:02:07
      Everyone who is participating virtually, please mute your microphone until it is your turn to speak.
    • 00:02:14
      Do any ARB members have anything to disclose?
    • 00:02:19
      No.
    • 00:02:21
      I do have a scheduling item.
    • 00:02:25
      In the event that we're still going at 2.40 p.m., I will have to leave and we'll hand the reins over to Dade and hopefully that won't happen and will be done before then.
    • 00:02:46
      Are there any members of the public that want to make a comment about a project that is not on the agenda for review?
    • 00:02:53
      All right, great.
    • 00:02:59
      We do not have any consent agenda items today.
    • 00:03:03
      So we will move on to our regular review item.
    • 00:03:08
      There is one and it is ARB-2023-92, Dunlora Park Phase 2.
    • 00:03:17
      Mariah, do you have your presentation?
    • Mariah GleasonUrban Designer
    • 00:03:20
      Yes.
    • 00:03:21
      Good afternoon.
    • 00:03:22
      My name is Mariah Gleason.
    • 00:03:23
      I'm a Senior Planner II in the Planning Division of Community Development.
    • 00:03:29
      Today I'm going to be presenting ARB 2023-92 Dunlora Park Phase 2 Townhomes.
    • 00:03:36
      This project is, or this is a first review of the architectural designs.
    • 00:03:43
      The proposal requires ARB review due to its proximity to the Rio Road East and John Warner Parkway entrance corridors, symbolized in the orange arrow.
    • 00:03:53
      The subject property, shown in red, is comprised of three platted and graded townhouse lots located at the southeast corner of the intersection of Dunlora Drive and Varick Street, approximately 280 feet from Rio Road.
    • 00:04:06
      East entrance corridor.
    • 00:04:08
      The townhouses are part of a 34-unit residential development known as Dunlora Park.
    • 00:04:13
      Residences within the development are typically two to three stories, single-family attached and detached units.
    • 00:04:20
      Dunlora Park is surrounded by other residential developments to the north, east, south, and KTEC is located west of the site.
    • 00:04:27
      The subject property is separated from Rio Road East and John Warner Parkway entrance corridors by two parcels that contain a multi-use path and are planted with various trees and grasses.
    • 00:04:38
      That block, shown in white, contains a grassy berm at its southern end in a sunken central area towards the middle and northern end.
    • 00:04:49
      These images were taken from the entrance corridors to understand the expected visibility of the site.
    • 00:04:54
      What they show are that the townhouses, particularly the western elevation of Lot 31, located closest to the entrance corridors, identified with a star, will be visible from the Rile Road East entrance corridor.
    • 00:05:05
      Due to the topography of the planted block, only the upper stories and roof lines of the townhouses are expected to be visible from the Parkway entrance corridor.
    • 00:05:17
      The site plan for the three townhouses was approved under the Dunlora Park phase two site plan, which was later amended by a major site plan amendment.
    • 00:05:28
      The proposed architecture of lots 29 through 31 is generally compatible with the characteristics of existing units.
    • 00:05:36
      These images demonstrate the proposed architectural features, colors, and materials.
    • 00:05:44
      The primary issue staff found in the report is the design of the west elevation of Lot 31, which is expected to be most noticeable and visible from the entrance corridor.
    • 00:05:57
      This elevation uses arctic white siding, which will draw attention to the unit, and the elevation is mostly blank.
    • 00:06:05
      Other minor issues included needing additional labels on the material selections document, confirming window glass material and the location and screening of mechanical equipment.
    • 00:06:17
      This is the full set of recommendations and recommended points of discussion.
    • 00:06:21
      Are there any questions about the report or presentation I can clarify for the board?
    • Chris HenningsenChair, Architectural Review Board
    • 00:06:28
      All right.
    • 00:06:28
      Well, thanks a lot for the presentation.
    • 00:06:33
      I'll just roll through and see if there are any questions.
    • 00:06:36
      Tara, do you have any?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:06:38
      No.
    • 00:06:38
      No questions.
    • Chris HenningsenChair, Architectural Review Board
    • 00:06:39
      Dave?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:06:40
      No questions.
    • 00:06:41
      Thanks, Marat.
    • Chris HenningsenChair, Architectural Review Board
    • 00:06:42
      Frank?
    • Frank StonerMember, Architectural Review Board
    • 00:06:43
      No, none for me either.
    • Chris HenningsenChair, Architectural Review Board
    • 00:06:44
      And I don't have any questions either.
    • 00:06:47
      Thanks.
    • 00:06:50
      So the applicant is here and has a presentation.
    • 00:06:55
      Now would be the time.
    • SPEAKER_08
    • 00:07:03
      Thank you.
    • 00:07:04
      I'm Chris Schooley with Greenwood Holmes.
    • 00:07:06
      We don't have a presentation, but we just have any questions.
    • 00:07:11
      It seemed like reasonable recommendations for us.
    • 00:07:17
      Sure, I'm never too quiet, so try to be louder.
    • 00:07:24
      You can only see the top half.
    • 00:07:26
      We usually surround the mechanical equipment anyway with a fence, so that's not a big deal.
    • 00:07:31
      We would just ask with some flexibility that kind of moves a little bit on the side of the house, depending on where it fits the best of the house.
    • 00:07:38
      I think other than that, probably landscaping is the best solution for that side, and we don't mind moving the arctic white to a different one of the three townhouses or not using it altogether.
    • 00:07:49
      I think that was it.
    • 00:07:51
      Was there anything else?
    • 00:07:52
      Ms. Cleason, you need the cover?
    • Mariah GleasonUrban Designer
    • 00:07:56
      The window glass.
    • SPEAKER_08
    • 00:08:00
      Yeah, what was the issue with the window glass?
    • Mariah GleasonUrban Designer
    • 00:08:03
      Making sure it's not highly reflective or tinted.
    • SPEAKER_08
    • 00:08:07
      Okay, yeah.
    • 00:08:08
      The only issue we had that we talked about was that we black out the dormer windows, but that's on the front, so you couldn't see that anyway.
    • 00:08:15
      Otherwise it would be standard windows.
    • Chris HenningsenChair, Architectural Review Board
    • 00:08:21
      All right, I guess we'll just see if any board members have any questions.
    • 00:08:25
      Frank, do you have any questions?
    • Frank StonerMember, Architectural Review Board
    • 00:08:27
      I don't think I do, no.
    • Chris HenningsenChair, Architectural Review Board
    • 00:08:30
      Great.
    • Taro MatsunoMember, Architectural Review Board
    • 00:08:30
      Dade?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:08:31
      None for me, thanks.
    • Taro MatsunoMember, Architectural Review Board
    • 00:08:33
      Tara?
    • 00:08:34
      No, thank you, sir.
    • 00:08:35
      Clarifying, appreciate it.
    • 00:08:37
      Thank you.
    • 00:08:38
      Thanks a lot.
    • Chris HenningsenChair, Architectural Review Board
    • 00:08:41
      All right, are there any members of the public that want to comment?
    • 00:08:48
      All right.
    • 00:08:49
      So the ARB will now go into discussion.
    • 00:08:52
      I guess, Dade, do you have any comments?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:08:56
      No further ones.
    • 00:08:56
      Appreciate Mariah's good report and the applicant's willingness to incorporate the staff comments.
    • 00:09:01
      So thank you.
    • 00:09:02
      All right.
    • 00:09:03
      Thanks.
    • 00:09:03
      Tara?
    • Taro MatsunoMember, Architectural Review Board
    • 00:09:04
      Same here.
    • 00:09:05
      Thank you very much.
    • 00:09:05
      Thanks.
    • 00:09:07
      Frank?
    • Frank StonerMember, Architectural Review Board
    • 00:09:09
      Yeah, I think the only question I'd have really relates to the compatibility of the architecture proposed in the new building with what's in the neighborhood is it's kind of a unified concept through there.
    • 00:09:22
      I don't know if probably should ask that of the applicant, but did you guys maybe outside or a purview as well?
    • 00:09:30
      So because it's not visible.
    • Mariah GleasonUrban Designer
    • 00:09:37
      So this group of images was taken from a visit to the site and demonstrates the design character of the existing residential units within the development.
    • 00:09:47
      Overall, there is strong consistency between the units.
    • 00:09:50
      They use lap siding, muted earth colors and gabled roofs, dormer windows, and
    • 00:10:01
      Porch Accents, these townhouses are on noticeably smaller lots and due to the visibility of what you would see from
    • 00:10:09
      The distance from the entrance corridor, how much would really be visible, we thought that the architecture proposed is in the same family and consistent that way.
    • 00:10:23
      But they will look different.
    • 00:10:25
      They are townhouses versus a larger lot size for single family attached, detached.
    • Frank StonerMember, Architectural Review Board
    • 00:10:34
      OK, thanks.
    • 00:10:36
      All right, thanks.
    • Chris HenningsenChair, Architectural Review Board
    • 00:10:38
      I guess I kind of share a Dade's opinion that the staff comments seem reasonable and since the applicant seemed to think they were reasonable too, I don't really have anything to add so I guess we could take a look at the motion just to see if anybody has any adjustments.
    • 00:11:23
      Well, let me ask before we even look at it, does anyone have any adjustments that they would like to make or think they may have any adjustments?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:11:33
      I don't have any to the staff comments.
    • 00:11:34
      I don't know whether the motion allows for administrative staff approval.
    • 00:11:39
      Personally, I don't see a need to see the application again if staff is satisfied with how those are incorporated.
    • 00:11:46
      I agree with that.
    • Frank StonerMember, Architectural Review Board
    • 00:11:47
      I would agree.
    • Margaret MaliszewskiPlanning Manager
    • 00:12:01
      said, but I think you said you were fine with that.
    • Chris HenningsenChair, Architectural Review Board
    • 00:12:05
      Yeah, it didn't sound like anyone had any tweaks.
    • 00:12:10
      And I think generally, we'd be okay with staff approval after this point.
    • Margaret MaliszewskiPlanning Manager
    • 00:12:22
      So in that case, our recommended motion is for approval with the conditions listed in the staff report.
    • Chris HenningsenChair, Architectural Review Board
    • 00:12:31
      Anybody want to make a motion?
    • Frank StonerMember, Architectural Review Board
    • 00:12:34
      I'll move that we approve the proposal with conditions listed in the staff report with no amendments.
    • Chris HenningsenChair, Architectural Review Board
    • 00:12:43
      I'll second.
    • 00:12:45
      Alright, thanks.
    • SPEAKER_01
    • 00:12:49
      Mr. Van Der Werf?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:12:50
      Aye.
    • SPEAKER_01
    • 00:12:51
      Mr. Hank?
    • 00:12:52
      Mr. Stoner?
    • 00:12:53
      Aye.
    • 00:12:54
      Mr. Matsuno?
    • 00:12:55
      Aye.
    • 00:12:56
      Mr. Van Der Werf?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:12:58
      Aye.
    • SPEAKER_01
    • 00:12:58
      Thank you.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:13:00
      Henningsen.
    • Margaret MaliszewskiPlanning Manager
    • 00:13:03
      And I'm sorry, who was the second?
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:13:05
      I got two votes.
    • Chris HenningsenChair, Architectural Review Board
    • 00:13:08
      Alright, thanks a lot.
    • 00:13:30
      All right, so we have two work sessions today.
    • 00:13:33
      The first is a discussion with Bob Pinnio of Design Develop on the process for creating images submitted to ARB Review.
    • Margaret MaliszewskiPlanning Manager
    • 00:13:42
      I'm going to pull up that presentation.
    • Bob PineoPrincipal
    • 00:14:00
      like some old friends out there.
    • Margaret MaliszewskiPlanning Manager
    • 00:14:20
      Good.
    • 00:14:21
      So I think it was back in September, maybe August, the board discussed, looked at some images, sort of before and after images of the Presidio project.
    • 00:14:33
      And we've been working with the applicants to sort of figure out what happened between
    • 00:14:56
      Sorry about that while we get that fixed.
    • 00:14:58
      So we had discussed the befores and afters and working with the applicant to sort of bring some greater explanation of that for you.
    • 00:15:07
      And so that's why Bob's here today.
    • 00:15:08
      And he's going to give us some some extra background and detail on that.
    • Bob PineoPrincipal
    • 00:15:16
      Thank you so much for your time.
    • 00:15:18
      So this is a, we went through the kind of some of the specifics, which I'm more than happy to do.
    • 00:15:25
      I wanted to give you a deeper view into some of the things that we're doing as a workflow process, just so you understand the context of it.
    • 00:15:34
      And then we can get into the specifics about working with Margaret.
    • 00:15:38
      We've been in front of the board a lot over the years and just from a, I find that the 3D world or the technology associated with three-dimensional workflows are advancing at a pretty fast rate.
    • 00:15:54
      We've always been trying to be at the cutting edge of that.
    • 00:15:57
      and so this is a quick hopefully you won't find this too boring but a little bit about us a little bit about the work that we've been doing for the last almost 20 years here that's associated with three-dimensional
    • 00:16:11
      perspectival images and how where we came to is specifically with Presidio but also as a bigger item when you see three-dimensional items before you, what is the standard, where did they come from,
    • 00:16:29
      How were they produced?
    • 00:16:31
      What was the intention behind them?
    • 00:16:33
      I think that's a bigger review.
    • 00:16:36
      So kind of philosophically, where does this stuff come from?
    • 00:16:40
      Where's the technology heading?
    • 00:16:41
      There are new advances in technology that make my job even easier.
    • 00:16:46
      So our job at design development, the design community.
    • 00:16:51
      So basically,
    • 00:16:53
      I hope this is not too boring, but I just want to give you a background.
    • 00:16:58
      Using technology to tell more compelling and accurate stories.
    • 00:17:01
      That's what we try to do on a day-to-day basis.
    • 00:17:05
      We have two teams, one in Baltimore, one in Charlottesville.
    • 00:17:08
      We're using, there's little white figures behind, because we've added three to our staff.
    • 00:17:13
      But we've been around since 2006, 2007.
    • 00:17:17
      Go to the next slide.
    • 00:17:21
      So this is the partnership.
    • 00:17:24
      We have 11 people.
    • 00:17:26
      And that's me and the studio director for Charlottesville, Kevin Shaffer, which he's presenting in front of you all the time, and our Baltimore studio head, Kanyu Wang.
    • 00:17:39
      So technology and workflow.
    • 00:17:42
      I'm going to kind of break this down into three things.
    • 00:17:49
      The world is changing relative to how we capture and design buildings three-dimensionally, how we capture and work with topography and tree canopies, and the next thing is 3D point cloud scan technology that we have incorporated into our business.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:18:09
      Something happened there with this slide.
    • Bob PineoPrincipal
    • 00:18:11
      So this is the reason we love three-dimensional work.
    • 00:18:16
      I'll get into that in a second.
    • 00:18:18
      But it's really about synthesizing all of the constraints of any of our projects, being able to talk about those constraints, how they influence design, how the client can participate in the resolution of those, and then presentation.
    • 00:18:34
      So presentation, when we come to you, it's towards the latter part of that discussion.
    • 00:18:39
      What do you want, client?
    • 00:18:40
      How does it look?
    • 00:18:41
      How does it fit in the context?
    • 00:18:43
      So we're presenting images not really just for you, but these are at the end of our design process and now architectural review, BAR review, things like that.
    • 00:18:55
      So this is a quick story.
    • 00:18:56
      This is my 2004 aha moment.
    • 00:18:58
      I was designing a building for a couple.
    • 00:19:01
      And after about an hour and a half of looking through the elevations and the sections, a client turns to me and points to the door and says, what is that?
    • 00:19:09
      It points to the door signal symbol.
    • 00:19:13
      Go to the next slide.
    • 00:19:14
      And goes, what is that?
    • 00:19:16
      You can go one more.
    • 00:19:17
      And that's a door symbol.
    • 00:19:18
      But for people that they're a very smart couple, they just didn't know the language of architecture.
    • 00:19:25
      The language of site design, the language of architecture, everybody's got their own kind of slant on how they present things, but a lot of times it doesn't mean anything to somebody else because it's kind of my language or the site plan or a civil engineer, a mechanical engineer.
    • 00:19:42
      They convey information, but a lot of times to somebody who doesn't understand them, it's more confusing than not.
    • 00:19:49
      This particular couple an hour to talk about their confusion.
    • 00:19:54
      My job is to give them what they want, and I'm talking a language they don't understand.
    • 00:19:59
      So we're born into a three-dimensional perspectival world when it comes to talking about what we want, or as a community, in this case, what's acceptable.
    • 00:20:11
      Talking in a language that everybody understands seems like a very natural progression of thought and technology.
    • 00:20:21
      So my journey with this came from the Boston area, came down here, quickly met Brian Wheeler from Charlottesville Tomorrow.
    • 00:20:30
      And I was kind of telling him about this, how the process of debate on a community level with built structures is kind of confusing.
    • 00:20:42
      And he showed me, he goes, well, the Ragon Mountain Dam project was happening at that point.
    • 00:20:48
      And he showed me an eight and a half by 11 sheet of a section through the dam.
    • 00:20:53
      And to me, it looked like, well, that's no big deal until I found out every half inch was 100 feet.
    • 00:20:58
      So being able to scale that drawing or scale that so that the community could understand what was coming, we started thinking about what's something that somebody knows that's in the community.
    • 00:21:09
      They know the rotunda.
    • 00:21:11
      They know how big it is.
    • 00:21:12
      Well, this is three rotundas with all of its side buildings right next to each other.
    • 00:21:16
      And there's still room for more.
    • 00:21:18
      So it was kind of this beginning of helping the community understand visually the things that were coming and democratizing these things so that they're perspectival, scaled, shade shadow, texture.
    • 00:21:34
      You can go on to the next slide.
    • 00:21:36
      So we started doing a lot of things with Charlottesville Tomorrow when Brian was there.
    • 00:21:42
      We started doing something, The Restoring Station, which was a Joe Higgins project on 29th, very controversial for whatever reason.
    • 00:21:51
      Well, we showed the plans in context at scale and you could see it from the entrance border.
    • 00:21:58
      So the whole idea of visualizing where you were at specific points was an easy thing to do from a technological standpoint.
    • 00:22:07
      We also worked with him to, and you can click onto the Western Bypass.
    • 00:22:13
      So at the time the Western Bypass was, you know, happening and nobody knew about it.
    • 00:22:18
      Again, these kind of
    • 00:22:20
      drawings that were very hard to stitch together and to understand.
    • 00:22:25
      So we modeled everything three dimensionally with Google Maps.
    • 00:22:31
      And I'll get into that in a second.
    • 00:22:32
      But Google Maps brings to scale drawings with photorealistic material with it, topography.
    • 00:22:42
      So we overlaid the plan of
    • 00:22:45
      The Western Bypass onto that, showed vignettes of it, tried to let everybody understand what the context, you could blow little sections up where there was complexity.
    • 00:22:57
      So that was the Western Bypass project.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:23:06
      Go back to that presentation.
    • Bob PineoPrincipal
    • 00:23:11
      I think see how, yeah, right there, that's good.
    • 00:23:13
      So we did that.
    • 00:23:15
      That was very well received and people printing it out and as on a public forum, people could now understand it a little bit better.
    • 00:23:24
      Next slide.
    • 00:23:26
      We also did something for the Southern Environmental Law Center.
    • 00:23:30
      This was called Let's Go 29.
    • 00:23:32
      You can click on that.
    • 00:23:33
      This is a video.
    • 00:23:34
      It's kind of not photorealistic.
    • 00:23:37
      And this is one portion of it trying to describe how traffic flows might work and this spooey.
    • 00:23:43
      which was going to happen which hasn't happened yet but letting trying to give somebody graphic sensibility of what's happening and why and in this case we were trying to tell a story so this was narrated you can't hear that this was a while ago technology has changed a lot since then we were stitching together a lot of nascent workflow
    • 00:24:08
      but again, telling stories, trying to be more accurate with them, trying to be descriptive of what's happening.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:24:18
      Okay, next slide.
    • Bob PineoPrincipal
    • 00:24:22
      Most recently, we did the Rivanna Station for the county and this was all about visualizing this tract of land that I think it should be a video that loads.
    • 00:24:35
      but again using the same kind of technology, the Google Maps, the site plan that was given to us, a little bit of invention when it came to.
    • 00:24:47
      I think if you accept all, it should be an animation that runs or maybe it's loading.
    • 00:24:54
      Oh yeah, maybe in that bottom left-hand corner.
    • 00:24:58
      So this is all about storytelling and with accuracy.
    • 00:25:04
      It's not down to the,
    • 00:25:05
      Foote, but it's down to the, you know, as far as the information that's readily available to us.
    • 00:25:12
      So topography, the building form, some existing parking, others that has been, you know, other building form and site plans that were really depicted, you know, a kind of rudimentary
    • 00:25:26
      but we were able to model those things and again trying to tell a story of what could be coming.
    • 00:25:34
      So this was successful in that the county had a vision that they could let everybody see, anybody who can see and see things visually, three-dimensional, perspectival and shade, shadow but also scale.
    • 00:25:50
      So what's this whole thing look like?
    • 00:25:52
      What are certain parts of it look like?
    • 00:25:54
      and as a community we can debate whether we want them or not want them, but this is hopefully a true version, an accurate version of what was being debated.
    • 00:26:15
      Next slide.
    • 00:26:17
      and our own work in front of, I've just got some examples of ARB work, but we also do a lot of work in the city.
    • 00:26:26
      Subaru, we just finished that, Region 10 Women's Shelter, that was four or five years ago.
    • 00:26:31
      We're open, you can see on the bottom right-hand side, all the IV proper to go through a couple, Presidio is on there.
    • 00:26:40
      We'll probably go back, actually, why don't you go on that?
    • 00:26:43
      And then we can come back.
    • 00:26:45
      and if you don't mind, go to ARB images.
    • 00:26:52
      So, and you can just kind of click through any one of those.
    • 00:26:58
      This was, that's the Monticello.
    • 00:27:01
      So again, seeing what Monticello, you know, what was the impact from Monticello standpoint.
    • 00:27:09
      But this is a good image to start with because this is where the images in question came from.
    • 00:27:16
      But I want to talk about process.
    • 00:27:18
      So we modeled three dimensionally the existing topography, the road, the bridge, Route 64.
    • 00:27:29
      And so we have a very, very accurate
    • 00:27:33
      Depiction of at scale of the entire site and then after that depends on where you take a picture from You know, so the camera can go to any one of these spots, which is part of the storytelling part of it What do you want to know and where yeah, so we can
    • 00:27:49
      you know the idea is to tell you a picture take a picture from the bridge above it around it facing south facing north anything you want to do you can explore that model and it should be very very accurate so that's the work you know there's a lot of work that we've done in front of the board yeah I think a good one Margaret would be one that kind of shows
    • 00:28:18
      like the 19 or 20, yeah, that one.
    • 00:28:23
      So this is proof of concept and working with a client, we went through a lot of iterations.
    • 00:28:32
      We weren't the base architect, but we did help the owner make improvements, facade improvements.
    • 00:28:39
      So we started with the model, we started with
    • 00:28:44
      Things that could be improved upon, and then the site was modeled at scale with all the retaining walls, the right elevations, things like that.
    • 00:28:53
      And then it's a question of materiality, color, form.
    • 00:28:58
      And these are things that we debated with ARB, but also the client chose.
    • 00:29:05
      And we can show you basically at any vantage point what it might look like.
    • 00:29:14
      And the great news here is that for the couple of images that are in question, we can talk about what happened there.
    • 00:29:22
      But basically, the entire site, all of this is built to a very, very high accuracy to what was built.
    • 00:29:31
      and also a depiction of the materials.
    • 00:29:34
      We don't build it obviously, but these are all indications of what it would look like if the material palette used was done.
    • 00:29:47
      Okay, let's go back to the slideshow and go to the next slide.
    • 00:29:53
      So I want to talk a little bit about new technologies and workflows.
    • 00:29:57
      I just got back from a conference at Trimble, which is a geospatial organization in Las Vegas.
    • 00:30:04
      It was amazing what they're doing and what's coming.
    • 00:30:08
      So we've
    • 00:30:11
      Trimble has bought SketchUp.
    • 00:30:13
      That happened about five or six years ago.
    • 00:30:16
      So SketchUp was our primary kind of narrative tool or three-dimensional tool.
    • 00:30:22
      So we got our 3D topography from that.
    • 00:30:25
      We could also model from that.
    • 00:30:27
      We could take pictures from that.
    • 00:30:28
      So that was our base.
    • 00:30:30
      That's what a lot of the work you've seen before.
    • 00:30:31
      It's still a big part of what we do, but we've also moved to Revit.
    • 00:30:39
      You can go to the next slide.
    • 00:30:41
      So SketchUp was our base, and now the state has flown using LIDAR the entirety of the whole state and has made that LIDAR data available for download.
    • 00:30:55
      And what's amazing about that LIDAR is that it not only gives you incredibly accurate ground plane, it also gives you incredibly accurate canopy and building information.
    • 00:31:08
      So you can go to the next slide.
    • 00:31:11
      and using something called segmentation, you can run automated AIs kind of moving into this world, into the architectural world as well and using AI and or algorithms.
    • 00:31:25
      What it does is it looks at the data that's captured.
    • 00:31:29
      Does anybody know what LIDAR is?
    • 00:31:31
      Yeah, so LIDAR is not that, it was invented in the 70s, but basically it's a light pulse that goes out and it hits until it hits something that stops it, it measures that point in an XYZ coordinate system, and it does that hundreds and hundreds and billions and millions of times.
    • 00:31:53
      And what it does is it produces a three-dimensional duplicate of the existing conditions.
    • 00:31:59
      So a digital duplicate at scale.
    • 00:32:01
      So what you're looking at here is a portion of a lidar image or lidar data that was captured.
    • 00:32:08
      And then using segmentation, you can distinguish between ground plane, vegetation, power lines, buildings, things like that.
    • 00:32:16
      So it automatically pulls that information out.
    • 00:32:19
      This is useful for us because it's not only available publicly and for free, we can now visualize our buildings in any context at a very, very high level of accuracy and without a lot of work, without a lot of extra work.
    • 00:32:36
      So this is an image of a winery that we're doing.
    • 00:32:41
      And on the top image, you can see a picture, a photograph of the site.
    • 00:32:46
      And then this is our model.
    • 00:32:51
      And in the background, you can see the lidar information that came off the state.
    • 00:32:55
      So now there's this parity between, visually speaking, between what we think was there and it's also capturing tree canopy as well, which has always been a bit of a challenge for us because we didn't have an accurate source except through
    • 00:33:13
      Kind of guessing what a tree you know trees grow and they move and they get cut down It's part of the part of the issue that happened in Presidio.
    • 00:33:23
      We had a very very accurate topography and road elevation and building but it was hard it was more subjected to understand where what trees were being left and their impact on the on the so I think we've solved for that at to this point and
    • 00:33:41
      The other thing we're doing is 3D point cloud scanning.
    • 00:33:44
      What you see there is a scanner.
    • 00:33:46
      It collects 125 million points in three minutes.
    • 00:33:51
      And it digitizes those points, takes a high resolution image.
    • 00:33:56
      And unlike the image you saw before, which were kind of colors, this adds an RGB value.
    • 00:34:01
      So if it captured this surface, that would be black, that would be brown.
    • 00:34:07
      So it's almost like a photorealistic version of the as-built condition.
    • 00:34:12
      So the amazing thing about that camera, you put it in here, you capture 125 million points, you go to that doorway and open it up, capture another 125 million points, it stitches those together, and then you go around the whole building and you get, you know, in a day or so, I'd probably do this building, not as a big building, maybe two or three days, we get a digital duplicate of the building itself.
    • 00:34:36
      So every measurement down to an eighth of an inch across the whole building,
    • 00:34:41
      This is just to say where we're going.
    • 00:34:46
      I think you might want to click onto that link.
    • 00:34:50
      This is a little video that we did.
    • 00:34:54
      And Margaret, if you go to about the midline, I want to just show you.
    • 00:35:02
      Let's try that.
    • 00:35:03
      So here's a good explanation of what we're trying to do here.
    • 00:35:06
      So what we have, yeah, if you could pause it, that would be awesome.
    • 00:35:10
      So what we have here is a 3D point cloud scan of the transit center in Charlottesville.
    • 00:35:14
      And we just use this as an example.
    • 00:35:17
      Very, very hard to get as-built conditions on a building like that because it's in a public way.
    • 00:35:22
      It's tall.
    • 00:35:22
      It's not orthogonal.
    • 00:35:24
      It's pitching back.
    • 00:35:25
      So our scanner catches all that information.
    • 00:35:28
      Then we bring it into what you're looking at a SketchUp and we can model to it.
    • 00:35:33
      So we understand, you know, you're you're drawing a vector line drawing to the existing conditions.
    • 00:35:39
      And then you're getting a very, very accurate representation because you're using that
    • 00:35:44
      The old days, the way we used to do it five years ago, we still do it, some people.
    • 00:35:48
      You take a tape measure, you measure this building.
    • 00:35:51
      This is curved, a little curved.
    • 00:35:54
      So the question is, how do you get good accurate as-built?
    • 00:35:57
      It's actually quite difficult the old way.
    • 00:36:00
      I feel like we jumped from like a caveman, but where we were to astrophysicists in one fell swoop, not that we invented the technology, but we're using it to our highest advantage.
    • 00:36:14
      So the good news there, you can go down to the next slide, is that using the point cloud and for the work of the ARB, this is another example of honing in to what's the story you want to tell and how accurate it is.
    • 00:36:31
      And there's always been, and there probably always will be, a subjective reality to the story that you're telling.
    • 00:36:38
      Where's the image?
    • 00:36:39
      Where did you take the picture?
    • 00:36:42
      Why did you take the picture?
    • 00:36:43
      Where you took it?
    • 00:36:44
      What are you trying to show?
    • 00:36:45
      What are you not trying to show?
    • 00:36:46
      This, and I won't say that we're trying to show our best light, you know, for our projects, and we're also trying to show areas of impact, like if there's an intersection that the ARB cares about,
    • 00:37:00
      and obviously we but we basically put the camera in that location and take a picture you know so there isn't a lot of gamesmanship being played here we're not trying to you know to show you something that's not there and so this is a picture of just how buildings are represented a point cloud just like this building we could scan it
    • 00:37:25
      It would look like the thing on the left because all the point clouds build a comprehensive idea of the building, and then we model to it, and then we take that building and put it into the site model.
    • 00:37:40
      So anything that you saw, you could have an incredible amount of strength or understanding that it was as real as we could get it.
    • 00:37:53
      Next thing.
    • 00:37:55
      And then how the point cloud works into making construction models and images.
    • 00:38:01
      So what you're seeing here is that orthogonal view, elevational view.
    • 00:38:06
      So this is blending that whole world of the plan section elevation.
    • 00:38:12
      Back to what's necessary to build, let's say, or I know some people just want straight elevations.
    • 00:38:19
      That's how they've compared other projects.
    • 00:38:22
      So this doesn't preclude that.
    • 00:38:24
      It allows for all of that investigation.
    • 00:38:27
      And it's also, again, in the case of the architecture profession, we're trying to make good, accurate stories that democratize the design process so that the owners can be part of that
    • 00:38:42
      of their experience with things that they want, and then we're showing you to the best of our abilities the reality of what it will look like.
    • 00:38:54
      So that's kind of the end of my presentation.
    • 00:39:00
      The problem with the Presidio was basically it came down to one element, which was the existing trees.
    • 00:39:08
      And we had a sharp embankment.
    • 00:39:11
      The viewpoint, if you look at the images that we have, and then if you can go to Google Earth and you look at the maps and how you can street view.
    • 00:39:19
      So the buildings are perfectly situated elevationally.
    • 00:39:23
      They're exactly right.
    • 00:39:24
      Problem was that there was a slope that came up, and the level of disturbance, it was the trees, since we didn't have the lidar, it was more of a guessing game of how far the disturbance was, and how far the trees were, because it's hard to designate how high they were.
    • 00:39:43
      So the trees were taken off of the slope further than we thought, and they weren't as tall as we thought, and that was what created the problem.
    • 00:39:57
      So there's a slope there.
    • 00:40:01
      You can imagine a slope that's populated with trees.
    • 00:40:05
      We had an image of a street map.
    • 00:40:08
      So that's the image that we used to identify the perspective.
    • 00:40:15
      What we didn't know was how far the trees were that were going to get cut down.
    • 00:40:20
      and their relative height.
    • 00:40:21
      So if they were higher, closer to the bottom of the heel of the site, they would have done a better job of protecting it.
    • 00:40:30
      As it was, a lot of the tall trees were on the upslope, which we couldn't tell from, and admittedly, it's one of the, because it's not subjective, we'd have to go out there and measure trees to understand their impact.
    • 00:40:48
      That's where the majority of the problem of this image came from.
    • 00:40:55
      But again, the visual parity between
    • 00:41:00
      Elevationally, the bridge and where the site was and the site walls and the buildings and all that was tied to the two elevations of not only the highway, but also the Sentara driveways, the Sentara circular path.
    • 00:41:19
      Those things were all tied in together.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:41:29
      Thank you for your presentation, Bob, and thank you also for all the presentations you've made before the board.
    • 00:41:33
      I know all of us really appreciate the clarity and the thoroughness that you bring to the work and how you help us understand the projects before us.
    • 00:41:41
      Appreciate as well the background on this view and what data there was and wasn't.
    • 00:41:48
      I guess, well, I don't know, Chris, to refer to you, are we just, we're in a work session and discussion?
    • 00:41:55
      So,
    • 00:41:59
      I guess do you have thoughts or recommendations on what we might do as a board to avoid a repeat where an outcome is different than we expected it to be?
    • Bob PineoPrincipal
    • 00:42:13
      I think it's a good question.
    • 00:42:16
      I think it's a question of process.
    • 00:42:18
      And the question I would ask, I feel like we've been, if we were doing this,
    • 00:42:25
      Hapaz would be in front of you a lot, just from all the things that we've done.
    • 00:42:31
      And if you go and compare, they're close facsimile to each other.
    • 00:42:37
      So I think a bigger question or a question to ask, which is the root of what you're asking, where are these coming from?
    • 00:42:45
      How do I know as somebody who's reviewing them?
    • 00:42:49
      There's always subjective understandings, even a site plan.
    • SPEAKER_01
    • 00:42:52
      You make sure that you're speaking.
    • Bob PineoPrincipal
    • 00:42:54
      Oh, yeah.
    • 00:42:54
      Sorry, sorry.
    • 00:42:55
      So there's always a subjective reality to perception.
    • 00:43:00
      So a site plan, things get missed.
    • 00:43:03
      I think that's why people like what we do, because there's less subjectivity to them.
    • 00:43:08
      I might ask the question, what was your process when you delivered these images?
    • 00:43:15
      And especially because it's so new, it's kind of the wild west.
    • 00:43:19
      There aren't a lot of rules.
    • 00:43:21
      What was your process?
    • 00:43:23
      What was your intent?
    • 00:43:25
      Can you describe where these things came from as a board?
    • 00:43:30
      And just knowing how things are derived, is this a image that you drew over?
    • 00:43:37
      What was the level of technology that you used to come to this conclusion?
    • 00:43:42
      I would say that's a good place to start, at least in questioning intent.
    • Frank StonerMember, Architectural Review Board
    • 00:43:55
      Bob, it looks like in the original rendering that you guys did that the wall structure at this particular project was different than what ended up getting built.
    • 00:44:06
      Is that true or does this accurately reflect what you guys showed on your...
    • Bob PineoPrincipal
    • 00:44:13
      All I can say, are you talking about the retaining walls?
    • 00:44:15
      All I can say is we don't go back and verify.
    • 00:44:19
      We model what was given to us from a site plan perspective.
    • 00:44:24
      So we take out top walls, elevations that are driven.
    • 00:44:27
      You might go back to the presentation, back to that presidio, because there's an overall view image.
    • 00:44:39
      So yeah, go down a little.
    • 00:44:41
      Yeah, you're right there.
    • 00:44:44
      Go to that Dropbox image.
    • Taro MatsunoMember, Architectural Review Board
    • 00:44:46
      Yeah, we could actually pull them up side by side maybe on the left and the right sides of the screen.
    • Bob PineoPrincipal
    • 00:44:51
      And do that one right there, that page 32.
    • 00:44:59
      So relative to the retaining walls, that's
    • 00:45:03
      That's what's built.
    • 00:45:05
      And if you look at what we had rendered, again, I don't go back and verify, but what we do do is use the site plan and take the top of wall and model it as accurate as we can to depict it.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:45:24
      And Bob, some of the 3D views included trees at the steps of the retaining wall.
    • 00:45:30
      Were those present in any of the perspective views or they were just in that area?
    • Bob PineoPrincipal
    • 00:45:35
      We're going back a couple years now.
    • 00:45:37
      I typically would render whatever's there.
    • 00:45:41
      So if there's site plan, because you can see in our images, the site plan came with landscaping, you know, images or, you know, specifics, what the planting, where they were, we would model those and put them in as they were there.
    • Margaret MaliszewskiPlanning Manager
    • 00:46:07
      But I think earlier in the review process, there might have been landscaping shown on the site.
    • 00:46:14
      But then when we got some of the other images that showed that the lower areas didn't look like they were going to be visible from the interstate, we just stopped looking at the landscaping in those areas around the retaining walls because we didn't think the walls were going to be visible.
    • Frank StonerMember, Architectural Review Board
    • 00:46:31
      It looks like the walls got a lot closer together because there is no landscaping between like here showing trees at every level it looks like.
    • Bob PineoPrincipal
    • 00:46:42
      I would have to show you what I modeled and when.
    • 00:46:46
      The objective is to model it very accurately with the latest information that we have.
    • 00:46:52
      So that, you know, when this was submitted to us, we were modeling, you know, basically CAD models which were driving the site submission.
    • 00:47:05
      So that's what we're modeling.
    • 00:47:08
      If that makes sense.
    • 00:47:09
      Now something, did it change during that process?
    • 00:47:13
      I don't know if that's the case.
    • 00:47:16
      You're referring to the trees, right?
    • Frank StonerMember, Architectural Review Board
    • 00:47:18
      Yeah, the trees between retaining walls.
    • Bob PineoPrincipal
    • 00:47:21
      So just counting the number of retaining walls, one, two, three, four, five in our model.
    • 00:47:27
      And maybe I think that's about what you ended up with, but.
    • Frank StonerMember, Architectural Review Board
    • 00:47:32
      Do we have a perspective from 64 that would have shown this?
    • 00:47:41
      Let's assume we can't see anything.
    • Bob PineoPrincipal
    • 00:47:45
      If you go to that aerial, looking down, and we can, you know, even in
    • 00:47:53
      In hindsight, we could take an image of the existing, you know, of the number 19, I think.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:48:01
      Oh, yeah.
    • 00:48:04
      One, two, three, four.
    • Bob PineoPrincipal
    • 00:48:04
      So there's five walls there.
    • 00:48:06
      So.
    • 00:48:09
      We could, you know, we could overlay the model as it was, we could overlay the image and the model at the same vantage point and compare them.
    • Frank StonerMember, Architectural Review Board
    • 00:48:23
      We put the photo, put that image from 64 back up.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:48:51
      Do we have the actual?
    • Frank StonerMember, Architectural Review Board
    • 00:48:58
      That was that 19.
    • 00:48:59
      Right hand side.
    • 00:49:00
      Be interesting to see that.
    • Bob PineoPrincipal
    • 00:49:07
      Might be in your tabs.
    • Frank StonerMember, Architectural Review Board
    • 00:49:09
      Yep.
    • 00:49:30
      The other one that showed all five walls as built.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:50:02
      Sort of the shift in looking down at them to looking up at them.
    • 00:50:06
      Yeah, I guess a philosophical question maybe for my my fellow board members is, you know, so often as we're looking at projects and trying to understand their impact, we're considering the landscape.
    • 00:50:17
      And frequently that landscape is outside of the applicant's control, as is the case here.
    • 00:50:24
      Is there anything that we should
    • 00:50:27
      Consider in terms of restricting what landscape can be shown to only that that's proposed with the site plan or otherwise to avoid any future scenarios where we evaluate something and its impact based on screening that may be part of the application.
    • 00:50:56
      I mean, on the one hand, there are many projects probably that don't have an impact because of the screening outside of their control and might not be as feasible if they had to be as completely screened within their own borders.
    • 00:51:13
      And yet, certainly this project has a much more dramatic visual impact on the corridor than I think certainly I anticipated.
    • 00:51:21
      So just for discussion.
    • Chris HenningsenChair, Architectural Review Board
    • 00:51:31
      Yeah, I guess to me there's like two...
    • 00:51:32
      I kind of have two observations.
    • 00:51:38
      One is just Bob is almost not a good example to use because he's so good at that.
    • 00:51:50
      And these two images, the rendering that was produced versus the actual
    • 00:52:01
      photograph are so close in my opinion.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:52:05
      Yeah, though it is quite accurate in terms of physical elements.
    • Chris HenningsenChair, Architectural Review Board
    • 00:52:09
      If the rendering that was submitted was the kind of like rudimentary crappy rendering that like I might do, then it might, it might not even be an issue.
    • 00:52:24
      It would be like, well, you know, it doesn't look like the rendering.
    • 00:52:28
      Well of course it doesn't look like the rendering because the rendering is like obviously an artist's impression of what it might look like and it seems like the better the rendering, the more accurate or more realistic the rendering gets, I think the more of an expectation there is that it's
    • 00:52:58
      really going to look just like that when and that kind of gets me to my second observation is that design or at least in terms of the building maybe not as much for site plans but like at least in terms of buildings frequently like at least in my experience like the design of the building itself
    • 00:53:26
      at the stage where you're submitting for ARB consideration is still like very preliminary in terms of the overall design of the building.
    • 00:53:38
      So there's still a lot to be ironed out.
    • 00:53:40
      So there's this problem, and I don't know that I'm arguing for anything specific, but just observing that like a lot of times
    • 00:53:54
      Building design will be submitted that looks further along in its development in terms of the design than it really is.
    • 00:54:05
      And it's like how much, when you get approval from the ARB, I guess there's a little bit of a, just speaking not as a member of the ARB, but as an architect, you might,
    • 00:54:22
      How much does that approval like lock you in to what was submitted?
    • 00:54:27
      Like how much can you take the kind of what you perceive as the intent of that approval to develop the design further to where you need it to go?
    • 00:54:38
      And how much does it have to retain the act appearance of like what you it and sometimes that
    • 00:54:51
      comes back to quality of what is submitted or at least like maybe not it's not even a quality issue but like you're able to get approval with some images that are kind of vague and maybe not show certain aspects of the bill and that kind of gives you more latitude in terms of like
    • 00:55:21
      future, you know, your ability to adapt.
    • 00:55:26
      Whereas if you're very specific, at least, and I'm just talking about the three-dimensional images that are produced.
    • 00:55:35
      I mean, plans should be, in my opinion, it's easier for like plans and elevations to be three-dimensional imagery.
    • 00:55:49
      It's like,
    • 00:55:51
      almost gives an advantage to somebody who's less specific about what they're showing and that depending on how much they're held to that in terms of like what the final product looks like compared to what was submitted
    • 00:56:17
      I don't quite know where I was going with all that.
    • 00:56:23
      That's my own random observation.
    • Frank StonerMember, Architectural Review Board
    • 00:56:29
      What recourse does the board have in the event that somebody submits a perspective like this, for example, where there's a clear disconnect between what happened in reality and
    • 00:56:46
      what we were shown.
    • 00:56:48
      Is there any recourse?
    • 00:56:49
      Can you go back?
    • 00:56:50
      Could you go back to Riverbend and say, hey, the walls, you know, this isn't what you submitted.
    • 00:56:56
      Now you're going to need to plant in front of that.
    • 00:56:58
      You know, we're going to need like, do we have any power, authority?
    • Margaret MaliszewskiPlanning Manager
    • 00:57:04
      Well, it's a good question.
    • 00:57:05
      I think in this particular case, well, I guess the question would be,
    • 00:57:17
      Go back to the approved documents.
    • 00:57:20
      Is it just the plans and the elevations and the site plans, or is it also the 3D images that are approved?
    • 00:57:31
      I think we could ask some others about that.
    • 00:57:33
      I'm not sure what the answer is.
    • 00:57:35
      I think in a case like this, particularly when it comes down to the retaining walls, there isn't a whole lot of opportunity to go back and plant trees like they're shown there.
    • 00:57:48
      It's just not going to work.
    • 00:57:54
      We have limited opportunities for making up for it after the fact.
    • 00:57:58
      We have looked at this, all the landscaping that's on the approved plan has been planted.
    • 00:58:02
      I think they're all real small at this point.
    • 00:58:06
      I think, you know, give it a few years and it'll get closer to what was shown, maybe not exactly.
    • Frank StonerMember, Architectural Review Board
    • 00:58:14
      So there are trees at every level?
    • Margaret MaliszewskiPlanning Manager
    • 00:58:16
      No, not on the retaining walls, on the other side of the pond.
    • 00:58:19
      So between the pond and the interstate, there are trees there.
    • 00:58:23
      And those can grow up and will soften some of that.
    • Taro MatsunoMember, Architectural Review Board
    • 00:58:31
      But isn't that like, I guess that's where I'm, I think there's like a question of like, sort of where do we, you know, what perspectives are we shown and what appears on them?
    • 00:58:40
      But I feel like there's a couple of things in this one that I'm noticing, like,
    • 00:58:44
      I don't think, it doesn't look like we got the view from the corridor that we were most concerned with in the package, in the ARB package, right?
    • 00:58:53
      I didn't see a highway view.
    • 00:58:55
      That's the image.
    • 00:58:58
      That's the rendering.
    • Dade Van Der WerfMember, Architectural Review Board
    • 00:59:01
      Yeah.
    • Taro MatsunoMember, Architectural Review Board
    • 00:59:03
      Okay, well then, okay, so maybe we got the image, but we did get just a depiction of landscape that didn't end up getting planted in the original project, in the eventual project, right?
    • 00:59:15
      Like, there's no trees at every level, there's not gonna be, looks like there are plantings at that other retaining wall near that building in the middle, and that doesn't look like it got planted either.
    • Bob PineoPrincipal
    • 00:59:36
      And what's the date of that?
    • Margaret MaliszewskiPlanning Manager
    • 00:59:38
      This is the approved site plan.
    • Bob PineoPrincipal
    • 00:59:40
      I see.
    • 00:59:41
      Yeah.
    • 00:59:42
      So what we rendered, you know, I have to look back on the date, you know, because I think we're talking about process and choices along the way.
    • 00:59:54
      And to your point, there's a beginning of this and then there's resolution like testing the architecture and the materiality.
    • 01:00:02
      And there's a whole, you know,
    • 01:00:04
      40 page document on cladding and windows and views and all that kind of stuff.
    • 01:00:11
      So I'd have to go back to see where we were in process.
    • 01:00:14
      But we didn't make this up.
    • 01:00:17
      This is a vector file drawing that
    • Margaret MaliszewskiPlanning Manager
    • 01:00:22
      So I think you can see all this landscaping here.
    • 01:00:25
      That doesn't have an impact yet from the interstate.
    • 01:00:30
      Someday it probably will.
    • Taro MatsunoMember, Architectural Review Board
    • 01:00:32
      But there's a change at one point from a scheme where they had retaining walls that were further apart and planted to one where the planting all went onto the other side of the pond.
    • Margaret MaliszewskiPlanning Manager
    • 01:00:51
      I'd have to go back to the preliminary plan and see if that one showed planting at each of the levels of the retaining wall.
    • 01:01:00
      I'm not sure that it did.
    • Bob PineoPrincipal
    • 01:01:01
      I mean, you can see that lower retaining wall with that big swoop on the right-hand side.
    • 01:01:07
      That's what's showing up on the plan is one, two, three, four, five.
    • 01:01:12
      One, two, three, four, five.
    • 01:01:14
      And there's even a little sixth one on the top.
    • 01:01:16
      So there's parity between that and that.
    • Frank StonerMember, Architectural Review Board
    • 01:01:21
      Yeah, it's just the landscaping that's not... Landscaping, yeah.
    • 01:01:24
      Accurate.
    • 01:01:25
      Well, and the spacing of the walls and the elevation of the walls.
    • 01:01:29
      If you look at the rendering or the picture, the photo from 29,
    • 01:01:36
      The walls are enormous, whereas you're led to believe in the rendered version that these walls could be four feet, six feet maybe?
    • Bob PineoPrincipal
    • 01:01:45
      I think what you might be, I don't know if you'd have to zoom in there, because you might be looking at multiple layers of retaining wall that look like they're one, but they're actually tiered because they don't build them that high.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:01:57
      So there's a foreground and a back.
    • Margaret MaliszewskiPlanning Manager
    • 01:02:00
      Yeah, they are, they are tiered and you just, there's no, there's no, any, any planting that's there is just not tall enough to, you're not seeing it.
    • 01:02:10
      So it's, it's at this, you know, the photo was just making it look like it's a single wall.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:02:20
      Back to the approved site plan, Margaret.
    • 01:02:32
      So I think part of what it is, Frank, is I think we're seeing both the retaining walls for the building and the retaining walls for the road.
    • Taro MatsunoMember, Architectural Review Board
    • 01:02:42
      But in the rendering, they show plantings for the building retaining wall, too, that aren't on the site plan.
    • Frank StonerMember, Architectural Review Board
    • 01:02:48
      Yeah, that's right.
    • Taro MatsunoMember, Architectural Review Board
    • 01:02:50
      I guess I think that there's this really practical matter.
    • 01:02:55
      There's a lot of landscaping that's shown on the rendering that does not appear to be reflected in the site plan.
    • 01:03:01
      They were never coordinated or something changed at one point, but it's pretty significant.
    • Margaret MaliszewskiPlanning Manager
    • 01:03:12
      To be fair, there is some planting on these walls that's there.
    • Taro MatsunoMember, Architectural Review Board
    • 01:03:19
      But they're showing a whole series of trees behind that clubhouse or whatever, the garagey thing.
    • 01:03:29
      You know, in the rendering?
    • Frank StonerMember, Architectural Review Board
    • 01:03:33
      Yeah, the other rendering, right?
    • 01:03:37
      Talking about this?
    • Taro MatsunoMember, Architectural Review Board
    • 01:03:38
      Yeah, yeah.
    • Frank StonerMember, Architectural Review Board
    • 01:03:48
      Yeah, I mean, it's a tough spot for you to be in as well, Bob, because if...
    • Bob PineoPrincipal
    • 01:03:52
      It's relatively, we modeled what we saw, what we were given at that point.
    • 01:03:57
      Yeah, yeah.
    • 01:03:59
      Outside of the existing trees, that was a tough one.
    • 01:04:05
      But the other ones are just like a building or a wall.
    • 01:04:09
      It's just not a diminished tree, but we take a tree at scale and put it in where there's a circle.
    • 01:04:16
      So it's just not subjective.
    • 01:04:20
      It's whatever the site plan tells us to do because we don't have
    • 01:04:23
      Time or the fee, or we're not the authority of that, which is populating it the way it's shown.
    • Frank StonerMember, Architectural Review Board
    • 01:04:31
      So at some point, the site plan must have shown a different configuration.
    • Taro MatsunoMember, Architectural Review Board
    • 01:04:38
      And I guess for us, too, it's just maybe next time we see an arrangement like this, know that it's probably not possible to put trees on that retaining wall the way that they've shown, right?
    • 01:04:47
      Right.
    • Frank StonerMember, Architectural Review Board
    • 01:04:47
      That would imply that the retaining walls are much further apart than what the reality is.
    • 01:04:56
      You know, like that should have been self-evident, I guess.
    • 01:05:00
      But the presumption was you wouldn't, you weren't really going to be able to see any of it anyway.
    • 01:05:04
      Who done that?
    • 01:05:05
      Right.
    • 01:05:05
      Which is really, comes back to your initial point.
    • 01:05:09
      And I think the other thing sometimes we rely on is tree buffer during the summer months.
    • 01:05:17
      And then all of a sudden in the winter.
    • 01:05:19
      Yeah.
    • 01:05:19
      Where did it go?
    • Bob PineoPrincipal
    • 01:05:20
      Yeah.
    • 01:05:21
      And construction.
    • 01:05:23
      Yeah.
    • 01:05:23
      Yeah.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:05:23
      Takes a toll.
    • 01:05:27
      Well, Bob, I appreciate your presentation and obviously the care and the accuracy that you bring with the information that you have available to you.
    • 01:05:34
      And so thank you.
    • 01:05:36
      Thank you for that.
    • 01:05:37
      I don't do others want to have other questions or.
    • Taro MatsunoMember, Architectural Review Board
    • 01:05:42
      Lidar stuff is pretty cool.
    • 01:05:44
      Seems like you're doing good work on that.
    • 01:05:45
      Thank you.
    • Bob PineoPrincipal
    • 01:05:46
      Yeah, it's all evolving, too.
    • 01:05:47
      So that's the that's the other message here is.
    • Frank StonerMember, Architectural Review Board
    • 01:05:52
      Technical question for you, if the state's now done Lidar on the whole state,
    • 01:05:59
      Has there been any progress in getting from LIDAR to CAD?
    • 01:06:04
      AI is going to do that.
    • Bob PineoPrincipal
    • 01:06:07
      They're working on it, but it's not there.
    • 01:06:10
      The other bigger problem is using the data for site because it's not certified.
    • 01:06:16
      And so nobody will, even though it's more accurate, no one will accept it.
    • 01:06:20
      You can't submit it because there isn't a licensed surveyor that said, you know, that's
    • 01:06:27
      It's more accurate, I think, than a ground survey in a lot of ways.
    • 01:06:40
      All right.
    • 01:06:40
      Well, thank you for your time.
    • Margaret MaliszewskiPlanning Manager
    • 01:06:42
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:06:43
      All right.
    • 01:06:48
      So we'll go on to our second work session, which is the comp plan goals objectives.
    • 01:06:56
      And
    • Margaret MaliszewskiPlanning Manager
    • 01:07:15
      Yeah, if you're ready.
    • 01:07:16
      Great.
    • 01:07:17
      So we want to do a work session on the goals and objectives for the comp plan today.
    • 01:07:23
      You may recall both in March and June of this year, we had some discussions on the goals and objectives and overall process.
    • 01:07:33
      At your places, I've printed out the comments that you had on those days.
    • 01:07:38
      So you have those for reference.
    • 01:07:39
      I also have it at the end of the slideshow here if we need to display it for any reason.
    • 01:07:44
      Tori Kanellopoulos is here with us today and she's on the team that's leading the comp plan update efforts and we may ask her to pop in or she may have questions or comments for y'all as we go along.
    • 01:08:01
      What we want to do is go through each of the draft goals and objectives and ask you if they address all the comments and concerns that you've had or if you have ideas for additional comments to make at this point.
    • 01:08:17
      Just as a reminder, the goal is the high-level, long-term direction.
    • 01:08:20
      The objective is a more specific outcome or target to accomplish that goal.
    • 01:08:27
      after we have to get through the goals and objectives.
    • 01:08:29
      Actually, we've already started work on the action steps.
    • 01:08:32
      So the action steps are the even more specific points that would fall under each of the objectives.
    • 01:08:38
      So we don't have those for you today.
    • 01:08:40
      Goals and objectives first.
    • 01:08:41
      We'll get to the action steps later.
    • 01:08:46
      So I was just going to go through, read the goal, give a highlight of the objectives, and get your comments.
    • 01:08:53
      Will that work for you all?
    • 01:08:55
      OK.
    • Margaret MaliszewskiPlanning Manager
    • 01:08:56
      First goal, Albemarle County will recognize, celebrate, and increase awareness of the broad range of historic, cultural, and scenic resources that contribute to Albemarle's unique sense of place.
    • 01:09:07
      We've got three objectives under this goal.
    • 01:09:10
      The first one is about identifying, mapping, and documenting all those resources.
    • 01:09:15
      The second objective is about sharing the stories and the information related to all those unique resources.
    • 01:09:22
      And the third objective is about identifying and protecting against potential threats to the resources.
    • 01:09:30
      I'm happy to take your comments.
    • Chris HenningsenChair, Architectural Review Board
    • 01:09:35
      All right, I guess we'll just go right down the line.
    • 01:09:37
      Dave, do you have any comments?
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:09:41
      No, I think they seem well aligned with the goal.
    • Taro MatsunoMember, Architectural Review Board
    • 01:09:45
      No, I don't have any comments.
    • Frank StonerMember, Architectural Review Board
    • 01:09:56
      I don't think I have any comments either.
    • 01:10:00
      It looks good.
    • Chris HenningsenChair, Architectural Review Board
    • 01:10:06
      Sorry to disappoint, but I don't have any comments either.
    • 01:10:14
      Autos, I think it's good.
    • Margaret MaliszewskiPlanning Manager
    • 01:10:16
      Okay, well let's go through each one.
    • 01:10:18
      If they're all speedy quick then get Tori to come up and help us figure out what we need to do next.
    • 01:10:25
      Okay, goal two.
    • 01:10:28
      Albemarle County will protect its historic, cultural, scenic, and rural resources and natural environment while considering the future trajectory of development in the community.
    • 01:10:37
      Again, we have three objectives under this goal.
    • 01:10:41
      The first one is encourage greater preservation and protection of the resources by
    • 01:10:48
      the landowners and business owners through incentives, grant programs, and other funding streams.
    • 01:10:54
      That's about encouraging it through incentives.
    • 01:10:56
      The second objective is increase the preservation and adaptive reuse of historic and cultural resources through county programs and updated regulations.
    • 01:11:06
      And this would be also in this objective as
    • 01:11:11
      Information about energy efficient upgrades and also documenting resources before demolition.
    • 01:11:22
      And the third objective would be cultivate and pursue strong partnerships to lend additional support to preservation protection and management of the resources.
    • Taro MatsunoMember, Architectural Review Board
    • 01:11:33
      Sorry, would you mind flipping back to the last one for a second?
    • 01:11:35
      I'm just trying to mentally.
    • Margaret MaliszewskiPlanning Manager
    • 01:11:38
      I'm sorry.
    • Taro MatsunoMember, Architectural Review Board
    • 01:11:38
      Would you mind just flipping back to the last goal for the last slide just for a second?
    • Margaret MaliszewskiPlanning Manager
    • 01:11:41
      The first one.
    • 01:11:42
      Recognize?
    • 01:11:42
      Great.
    • Taro MatsunoMember, Architectural Review Board
    • 01:11:47
      Okay.
    • 01:11:47
      Okay, thanks.
    • Margaret MaliszewskiPlanning Manager
    • 01:11:51
      The first goal was about identifying and increasing awareness, and the second one gets into protection.
    • Taro MatsunoMember, Architectural Review Board
    • 01:12:01
      Okay.
    • Margaret MaliszewskiPlanning Manager
    • 01:12:05
      Comments?
    • Taro MatsunoMember, Architectural Review Board
    • 01:12:10
      Can we just go, maybe we go through all of them first and then come back.
    • Margaret MaliszewskiPlanning Manager
    • 01:12:15
      Goal three, Albemarle County will have opportunities for all community members to access and enjoy local, historic, scenic, and cultural resources.
    • 01:12:24
      Three objectives here again.
    • 01:12:26
      First one, provide both online and in-person opportunities to access the resources and to increase awareness about the benefits of preserving them.
    • 01:12:37
      Objective two, protect, enhance, and recognize the importance of local viewsheds and landscapes that contribute to the county's identity, especially around historic and cultural sites and landscapes, mountain resources, and waterways.
    • 01:12:50
      And objective three, reduce light pollution to protect and enhance the dark sky while balancing the need for a safe and built environment.
    • 01:13:02
      Goal four, Albemarle County will have attractive and scenic entrance corridors and other important county roadways that support the county's natural environment and unique sense of place.
    • 01:13:13
      First objective under goal four is to elevate the quality of design along designated entrance corridor streets and encourage the use of renewable energy sources and sustainable building materials.
    • 01:13:23
      And objective two, increase the number of designated scenic roads in Albemarle County.
    • Chris HenningsenChair, Architectural Review Board
    • 01:13:33
      I guess I have a question about that last one.
    • 01:13:35
      A designated scenic road, that's a different category than an entrance corridor, and does that come with specific requirements that are similar to EC requirements?
    • Margaret MaliszewskiPlanning Manager
    • 01:13:50
      A state scenic road doesn't have any requirements associated with it, but when we get to the action steps here, we may
    • 01:14:01
      I have some that talk about that state designation that doesn't have the requirements and possibly getting into some of the discussion that you all have had previously about the impact of the landscape in the entrance corridors and is it more about just the scenic aspect or is it the architecture as well and maybe finding some action steps to work through that.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:14:32
      And the scenic designation would give us potentially a vehicle to influence landscape in a way beyond what's available through the MECE.
    • Margaret MaliszewskiPlanning Manager
    • 01:14:40
      Right, a potential action step could be to pursue a local scenic street designation which could have regulations associated with it and address some of those issues.
    • Frank StonerMember, Architectural Review Board
    • 01:14:55
      How many designated roads are there currently in the county?
    • 01:14:59
      Scenic roads?
    • 01:15:00
      Yeah, scenic roads.
    • Margaret MaliszewskiPlanning Manager
    • 01:15:02
      They're not that many.
    • 01:15:03
      And I don't have that list in front of me, but I can try and get that for you.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:15:11
      It's 250 designated, but is it a state scenic road or it's a county?
    • Margaret MaliszewskiPlanning Manager
    • 01:15:16
      No, you're quizzing me.
    • 01:15:17
      I did not spend well enough.
    • 01:15:22
      It's actually in, if I had just brought the current comp plan that weighs 20 pounds, I could go right to the page and list them off for you.
    • 01:15:32
      I'll get that information for you soon.
    • Frank StonerMember, Architectural Review Board
    • 01:15:46
      Under objective 4.1, I guess one question I have is how do we balance the sort of quality of design with potentially renewable energies used in the form of solar panels, for example.
    • 01:16:05
      I compromise.
    • Margaret MaliszewskiPlanning Manager
    • 01:16:07
      Exactly.
    • 01:16:08
      Yeah, that's a really good question.
    • 01:16:10
      We don't have the answer to that at this point, but I think our action steps will try to set a path for figuring that out.
    • Taro MatsunoMember, Architectural Review Board
    • 01:16:24
      Could we go back to goal two, maybe?
    • 01:16:29
      I'm sorry.
    • Frank StonerMember, Architectural Review Board
    • 01:16:31
      No, no, I was going to say, maybe we go three to this.
    • 01:16:36
      I had a question on three, but we can go to two and then back.
    • Taro MatsunoMember, Architectural Review Board
    • 01:16:39
      Okay, sorry.
    • 01:16:40
      Sorry to jump you in line.
    • 01:16:41
      I guess my one comment is just that the goal itself says while considering the future trajectory of development in the community, but I don't know if any of the objectives speak specifically to how that development should happen or what our vision for it might be.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:17:07
      Okay.
    • Taro MatsunoMember, Architectural Review Board
    • 01:17:10
      You know, I mean, I think that there's a way to say, you know, that, I don't know, that growth within the county, because it won't look exactly like things that, precedents that we have within the county.
    • 01:17:26
      But I think we still want to encourage a high level of design quality and consistency within those new development areas.
    • 01:17:37
      I think just because we call it out in the goal, it might be good to include it in an objective.
    • SPEAKER_01
    • 01:17:43
      Okay.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:17:46
      I guess sort of related to that, I had the question looking at this one, because on the one hand, there's the active verb that a county will protect, it's historic, etc., but only consider its future trajectory.
    • 01:17:57
      So I wasn't sure whether there
    • 01:18:00
      whether the development of the county is addressed with an active verb elsewhere in the polls outside of this section.
    • 01:18:10
      I guess I'll try to change it to well-developing.
    • 01:18:21
      I'm not sure how intentional it was that the development is just being considered.
    • Margaret MaliszewskiPlanning Manager
    • 01:18:30
      I'm going to ask Tori.
    • 01:18:35
      I think that wording got added in.
    • SPEAKER_00
    • 01:18:47
      Good afternoon, Tori Kanellopoulos.
    • 01:18:49
      I'm a principal planner in community development and thank you all for your discussion and input today.
    • 01:18:54
      I think it's really helpful.
    • 01:18:55
      I think for this one it was kind of meant to acknowledge that, you know, development is going to continue to happen, especially in the development areas.
    • 01:19:06
      And a lot of those more specific recommendations for how and where that should happen would be like in the land use section of the comp plan.
    • 01:19:14
      But in this section just kind of considering what some of those chapter considerations are going to be related to historic, cultural, and scenic resources.
    • 01:19:25
      and also I'll note the discussion on solar panels and the entrance corridors is something we've talked about too and I know we're not quite to action steps yet but if you all have any thoughts on action steps or implementation we're happy to hear those and consider them.
    • 01:19:40
      and we've presented these goals and objectives to the Planning Commission and got their input and I think they generally thought everything was going in the right direction.
    • 01:19:49
      I think they had some questions about Objective 4.1, kind of similar to that, what's the kind of entrance corridor piece versus the renewable energy and sustainable building materials piece and then we'll share these with the Board of Supervisors in January.
    • 01:20:05
      Happy to come up and answer more questions too.
    • Frank StonerMember, Architectural Review Board
    • 01:20:10
      So quick question on objective 2.1, incurred greater preservation and protection of Albemarle's historic level.
    • 01:20:21
      What are the things that you all are thinking we should be doing in the way of greater preservation that we're not doing now?
    • Margaret MaliszewskiPlanning Manager
    • 01:20:33
      Well, we don't have any incentive programs really at all in place, so I think the action steps will focus on finding some of those incentive programs and finding some funding streams.
    • 01:20:53
      We haven't figured it all out yet, so we're still working on that.
    • 01:20:58
      I think
    • 01:21:03
      Yeah, I think it's really about the incentive programs.
    • 01:21:09
      We've been finding that some of these objectives overlap from one goal to the next, so there are other programs that could be put in place, like the Historic Preservation Committee has recommended.
    • 01:21:24
      a program to acknowledge good preservation so you could have an annual awards program that's a type of incentive or a type of encouragement perhaps but I think financial incentives are really what are needed.
    • Chris HenningsenChair, Architectural Review Board
    • 01:21:40
      And just as a comment like I do appreciate that what's being discussed is like incentives rather than like
    • 01:21:54
      you know additional like yeah mandates or regulation that would like you know require additional reviews and all that kind of stuff which I think incentive is a better approach assuming the incentives are
    • 01:22:15
      Incentivizing enough to actually get people to tip the balance.
    • Margaret MaliszewskiPlanning Manager
    • 01:22:20
      Right.
    • 01:22:21
      Well, under this goal, 2.1 is about incentives and 2.2 is about potential additional regulations.
    • 01:22:29
      So I think where we're headed is sort of a balance between them.
    • 01:22:35
      The other issue about funding is if you have a local historic district with local regulations then you can become a certified local government through the Department of Historic Resources and you can become available or eligible for grant programs through that organization.
    • 01:23:00
      You can't be a certified local government without a local historic preservation ordinance in place.
    • 01:23:28
      Mariah has done the research that I did not do.
    • 01:23:31
      There's five scenic highways listed in the current company.
    • Mariah GleasonUrban Designer
    • 01:23:39
      Just to list them off, there's Skyline Drive, Blue Ridge Parkway, Colonial National Parkway, Journey Through Hallowed Ground Corridor, which is routes 20 and 53, and George Washington Memorial Highway.
    • Chris HenningsenChair, Architectural Review Board
    • 01:24:08
      Well, any additional discussion?
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:24:13
      No, I appreciate the development and the concrete.
    • Margaret MaliszewskiPlanning Manager
    • 01:24:18
      Thank you.
    • 01:24:19
      So we are working on action steps.
    • 01:24:21
      Tori, we do plan to bring those back in the future next year.
    • 01:24:25
      Is that right?
    • SPEAKER_00
    • 01:24:26
      Yes.
    • 01:24:28
      We do plan to share those next year.
    • 01:24:30
      So I think the anticipated timeline would be rolling out action steps for all comp plan chapters, probably in like mid spring, you know, April timeframe.
    • 01:24:41
      So that would include kind of broad community engagement, but also coming back to you all and other county committees for input.
    • Chris HenningsenChair, Architectural Review Board
    • 01:24:49
      All right.
    • SPEAKER_00
    • 01:24:51
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:24:52
      All right.
    • 01:24:52
      Thanks a lot.
    • 01:24:57
      So we will move on to other business.
    • 01:25:00
      First is approval of the October 2nd, 2023 minutes.
    • 01:25:06
      I'll move to approve this.
    • 01:25:09
      Second.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:25:11
      Thanks.
    • Margaret MaliszewskiPlanning Manager
    • 01:25:12
      I'm sorry.
    • 01:25:13
      Actually, the minutes that we want to approve are November 6th.
    • 01:25:16
      Sorry, different dates there.
    • 01:25:18
      My mistake.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:25:20
      I'll move to approve that.
    • Taro MatsunoMember, Architectural Review Board
    • 01:25:25
      And I'll still second then I guess.
    • Chris HenningsenChair, Architectural Review Board
    • 01:25:29
      Oh, thank you.
    • 01:25:30
      I guess we'll put it to a vote.
    • SPEAKER_01
    • 01:25:33
      Okay.
    • 01:25:34
      Mr. Henningsen.
    • Chris HenningsenChair, Architectural Review Board
    • 01:25:36
      Aye.
    • SPEAKER_01
    • 01:25:36
      Mr. Hancock.
    • Chris HenningsenChair, Architectural Review Board
    • 01:25:39
      It's not here.
    • SPEAKER_01
    • 01:25:40
      I'm sorry.
    • 01:25:41
      Mr. Stoner.
    • Chris HenningsenChair, Architectural Review Board
    • 01:25:42
      Aye.
    • SPEAKER_01
    • 01:25:43
      Mr. Matsuno.
    • 01:25:45
      Aye.
    • 01:25:46
      And Mr. Van Der Werf.
    • 01:25:47
      Aye.
    • 01:25:47
      Thank you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:25:48
      All right.
    • 01:25:49
      Thanks a lot.
    • 01:25:51
      All right.
    • 01:25:52
      Are there any other items from staff or board members?
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:25:58
      I guess following up on the presentation from Mr. Pinnio, it sounded like Margaret, you might be asking County Council, you know, what status those representations in the application or the presentation might have and whether that might give us any basis to ask for any medication in the individual.
    • Margaret MaliszewskiPlanning Manager
    • 01:26:19
      I will ask that question.
    • 01:26:20
      I will go back and look at the preliminary plan again as well so we can just see where things started to shift.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:26:29
      Thank you.
    • 01:26:31
      The one other item I'll mention is I think folks are aware that the county is reviewing its cell phone personal wireless facility regulations based on the survey and
    • 01:26:43
      The study that's been done, there's a recommendation to significantly relax and allow administrative approval of increases in height up to 30 feet above trees.
    • 01:26:55
      No limit on the extent of antennas.
    • 01:26:59
      I have an open question I just sent to Bill Fritz just to ask
    • 01:27:04
      whether sites that were previously, well, entrance corridor sites that required ARB review to determine that there was appropriate screening, whether those would, under this ordinance, be administratively approval for greater height and number of towers.
    • 01:27:20
      So I think it might be worth, if that is the case in the current proposed legislation, are maybe meeting with planning and reviewing that.
    • 01:27:32
      And I think there is gonna be
    • 01:27:34
      Planning Commission meeting early next year.
    • 01:27:36
      I would appreciate if there is an impact to sites previously reviewed and approved by the board, well, reviewed, I would like to request that we discuss it and perhaps formulate a board position.
    • Margaret MaliszewskiPlanning Manager
    • 01:27:52
      Okay.
    • 01:27:54
      Thank you.
    • 01:27:56
      I'll look into that and get back to you.
    • Chris HenningsenChair, Architectural Review Board
    • 01:27:59
      Thanks.
    • 01:28:00
      Yeah, that will be interesting to see how that whole cell tower thing affects our input into that whole thing.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:28:11
      Certainly, there's about 30 years of, I guess, board and staff time invested in the current regime, which has preserved a good part of the visual character of the county.
    • 01:28:24
      I would just like to understand if there will be an impact to sites that we previously thought provided screening.
    • Chris HenningsenChair, Architectural Review Board
    • 01:28:31
      Thanks.
    • 01:28:35
      All right.
    • 01:28:39
      So next ARB meeting is scheduled for December 4th, 2023.
    • 01:28:44
      Are there any board members here who do not think they'd be able to attend that?
    • 01:28:55
      All right, I think it sounds like tentatively we have four for that one.
    • 01:29:01
      So in that case, this meeting is adjourned to the next meeting on December 4th, 2023.
    • 01:29:07
      And it is 2.30.
    • 01:29:11
      Thank you very much.
    • Dade Van Der WerfMember, Architectural Review Board
    • 01:29:13
      Thank you.